PJM Basics - Delivery Flashcards

1
Q

construction manager as advisor

A

The CM, an expert at managing construction budgets, schedules, and other processes, serves as an independent adviser to the owner throughout all phases of design and construction, consults on constructibility early on, does not build anything. Low risk for CM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

construction manager as agent

A

manages and administers the contracts between architect and contractor, hires them both. Good for inexperienced clients who do not want to be super involved. Low risk for owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

construction manager as constructor

A

also know as CM at risk, the CM takes the place of the contractor and builds the building.
Owner engages CM and Architect at the same time
Fast schedule and low risk for owner
CM is incentivized to drive up cost
final GMP is known by the end of SD
Architect must maintain stricter process of quality control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

traditional design bid build

A

architect creates contract docs, contractors bid a fixed price, and the lowest bidder wins
takes longer, costs less, less likely to be corruption, used in public projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

design build

A

arch and contractor are one business entity
fewer conflicts
less oversight of design quality
construction cost determined before design is complete
one contract
less risk for owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

negotiated select team project

A

sub category of desing bid build
bring the contractor in early in design process
contract to guarantee contractor a fixed profit
portions of project that are difficult to fabricate can begin earlier
high quality and high speed
more expensive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

bridged design build

A

architect and contractor are still a single entity but the owner may hire a separate design architect (also known as a bridging consultant) to make sure quality is maintained

low risk to owner but more expensive and takes longer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

cost plus fixed fee

A

contractor is selected after CDs
they receive a fixed profit
they are disincentivized to allow cost to ballon because they will not profit more
gives lots of flexibility for change of program or issues that come up on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

integrated project delivery

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

unit cost

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

cost plus fixed fee

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

guaranteed maximum price

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

stipulated lump sum

A

owner pays contractor one price to build everything in the contract
-best for projects with a well defined scope of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

time and materials

A

Contractors bill for all material costs and labor at an hourly rate
-helpful for projects with uncertain scope
-tracking costs is burdensome
-increase risk for owners (unless there is a not to exceed clause)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what would be a good contract method if the scope of work is well defined

A

lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what would be a good contract method if the scope of work is unclear?

A

time and materials

17
Q

what would be a good contract method if the project involves repeated materials?

A

unit price

18
Q

what would be a good contract method if the project has a fixed budget?

A

guaranteed maximum price

19
Q

what would be a good contract method if there is uncertainty in estimating?

A

cost plus fixed fee

20
Q

if the driving factor is scope?

A

cost plus fixed fee because contractor isn’t motivated to let costs balloon

21
Q

if the driving factor is time?

A

one that skips bidding

22
Q

if the driving factor is quality?

A

negotiated select team

23
Q

if the driving factor is cost?

A

design bid build

24
Q

what method poses less legal risk?

A

Design build because two of the main parties that sue are tied together

25
Q

what type of of projects limit risk?

A

Any method with a CM