Pg 4 Flashcards
If you have a contract with a contractor to build a house for $80,000, but he walked off the job halfway through, and then you made a second contract with a different contractor for $60,000 to finish the job, but you end up paying that contractor $90,000 because you feel bad since the contract isn’t profitable, what happens?
The extra $30,000 is not recoverable because the plaintiff was not contractually obligated to pay it. He can only recover the amount that he contracted for.
Also watch out, because technically the plaintiff hasn’t paid anything to the first contractor, so he wasn’t injured, he actually saved money. He isn’t injured until the cost to complete exceeds the original contract price.
If a contractor only does half of a job for you and then walks off, can he get quasi-contractual restoration?
The majority approach is that someone that willfully breaches a contract cannot recover in quasi-contract. So he would probably get nothing because he willfully breached by walking off the job.
What is the standard measure for defective performance by a contractor in a construction contract?
The cost to remedy the defect, unless it will be economically wasteful. In that case, then you only get the diminution in value caused by the defective performance [difference between the market price of the property without defects and the market price with defects]. To figure this out, the courts look at what the parties intended. Breach could come from workmanship or the materials that are used.
What is the question to ask when there is defective performance by a contractor in a construction contract?
Ask if the owner should get the cost to complete, or the difference in value between the work as promised and the work as performed
If there has been defective performance in a construction contract but the cost to complete would be economically wasteful, what happens?
The court has to determine whether the subjective affection of the owner for the intended performance has cultural relevance and isn’t just opportunistic. Disproportionality plays a big role and so does the avoidance of economic waste. Courts try to avoid unreasonable duplication of effort.
If the house that you contracted for was defectively built, but the cost to rebuild would be $100,000 where as the difference in the value of the house is only $10,000, what would a court probably do?
Likely will just give you the difference in value instead of allowing you to demolish the house because that would be wasteful. Economic waste is only allowed in the most extreme situations. But if the point of the contract was aesthetic or personal to the owner, courts don’t usually force the owner to just take the difference in value. The difference in value usually only happens when the defective performance involves trivial defects.
If the work that you had a contractor do required that he be licensed, and it turns out that he wasn’t, what can he recover on your contract?
He can’t recover anything
If a buyer or owner breaches a construction contract, how does that often happen?
- wrongful termination
– abandonment of the project
– barring the contractor from the worksite
– interfering with the contractor’s performance
– refusing to pay
What is the remedy that is given under the majority rule and the minority rule for when a buyer or owner breaches a construction contract?
– majority: gives the contractor the profit he expected to make on the contract plus costs that were expended to date
– minority: gives the contract price minus the cost to complete
– minority alternative: gives the price minus the cost saved
What is involved in the majority approach to when a buyer or owner breaches a construction contract?
The contractor gets the profit he expected to make on the contract plus any costs he expended up to that date. I.e.: if a contractor agreed to build a house for $100,000 and construction costs are $75,000, so he expected to make a $25,000 profit, if the owner breaches before any work is done, the contractor gets $25,000. But if he already finished half, he gets $25,000 for lost profit plus the costs that he spent up until that date which would be $50,000.
What is involved in the minority rule for when a buyer or owner breaches a construction contract?
This gives the contract price minus the cost to complete. So if the contract price was $100,000, and it would cost $25,000 to complete performance, then the recovery would be $75,000.
What is involved in the minority alternative approach for when a buyer or owner breaches a construction contract?
This gives the price minus the cost saved by not having to perform.
Are overhead calculations included in the remedy for when a buyer or owner breaches a construction contract?
Not usually, because they would be paid regardless of whether the contract was fulfilled, so they are not usually included.
If a buyer or owner anticipatorily breaches a construction contract, what happens?
- repudiation before any work is done: contractor gets his expectancy interest which is his lost profit [difference between the contract price and his cost to perform]
What is involved in the contract price for a construction contract?
The cost to do the construction and the profit to the contractor