Performance Variables Flashcards

1
Q

What does Budget at completion (BAC) mean

A

Total planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does Earned value or budgeted cost of work performed (EV or BCWP) mean

A

Fraction of the completed work in terms of the planned budget at a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the formula for

EV or BCWP

A

EV = BAC X (Work completed / Total work required)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does

Actual cost (AC or ACWP) mean

A

The money spent on the work until a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the formula for AC or ACWP

A

The sum of all the costs until a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does

Cost variance (CV) mean

A

The difference between what you planned to spend and what is actually spent until a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for CV

A

CV = EV – AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does

Cost performance index (CPI) mean

A

The work performed per actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the formula for CPI

A

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does

Planned value or budgeted cost of work scheduled (PV or BCWS) mean

A

The fraction of work planned to be completed at a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the formula for PV or BCWS

A

PV = BAC X (Time passed / Total schedule time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does Schedule variance (SV) mean

A

The difference between the work actually completed and the work planned to be completed at a given point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the formula for SV

A

SV = EV – PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does Schedule performance index (SPI) mean

A

The actual work performed per planned work performed in terms of cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the formula for SPI

A

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does Estimate to complete (ETC) mean

A

Estimate of what will be spent on the remaining project (or a project activity) based on the performance so far and the planned cost

17
Q

What is the formula for ETC

A

ETC = BAC – EV

18
Q

What does

Estimate at completion (EAC) mean

A

Estimate of what will be spent on the whole project (or a project activity) based on the performance so far and the planned cost

19
Q

What is the formula for EAC

A

EAC = ETC + AC

20
Q

What does To complete performance index (TCPI) mean

A

Calculates the efficiency: remaining work per remaining funds

21
Q

What is the formula for TCPI

A

(BAC – EV) / (BAC – AC)