Performance Obligation Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

In non-carrier cases, who has obligation to tender delivery?

A

Seller

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the contract presumption in carrier cases?

A

That the contract is a shipment contract

Seller generally only needs to put the goods in the possession of a carrier and make appropriate arrangements for them to be sent to buyer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the performance obligation in a destination contract?

A

Seller agrees to tender the goods at a particular destination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

F.O.B.

A

Free On Board is the delivery point

FOB sellers location = shipment contract

FOB buyer’s location = distination contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risk of Loss – Carrier Cases

A

Risk of loss shifts to buyer when seller has completed delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk of Loss – Non-Carrier Cases

A

If seller is a merchant, sellers bears the risk of loss until buyer takes possession

If seller is not a merchant, seller bears risk of loss until buyer tenders the goods (makes them available)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Pre-Existing Duty Rule

A

Promisor cannot provide consideration where that consideration is a duty that promisor is already obligated to perform

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a unilateral mistake?

A
  • When one party to the contract operates under a faulty assumption about material facts
  • The mistaken party’s obligation to perform is not excused, UNLESS,
    • the other party knew or had reason to know of the party’s mistake, or
    • the mistake was based on a clerical error
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a mutual mistake?

A

When both parties have labored under a common faulty assumption regarding the present facts

The contract is voidable by the disadvantaged party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Doctrine of Impossibility

A

RULE: excuses both parties from their obligations under a contract if the per- formance has been rendered impossible by events occurring after the contract was formed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Doctrine of impossibility requirements:

A
  1. objectively impossible performance; and
  2. the occurrence of the contingency must not be known to the parties at the time of contracting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Two types of impossibility

A
  1. objective impossibility
  2. Subjective impossibility
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When does objective impossibility occur?

A

When the performance under the contract becomes literally impossible because of circumstances beyond the control of the parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When does subjective impossibility occur?

A

when the performance under the contract becomes impossible because of some failure or fault on the part of the performing party. Under those circumstances, the performance obligation is not excused and will be considered as a breach of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When does doctrine of impossiblity not apply?

A
  1. Where the parties have allocated the risk of the contingency and provided remedial measures in the event of its occurrence; or
  2. Where events render performance only temporarily impossible (this will typically only suspend the obligations of the parties until the impossibility ends).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Categories of Impossibility

A
  1. destruction of the subject matter of the contract;
  2. death or incapacity; and
  3. illegality.
17
Q

Doctrine of Impracticability

A

RULE: a promisor may be excused from performance where unforeseen difficulties have made performance prohibitively expensive or otherwise extremely burdensome

18
Q

Requirements for showing that a contract is impractiable:

A
  1. the impracticability of the performance was caused by some unforeseen contingency;
  2. the risk was neither assumed nor allocated by the parties; and
  3. the increase in the cost of performance would be far beyond what either party anticipated.
19
Q

Frustration of Purpose Elements

A
  1. the party’s principal purpose in entering the contract is frustrated;
  2. there is substantial frustration; and
  3. non-occurrence of the event precipitating frustration was a basic assumption of the contract.
20
Q

What is an accord?

A

a contract under which the obligee promises to accept substituted performance in satisfaction of the obligor’s existing duty.

21
Q

What is satisfaction?

A

performance of the accord—will discharge the original duty.

22
Q

What happens if accord is breached?

A

If the obligee breaches the accord, the original duty is not discharged, but the obligor can seek specific performance of the accord (in addition to damages for partial breach).

23
Q

When does Anticipatory repudiation occur?

A

when, prior to the time that performance is due under the contract, a party announces his intention not to perform, or circumstances make such an intention reasonably clear to the aggrieved party.

24
Q

How is anticipatory repudiation established?

A
  1. a party’s definitive statement indicating that he will commit a breach of contract; or
  2. party’s voluntary or affirmative act that renders the party unable to perform or apparently unable to perform (e.g., the sale of the contracted-for item to a third party).
25
Q
A