Performance, Breach, and Discharge Flashcards
Non-conforming goods
The UCC allows a buyer to accept or reject non-conforming goods in whole or in party. In either event, buyer can recover damages for breach - even if there was an accommodation
Risk of Loss - hand delivery
If seller is a merchant, ROL is on seller until buyer takes possession
If seller is NOT a merchant, ROL is on seller until made available to buyer
Risk of Loss - carrier delivery
“shipment and destination contracts”
Shipment contract (FOB seller) - default; ROL is on seller until goods taken to carrier
Destination contract (FOB _) - ROL is on seller until goods get to buyer
Requirements Contract
If something interrupts deal but supplier acted in good faith, the supplier is excused
Modification
CL modification requires consideration for valid modification
UCC only requires good faith
Modification can be oral or written (unless UCC clause prohibits oral modification)
Mutual modification - valid so long as its fair and reasonable in light of unforeseen circumstances
Conditions - 3 Types
Condition Precedent - something must occur before contract to trigger obligation
Condition Concurrent - something must happen at same time as contract to trigger obligation
Condition Subsequent - something must happen after contract to trigger obligation
Exceptions to Conditions
Waiver
Bad faith
Avoiding forfeiture
Time (NOT) of Essence
Time is not of the essence unless a contract says such – if it does time is a condition
Non-Conforming Goods
If buyer receives non-conforming goods, they may:
- completely reject (in reasonable time)
- completely accept (requires payment)
- partially accept/reject
If seller had reasonable grounds to believe recipient would accept non-conforming goods OR delivers non-conforming good before due date: seller can fix delivery if he gives notice to cure and delivers conforming goods in reasonable time
Installment Contracts
If one shipment is non-conforming it does NOT constitute a total breach
Buyer can reject it but must give seller chance to cure if seller is capable
UNLESS it impairs the value of entire contract
Impracticability
If unforeseen circumstances makes contract SO expensive or difficult to perform, a party can argue its impracticable – must be MAJOR unforeseen changes
Impossibility
If contract is impossible for nayone to perform, obligation is discharged
EXCEPTIONS:
1) temporary impossibility
2) pre-preparation for setbacks (ex: bad weather)
Frustration of Purpose
If purpose of contracts no longer exists, party can be discharged from performance
Anticipatory Repudiation
Occurs when a party unequivocally refuses to perform before due date – other party can sue for breach immediately OR wait and see
Uncertainty is NOT unequivocal – party can demand assurances. If theres a response in reasonable time, the party must wait and see. If there is no response, the party can treat it as breach.
UCC requires assurances to be in writing and reasonable time for response is 30 days
Anticipatory repudiation can be retracted UNLESS: 1) party already sued, 2) party already accepted repudiation, or 3) party relied on repudiation