Performance and Breach Flashcards
What is the entire obligations rule?
Full performance
Cutter v Powell
Entire obligations rule
Sailor to be paid for services til end of voyage on completion but died before and widow got nothing
Sumpter v Hedges
Entire obligations rule
Ran out of money for building work, completed by D using C’s material. Could claim money back for material but not payment for work completed.
The entire obligations rule is mitigated when?
- severable obligations
- substantial performance
- new contract
- Law reform (frustrated contracts) act
Taylor v Laird
Severable obligations
Sailor paid per month so when left in 9th could claim for 8th’s pay
Williams v Roffey Bros
Substantial performance
completed 8 flats substantially so must be paid minus sum for defects/incomplete
Bolton v Mahadera
substantial performance
agreed to install heating/hot water
serious defects so pay nothing til defects cured
Christy v Row
new contract
coal to hamburg, but stopped by war
at request of cosignee ship elsewhere, so pay for coal delivered
Metcalfe v Britannia Ironworks
new contract
railways bars to be paid for after delivery
could not get there as route closed for winter, left elsewhere eventually delivered - no pay no new contract
frustrated contracts act
non-performance due to frustration such as Cutter v Powell then court may award just sum for valuable benefit conferred
right to terminate contract depends on nature of term breached
always condition
never warranty
if serious breach of innominate term
when is a term a condition?
statutory (and judicial) classification
intention of parties
express clarification
Arcos v E A Ronaasen & Son
statutory classification of condition
sale of goods act 1979 - has to conform to description
sale of wood staves - half inch thick
95% delivered were but still right to reject goods
Bunge v Tradax
judicial classification
required 15 days notice of intention to ship goods so could select port
5 days too late
held condition
Schuler v Wickman Machine
express clarification denied by courts as no loss
condition that visited 6 largest UK motor manufacturers every week, didn’t a couple of times out of 1,000s
contract terminated when failed to, denied by courts