Performance and Breach Flashcards
The Sale of Goods Act 1979, section 11
(2) a buyer may treat a breached condition as ground for repudiation or may elect to treat it as a breach of warranty
(3) breach of condition mean repudiation is available; breach of warranty means only damages; election does not make a condition a warranty it is a matter of construction
Treital’s definition of breach
A breach of contract is committed when a party without lawful excuse fails or refuses to perform what is due from him under the contract, performs defectively or incapacitates himself from performance
SOGA 1979 Section 12-15
Recognises and implements the difference between conditions and warranties
SOGA 1979 15A
A non-consumer can only get damages where a breach is so slight it would be unreasonable to reject the goods
Hong Kong Fir Shipping (1962) CA
Treital views this as a landmark case; ship must be seaworthy; ruled this is an innominate term where only actionable where the result of the breach was so fundamental it goes to the root of the contract/substantially deprives of the benefit (Lord Diplock); more flexible but less certainty
Bunge Corp v Tradax (1981) HL
There is an assumption in a contract where “time is of the essence” that time is always a condition
The Mihalis Angelos (1971)
Valued certainty over flexibility and rejected to apply the in nominate term rule; expected readiness to load clause was condition regardless of effect
Wickman v Schuler (1974) HL
Contract elected visiting factories as a condition but court says no on construction
Lombard V Butterworth (1987)
Time is of the essence always a term despite magnitude of the breach
Bettini v Gye (1876)
Opera singer 3 days late for rehearsal
Pussard v Spiers (1876)
Opera case is breach when a week late into season
Vital v Norelf (1996)
Exceptional circumstance where silence amounted to acceptance of rescission; “silence was pregnant with meaning” as conduct explicitly showed acceptance
Cutter v Powell (1795)
Second mate written agreement was an entire obligation so no part payment allowed
Simon v Hedges (1898)
Builder only reimbursed martial costs not cost for half of labour
Hoeing v Isaacs (1982) CA
The decoration work was defective but only allowed cost of repairs (£55) off price of complete contract