perforance and breach of contract Flashcards
breach of contract
a breach of committed when a party without lawful excuse fails or refuses to perform what is due to him under the contract
where do obligations in a contract come from?
Express Terms: Production specification
Implied Terms: Contracts between trader and consumers: A term that the good are satisfactory
Strict liability
default position in contract law - only have to prove that they didn’t do it
fault-based liability
take ‘reasonable care’ or ‘use reasonable endeavours’
what are the two basic remedies for breach of contract
damages and termination of contract
damages
an award of monetary compensation and the objective is to put the innocent party in the position as if the contract had been performed.
termination of contract
if the innocent party is entitled to terminate the contract because of a breach, they can effectively tear up the contract and refuse to perform or accept performance of future obligations. It is powerful and an advantageous remedy and it is used commercially
Is an innocent party always entitled to terminate the contract
No
condition precedent
something that must be done as a condition of the other party’s performance - something has to be performed before a contract price arises
entire obligations rule
a party must perform his entire obligation before receiving payment
severable obligations rule
party can receive payments at various stages of the contract
Cutter v Powell
Mr Powell engaged Mr cutter as a second mate on a ship and the contract provided for a high level of pay if Mr Cutter continues and does his duty from the port of Jamaica to the port of Liverpool. Mr Cutter died and his widowed wife wanted to claim for a proportion of his wages under this contract.. Courts held that the obligation to pay the contract price had not arisen has he didn’t finish the performance.
Law Reform (frustrated contract) act 1943 - where non-performance arises due to frustration (like in Cutter v powell) the court may award a ‘just sum’ in respect to the valuable benefit.
Taylor v Laird
Commander of ship hired for £50 a month, but he didn’t complete the voyage. Held that it was a severable obligation so he had to pay for the work he done
substantial performance doctrine
mitigates the harshness of the entire obligations rule. If the work is done and is regarded fit for the purpose, then the party is obliged to receiving his contractual price
Hoenig v Issacs
redecoration of flat for £750, minor defects totalling up to £55. Courts held that that the works were finished and the claimant was entitled to the full contract price, but defendant could set-off £55
Bolton v Mahadeva
Installation of central heating system for £564. System had serious defects and unfit for purpose so the customer not obliged to pay the contract price.
quantum merit
‘as much as it deserves’ - courts may award a sum of the benefit obtained by the other party if a contract has only been partly performed and the right to the price has not yet arisen. VERY RESTRICTIVE AND LIMITED
Anticipatory breach
after a contract is made, but before it was meant to be performed. Breach before the works are meant to start