PDF 1 Flashcards

1
Q

Is a schedule of when contractors and suppliers will be paid for the current progress of installed work

A

Contractor progress payment schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Are partial payments for work completed during a portion of a construction period, usually a month.

A

Progress payments or interim payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Referring to an obligation that arises from a document that has been signed or issued by the warrantor

A

Warranty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Summaries of the day’s events in the member’s own words. They are used to keep track of any daily work activity, conversations, observations, or any other relevant information regarding the construction activities

A

Diaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Keeps track of the regular activities on the job site such as phone logs, transmittal logs, delivery logs

A

Logs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Are more formal way of recording information on the job site. They contain information that includes the day’s activities, temperature and weather conditions, delivered equipment or materials, visitors on the site and equipment used that day.

A

Daily field reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Are required on a daily basis

A

Labor statements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Are needed for labor planning to complete a project in time

A

PERT CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Uses a third party mediator to resolve any disputes. The mediator helps both disputing parties to come at a mutual agreement. Thus process ensures that no attorneys become involved in the dispute and is less time-consuming

A

Mediation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Takes more time and money that a mediation. It takes place in an informal setting and involves some type of advisor or attorney that must be paid. The disputing parties may come to an agreement or the third party advisor may offer their advice. The agreement is non binding and can be broken.

A

Minitrial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Is the most costly and time-consuming way to resolve a dispute. Each party is represented by an attorney while witnesses and evidence are presented.

A

Arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The construction typically includes three parties:

A

Owner
Licensed designer
Builder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A contract which involves planning, design, and construction contract administration

A

Owner-designer contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A contract which involves construction

A

Owner-contractor contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

To provide construction advice to the designer, design advice to the constructor on the owner’s behalf and other advise as necessary

A

Construction manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describes the prevailing model of construction management, in which the general contractor is engaged through a tender process after designs have been compl by the architect or engineer

A

Design, bid , build

17
Q

Many owners - particularly government agencies - let put contracts know as

A

Design-build contracts

18
Q

In this type of contract, the construction team (known as the design-builder) is responsible for taking the owner’s concept and completing a detailed design before proceeding with construction.

A

Design-build contracts

19
Q

Is a fee-based service in which the construction manager is responsible exclusively to the owner , acting in the owner’s interests at every stage of the project

A

Construction cost management

20
Q

Is a delivery method which entails a commitments by the construction manager to deliver the project within a guarantee maximum price (GMP)

A

CM at-risk

21
Q

Can represent the owner by helping select the design and construction teams and managing their he design, helping owner stay within a predetermined budget

A

Agency CM

22
Q

Acts as a consultant to the owner in the development and design phases and as a general contractor during construction

A

Construction management

23
Q

Is a global term referring to the business relationship of a construction contractor, owner and architect

A

CM at-risk

24
Q

In which it signs contracts with incentives for early completion and penalties for late completion, and uses intense construction during longer periods of complete closure to shorten the overall project duration and reduce cost

A

Accelerated construction techniques