PcM Flashcards

1
Q

Name 3 Milestone dates

A
  1. Design phase milestones
  2. Construction Commencement
  3. Substantial Completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the AIA Form B101?

A

Standard Form of Agreement Between Owner & Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often do the AIA contracts get revised / updated?

A

Every 10 years on the 7’s (2007, 2017, 2027)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Cost of Work?

A

The Cost of Work is the cost of construction only. Does not include architects fee, land fee, lawyers fees etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name 2 consultants the owner typically engages

A

Geotechnical Engineer & Civil Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name 3 consultants the architect typically engages.

A

Structural Engineer, Mechanical Engineer & Electrical Engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What insurance does an architect need to carry?

A

Commercial general liability, automobile liability, workers compensation, employers liability & professional liability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is AIA G703?

A

Application and Certificate for Payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is AIA A201?

A

General Conditions of the Contract for Construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are 4 implied duties of an Architect?

A
  1. Cooperating with contractors.
  2. Not interfering with the contractors work.
  3. Giving relevant information to contractors.
  4. Assisting the owner in coordinating work.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the three conditions that must be met for an architect to be found negligent?

A
  1. A legal duty must be established between parties.
  2. It must be shown that the architect breached that duty.
  3. It must be shown that the breach of duty was the cause of damage or injury.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are three defense of claims?

A
  1. Betterment
  2. Statute of Limitations.
  3. Statute of Repose
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Betterment?

A

If a change order arrived at the fault of the Architects mistake, the architect can claim the owner would have had to pay for the originally intended outcome therefore the architect should only pay for the costs acquired by making the change later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Statute of Limitations?

A

Sets a time limit within which a claim can be made. Each state has its own statute of limitations.
Typically begins at the date of substantial completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Statute of Repose?

A

A set time limit in which a claim can be made, typically shorter time period than statute of limitation and does not begin until the problem is first discovered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is AIA Document A201?

A

General Conditions of the Contract for Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the Cost of Work?

A

The Cost of Work is the cost of construction only. Does not include architects fee, land fee, lawyers fees etc.

18
Q

Name 2 consultants the owner typically engages

A

Geotechnical Engineer & Civil Engineer

19
Q

Name 3 consultants the architect typically engages.

A

Structural Engineer, Mechanical Engineer & Electrical Engineer.

20
Q

What insurance does an architect need to carry?

A

Commercial general liability, automobile liability, workers compensation, employers liability & professional liability.

21
Q

What is AIA G703?

A

Application and Certificate for Payment

22
Q

What is AIA A201?

A

General Conditions of the Contract for Construction.

23
Q

What are 4 implied duties of an Architect?

A
  1. Cooperating with contractors.
  2. Not interfering with the contractors work.
  3. Giving relevant information to contractors.
  4. Assisting the owner in coordinating work.
24
Q

What are the three conditions that must be met for an architect to be found negligent?

A
  1. A legal duty must be established between parties.
  2. It must be shown that the architect breached that duty.
  3. It must be shown that the breach of duty was the cause of damage or injury.
25
Q

What are three defense of claims?

A
  1. Betterment
  2. Statute of Limitations.
  3. Statute of Repose
26
Q

What is Betterment?

A

If a change order arrived at the fault of the Architects mistake, the architect can claim the owner would have had to pay for the originally intended outcome therefore the architect should only pay for the costs acquired by making the change later.

27
Q

What is Statute of Limitations?

A

Sets a time limit within which a claim can be made. Each state has its own statute of limitations.
Typically begins at the date of substantial completion.

28
Q

What is Statute of Repose?

A

A set time limit in which a claim can be made, typically shorter time period than statute of limitation and does not begin until the problem is first discovered.

29
Q

What is AIA Document A201?

A

General Conditions of the Contract for Construction

30
Q

What is the Cost of Work?

A

The Cost of Work is the cost of construction only. Does not include architects fee, land fee, lawyers fees etc.

31
Q

Name 2 consultants the owner typically engages

A

Geotechnical Engineer & Civil Engineer

32
Q

Name 3 consultants the architect typically engages.

A

Structural Engineer, Mechanical Engineer & Electrical Engineer.

33
Q

What insurance does an architect need to carry?

A

Commercial general liability, automobile liability, workers compensation, employers liability & professional liability.

34
Q

What is AIA G703?

A

Application and Certificate for Payment

35
Q

What is AIA A201?

A

General Conditions of the Contract for Construction.

36
Q

What are 4 implied duties of an Architect?

A
  1. Cooperating with contractors.
  2. Not interfering with the contractors work.
  3. Giving relevant information to contractors.
  4. Assisting the owner in coordinating work.
37
Q

What are the three conditions that must be met for an architect to be found negligent?

A
  1. A legal duty must be established between parties.
  2. It must be shown that the architect breached that duty.
  3. It must be shown that the breach of duty was the cause of damage or injury.
38
Q

What are three defense of claims?

A
  1. Betterment
  2. Statute of Limitations.
  3. Statute of Repose
39
Q

What is Betterment?

A

If a change order arrived at the fault of the Architects mistake, the architect can claim the owner would have had to pay for the originally intended outcome therefore the architect should only pay for the costs acquired by making the change later.

40
Q

What is Statute of Limitations?

A

Sets a time limit within which a claim can be made. Each state has its own statute of limitations.
Typically begins at the date of substantial completion.

41
Q

What is Statute of Repose?

A

A set time limit in which a claim can be made, typically shorter time period than statute of limitation and does not begin until the problem is first discovered.

42
Q

What is AIA Document A201?

A

General Conditions of the Contract for Construction