PCIS Group Isolations Flashcards

1
Q

Group 1 Isolation Signals

A
(Main Steam)
RWL LLL  ≥ -113”
Vacuum Low ≥ 8” Hg
MSL Low Pressure ≥ 835#
MSL High Flow ≤ 142.7%
MSL High Area Temp ≤ 195°F
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Group 2 Isolation Signals

A

(PC Priorities)
RWL L ≥ +3”
DW High Pressure ≤ 1.84#

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Group 3 Isolation Signals

A
(RWCU)
RWL LL ≥ -42”
RWCU F/D High Inlet 140°F
SLC Initiation
RWCU High Flow ≤ 191%
RWCU Area Temp ≤ 195°F
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Group 4 Isolation Signals

A

(HPCI)
HPCI Low Steam Supply Pressure ≥ 107#
HPCI High Steam Flow ≤ 250% w/ 6 sec TD
HPCI Area Temp ≤ 195°F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Group 5 Isolation Signals

A

(RCIC)
RCIC Low Steam Supply Pressure ≥ 61#
RCIC High Steam Flow ≤ 288% w/ 6 sec TD
RCIC Area Temp ≤ 195°F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Group 6 Isolation Signals

A

(RB)
RWL LL ≥ -42”
RB H&V High Rad ≤49 mrem/hr
DW High Pressure ≤1.84#

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Group 7 Isolation Signals

A

(Fuel Failure)
RWL LLL ≥ -113”
MSL HI HI Rad ≤ 3x normal full power background

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Group 1 Actions

A

Closes MSIVs and MS drain valves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Group 2 Actions (RHR)

A

Isolates RHR Shutdown Cooling flow path
Isolates RHR Injection Check Valve bypass valve
Isolates RHR to Radwaste and sample valves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Group 2 Actions (Other Than RHR)

A
Isolates DW floor and equipment drains
Isolates PC Nitrogen supply
Isolates steam supply to AOG
Initiates TIP withdrawal signal
Isolates supply and return valves to DW vent monitor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Group 3 Actions

A

Isolates RWCU system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Group 4 Actions

A

Trips HPCI turbine
Isolates HPCI SS line
Closes HPCI SP suction
Isolates HPCI exhaust line drains

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Group 5 Actions

A

Trips RCIC turbine

Isolates RCIC SS line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Group 6 Actions

A
Isolates PC vent and purge system
Trips RB ventilation fans
Isolates RB ventilation system
Isolates Recirc MG Set ventilation
Starts SGT system
Sends open signal to REC critical loop isolation supply valves
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Group 7 Actions

A

Isolates Recirc Loop sample line