Pasulj master Flashcards
Which of the following should be done during the Sprint Review?
A) Communication of the project progress
B) Discussion of the Scrum process, and how it was used during the Sprint
C) Revision of the technical practices
D) Demonstration of the Increment
AD
The Product Owner determines the number of items that should be selected for each Sprint.
T/F
F
Which of the following best describes the Product Backlog?
A) It provides information required for the design phase of the project
B) It contains all the tasks required for the project
C) It grows and change as more is learned about the project
D) It’s a baseline for the change management process
C
How can security concerns be addressed in Scrum? (Choose 2 answers)
A) They can be outsourced to a department responsible for security
B) They can be added to the Definition of Done
C) They can be added to the Product Backlog
D) They can be handled in a separate Sprint dedicated to security
BC
When can the composition of the Development Team change?
A) After each release
B) Whenever needed
C) Not during the Sprints
D) The composition of the team should not change
C
The Scrum Master has a lot of unresolved issues. Which three of the following actions can be taken to facilitate it?
A) Inform management of the impediments and their impact
B) Prioritize the issues and work on them in order
C) Consult the Development Team
D) Ask the senior management for help
E) Escalate the issues to the right person
ABC
Which is NOT a Development Team responsibility?
A) Optimizing the work required for Sprint Backlog items
B) Resolving internal team conflicts
C) Selecting the Product Owner
D) Measuring the performance of the Sprint
C
Who adds new work to the Sprint Backlog during the Sprint?
A) The Product Owner
B) The Product Owner and the Development Team together
C) The Development Team
D) The whole Scrum Team together
E) The Scrum Master
C
When is a Sprint canceled?
A) When the Development Team finds it necessary
B) When the Product Owner determines it makes no sense to finish it
C) When the infrastructure and tools are not ready for the whole project
D) When the Scrum Master decides to
B
What’s the main responsibility of testers?
A) They help the team incorporate the test driven development practice
B) They verify the programmers output
C) There’s no tester role in Scrum
D) They proactively verify the programmers output
E) They find bugs
C
What’s the timebox for a complete Sprint Planning meeting? A) 6 hours for a one month Sprint B) 8 hours for a one month Sprint C) 8 hours for a two week Sprint D) 6 hours for a two week Sprint
B
Who should know the most about the project performance? A) The Product Owner B) The Scrum Master C) The Scrum Team D) The Development Team E) The Project Manager
A
When is a Sprint Backlog item considered complete?
A) When the Sprint is over
B) When everything is done based on the Definition of Done
C) When the user acceptance tests are done
D) When all of its tasks are complete
B
While the Sprint Planning is progressing, the Development Team has realized that they don’t have enough resources to complete all the selected Sprint Backlog items. Which two of the following is usually the best action?
A) Inform the Product Owner and start the development
B) Hire more developers
C) Remove some of the items from the Sprint Backlog
D) Work overtime
AC
Scrum Teams should normalize their estimations, so that management can measure and compare their performance.
T/F
F
Which of the following best describes Scrum?
A) A methodology for software development
B) A framework for the development of complex products
C) A practical project management methodology
D) A practical and modern project management standard
B
Which 2 of the following are true about the Product Owner?
A) Can be influenced by a committee
B) Is accountable for prioritizing the Product Backlog items
C) Should be dedicated to one project
D) The role can be played by a committee
AB
Which of the following is a right action from the Scrum Master in response to a Product Owner who has problems managing the Product Backlog?
A) Extend the Sprint, so that the Product Owner has more time ordering items
B) Ask the customer to order the items instead of the Product Owner
C) Help the Product Owner order the items
D) Ask the Development Team to help the Product Owner understand the dependencies among items to be used in ordering them
C
The Sprint Review is:
A) An opportunity for improving the Scrum processes
B) An opportunity for inspection and adaptation
C) An opportunity for reviewing the viability of the project
D) An opportunity for receiving approval for the work done
B
How is budgeting done in Scrum?
A) Ideally revised each Sprint to ensure value is being delivered
B) Usually every day
C) Scrum doesn’t need the traditional budgeting system
D) Budgeting is very simple and limited to the run cost (time and material)
A
The customer wants the Development Team to add a very important item to the current Sprint. What should they do?
A) Refer the customer to the Product Owner
B) Reject the request
C) Replace an item in the current Sprint Backlog with the new one
D) Add the item to the Product Backlog
E) Add the item to the current Sprint Backlog
A
When the Scrum Team becomes mature enough, it doesn’t need a Scrum Master anymore.
T/F
F
When should a Sprint Goal be created? A) In the beginning of the project B) In the Sprint Planning meeting C) Any time during the Sprint D) It’s not mandatory E) In the previous Sprint Retrospective
B
What does it mean for a Development Team to be cross-functional?
A) The team includes not only programmers, but also testers, architects, UI designers, etc.
B) All the Development Team members should be cross-functional individuals.
C) The team should collaborate with all functional units
D) The developers should work closely with business analysts, architects, and testers external to the team.
A