Part 2 Flashcards

1
Q

What are the three distinct aspects of cost according to Woodward (1997)?

A

Project total cost, cost as a measure of progress, and cost control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the two main methods of cost planning?

A

Costing a design and designing to a cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of cost planning?

A

To establish more detailed project costs as the design develops. It starts with cost per unit benchmarks, then derives figures per square meter, followed by an elemental cost plan, and finally a detailed bill of quantities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are value engineering and value management?

A

Techniques to ensure the client gets “value for money”. Value engineering identifies unnecessary costs partway through design.

Value management ensures the proposed project is the correct solution at the beginning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How can cost be used to measure project progress when steady-state production is not possible?

A

By using S-curves and costed bar charts to track actual vs planned costs over time. This is possible because cost information is readily available even if units of output are not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is risk management critical for project success?

A

Because all projects involve change, and change is inherently risky. Risks must be identified and managed proactively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are some key sources of risk in construction projects?

A

Ground conditions, permissions/approvals, interdependencies between activities, site safety, quality of work, availability of labour and materials, weather, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the main steps in the risk management procedure?

A

1) Identify and classify risks

2) Analyse likelihood and impact of risks

3) Respond to risks using the “4 Ts” - Treat, Tolerate, Transfer, Terminate

4) Monitor risks and refine assessments over time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a risk register and why is it important?

A

A risk register is an evolving document that captures identified risks, their analysis, response plans and owners. It is critical for tracking and communicating about project risks over time as they change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the “4 Ts” of risk response?

A

Tolerate (accept the risk), Treat (reduce the risk to an acceptable level), Transfer (pass on via contract or insurance), Terminate (avoid the risk entirely).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who are considered project stakeholders?

A

Any actor that will incur (or perceive they will incur) a direct benefit or loss as a result of the project. This includes both those contracted to the project (internal stakeholders) and those impacted by it (external stakeholders).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the four main stages of the stakeholder management process?

A

1) Identify potential stakeholders 2) Analyse their interests, influence and likely responses 3) Plan stakeholder engagement 4) Manage stakeholder relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some key principles of effective stakeholder management according to the APM?

A

Communicate, consult early and often, plan thoroughly, focus on relationships not just process, compromise, and take responsibility. Understand that it is challenging but critical.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the main categories of internal and external project stakeholders?

A

Internal: project owner, project professionals, suppliers/contractors, customers.

External public: local/national authorities, the public. External private: interest groups, trade/industry, media.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are some of the key benefits of proactive stakeholder management?

A

Increased trust and certainty, robust risk management, greater awareness of issues, more innovation and alignment with strategic priorities. It reduces uncertainty, reactive planning and conflict.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is project governance?

A

The oversight function aligned with the organisation’s governance model that spans the entire project lifecycle. It ensures projects “do the right things and do them right.”

17
Q

Why is project governance important?

A

It provides a clear framework for responsibility, accountability, stakeholder management, issue resolution, information dissemination, resource provision and timely decision-making to support project success.