Other MEE Rules Flashcards

1
Q

Damages in construction contracts

A

In construction contracts, the general measure of damages for a contractor’s failure to begin or to complete a building project is the difference between the contract price and the cost of construction by another builder, plus any progress payments made to the breaching builder and compensation for the delay in completing the construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Consequential damages

A

Actual damages can be either direct or consequential. Consequential damages are a direct result of the breach but need not be the usual result of the breaching party’s conduct. Instead, consequential damages need only be a reasonably foreseeable result of the breach given the parties’ specific circumstances. For consequential damages to be recoverable, they must have been reasonably foreseeable to the breaching party.

Damages are foreseeable if they were a natural and probable consequence of breach, if they were “in the contemplation of the parties at the time the contract was made,” or if they were otherwise foreseeable. Consequential damages do not concern the value of the lost performance due to breach, but there must be a causal link between the breach and the consequential damages for them to be recoverable. And the plaintiff must prove the dollar amount of consequential damages with reasonable certainty not speculatively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Restitution

A

When a plaintiff confers a measurable benefit on a defendant and the plaintiff has a reasonable expectation of compensation, it would be unfair to permit the defendant to receive the benefit without compensating the plaintiff. In this case, the court can permit the plaintiff to recover the value of the benefit as restitution to prevent this unjust enrichment. (Although this type of action is often characterized as based on an implied-in-law contract or a quasi-contract, quantum meruit does not depend on the existence of a contract.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Expectation damages

A

Compensatory damages are meant to compensate the non-breaching party for actual economic losses. Expectation damages are intended to put the non-breaching party in the same position as if the contract had been performed. Expectation damages must be calculated with reasonable certainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly