OP-2 Flashcards
who reviews the OP-2 annually
POC Branch
Who can take action in an emergency
anyone can
What is an EROF form
A form filled jointly by workers and the operations supervisor for the authorization process of equipment outages.
A statement from operations supervisor that states to work on energized equip without a clearance is a?
OK to work
A person who is authorized to give ok’s to work and authorize clearances is a
Operations supervisor
a workers lock box sign on/off sheet is
a written method to account for all workers on a clearance
Who has the authority to stop work
anyone
Who is responsible for updating and reviewing the interpretation of the attachments contained in OP-2
the POC branch
whos resolves any conflicts with the procedures and actual operation practice of OP-2
POC manager
what will contractors and unqualified workers be required to have when working around equipment
OP-2 Awarness
an exception can only be approved by
Branch managers and division managers
Bracket grounds will be accounted for on what form
EROF
The only documenting that will be done about switching will b done on what form
switching order form
any equipment above 600 volts needs how many switch persons
2
what is the correct way to check if a switch is turned of when deenergizing
check the position indicator not the lights on the face of the breaker panel
Any questions about the switching instructions should be?
Brought to the attention of the operations supervisor before starting
If there is any issues the switch person finds what should they do
They shall not proceed and re-check with the operations supervisor
operation locks on clearances are what when switching applications
Red