ALL general switching orders that are considered non-rotation shall have a unique system generated number assigned.
TRUE
EACH field division shall devise an appropriate training and testing program that is unique to that field division’s needs in order to certify its employee as workers. operations supervisors and switchpersons
false
a “worker” as defined by op-2
the person who has the responsibility for performing the work authorized
Immediately after the Clarence Holder has reported on the clearance the contractors representative shall walk the clearance with the clearance holder and visually check the clearance limits
True
Per OP-2 when the thrust bearing oil pump must be made operational to rotate a main unit shaft for alignment purposes exception procedure may be applied
True
And equipment request order form should’ve reflect if the placement of grounds will be required
True
The Safe clearance procedure describes the methodology to be followed in requesting ,placing ,issuing ,transferring and removing and releasing a clearabce
True
Clearance points that utilize a double blocking arrangement will result in overlapping clearance limits and is not permissible in accordance with OP-2
False
The use of yellow and black barricade tape
Shall be installed and removed by the worker authorized to perform the work
Tie wrap is used as means of attaching tags with minimum unlocking strength of no less than 50 pounds
True
Under certain circumstances when working on circuits of less than 600 V. A special conditions tag can be used for the workers protection and to describe the work authorized
False
According to OP-2 to the term low-voltage means a nominal voltage of 4160 V or less
False
When making corrections on the switching order form
Maybe made with a single line through entry initialed by the operation supervisor making the correction
The workers card is the responsibility of all workers working under the clearance
True
Should an unqualified person be allowed to enter a dangerous area that is barricaded off without an escort
No
When releasing a clearance
All of the above
Except for interconnected system clearances if protective grounds or noted on the equipment request order form the electricians will be the first to sign onto the clearance and the last to sign off
True
Only an authorized a qualified person can take action in an emergency
False
Only an authorized and qualified person can take action in an emergency
False
If a worker switch person or operations supervisor fails this exam he/she may be removed from or will not be added to the list of authorized personnel
True