True or False:
Project charter should include detailed schedule of the project
False
True or False:
Fishbone is a diagramming technique to show causes of an event
True
True or False:
Risk avoidance is mostly used for the high risks
True
True or False:
Project management office (PMO) is responsible for scheduling of the projects
False
True or False:
Dedicated project teams are mostly common in the functional organizations
False
True or False:
Project charter should include the list of project team members
False
True or False:
WBS should have at least three levels
False
True or False:
Dummy activity is used in ADM method to satisfy all the activity consequences
True
True or False:
S-curve is used to show the earned value
False
True or False:
Portfolio usually consists of programs and projects
True
A project?
a) has a short duration
b) results is tangible outcome
c) is unique
is unique
RBS is defined in:
a) the risk management planning stage
b) the risk identification stage
c) the risk qualitative analysis stage
d) the risk quantitative analysis stage
the risk management planning stage
In an integrated joint venture:
a) collaborate in all phases of a single project
b) collaborate in all phases of a group of projects
c) partners take joint responsibility for the project
d) partners are responsible for plan their own portion of the work
partners take joint responsibility for the project
Owner has the highest level of control in: (1 mark)
a) Design-build
b) Design-bid-build
c) CM at risk
d) Turnkey
Design-bid-build
A structured communication technique, carried out in two or more rounds, designed to
gather information from a panel of experts
a) Pareto diagram
b) Root cause analysis
c) Ishikawa technique
d) Delphi technique
Delphi technique