OCEs/Cost Plans Flashcards
Whats the difference between Life Cycle and Whole Life Costing
Life Cycle is Cradle to Grave (Construction, Maintenance, Operation, Demolition)
Whole Life is the above plus client costs like financing and land acquisition
What headings of costs go into a Cost Plan?
Construction works
Preliminaries
OH&P
Out of Hours
Phasing
Fees
Risk
Inflation
What are the different methods of OCE
Floor Area Method
Functional Unit Method
Elemental Method
What is the Elemental Method of an OCE?
Benchmarked off of other projects, broken down by element usually on a sqm or sqft
Where do you find the information required to create each Cost Plan?
Appendix C of NRM 1
What information do you need for an OCE?
Site information
Building details (use, size)
Enabling/decanting
Programme
When do you decide a cost limit?
Stage 1 - OCE
What is a Cost Limit?
The maximum budget for a project
What is the formula for indices
(New-Old)/Old