(NTB updated w/formual) Unit 5 - Project Monitoring, Controlling and Closing Flashcards

1
Q

Describe the bare-bones process a PM uses to monitor current progress against project baselines.

A
  1. Monitor
  2. Analyze
  3. Propose Changes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 5 stages of team development?

A
  1. Forming
  2. Storming
  3. Norming
  4. Performing
  5. Adjoruing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are 5 Baselines the PM should be monitoring during the project?

A
  1. Project Scope Baseline
  2. Project Schedule Baseline
  3. Project Cost Baseline
  4. Project Risk
  5. Project Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 4 steps of the Project Change Management Process?

A
  1. Identify Change
  2. Evaluate Change
  3. Decision
  4. Communicate Change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 4 Principles of Quality Management?

A
  1. Quality Management
  2. Quality Assurance
  3. Quality Control
  4. Quality Audit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Quality management?

A

The process of identifying the requirements and how they will be measured

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Quality Assurance?

A

The Process of validating that the requirements and measurements are appropriate for the project environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Quality Control?

A

The process of monitoring and changing project execution to ensure that activities are being executed as planned
and will result in meeting the requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Quality Audit?

A

Rigorous reviews of the project performance. completed by groups of experts outside of the project team, such as
a company’s quality assurance (QA) department or an outside consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What 4 Components make up “Earned Value management”?

A
  1. EV (Earned Value)
  2. PV (Planned Value)
  3. AC (Actual Cost)
  4. BAC (Budget at Completion)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is EV?

A

Earned Value

–Dollar value of all work completed to date
–Based on the baseline budgeted cost of each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is PV?

A

–The dollar value of all work scheduled to have been completed to date
–Based on the baseline schedule and the calendarized baseline budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is AC?

A

–Total dollar value of costs incurred to date–Includes work and invoices already paid as well as any expenses that have been incurred but not yet invoiced or paid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is BAC?

A

–Approved total baseline budget approved for the completed project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is CV?

A

Cost Variance

  • compares the difference between the EV and the AC to determine if the project is meeting its budget expectations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the formula for CV?

A

CV = EV − AC

17
Q

What is SV?

A

Schedule Variance

compares differences between the EV and the PV to determine if the project is meeting its schedule expectations or if there is a variance.

18
Q

What is the formula for SV?

A

SV = EV − PV

19
Q

What is Negative Variance?

A

A negative value for SV or CV
* indicates that the project is behind in that measure of variance.

20
Q

What is Positive Variance?

A

Positive value
* indicates that the project is ahead in that measure of variance.

21
Q

What does a CV or SV value of 0 mean?

A

that there is no variance, and you are right
on track.

22
Q

What is CPI?

A

Cost Performance Index

23
Q

What happens during the “Closeout” phase of a project?

A

project documents indicate that the project has been completed and
that the project sponsor or customer agrees with and approves of the outcomes.
* Finalizes all project activities completed across all phases of the project to formally close the project and transfer the completed or canceled project as appropriate
* Purpose is to assess the project, ensure completion, and derive any lessons learned and best practices to be applied to future projects

24
Q

What are 5 activities that take place during the “closeout” phase of a project?

A
  1. Receiving formal acceptance of project deliverables (client acceptance)
  2. Creating a vendor-closing checklist
  3. Releasing project team members
  4. Documenting reasons for project termination
  5. Conduct lessons learned review
25
Q

What are 4 questions to ask during the “lessons learned” review?

A
  1. What did we do right?
  2. What can we do better?
  3. What went wrong?
  4. How can we prevent what went wrong then from going wrong next time