NERC TEST QUESTIONS Flashcards
A transmssion operator must maintain adequate reactive power resources to
protect voltage levels under contingency conditons
A sudden enexpected change in weather conditions occurs, Which of the following pieces of data would be most vauluable in anticipating the impact of this weather change on load magnitude?
similar weather data from the previous year
The transmission media in a power line carrier PLC telecommunications system is
a power transmission line
BA “a” sells 100MW to adjacent BA “b”. The ramp is 10 minutes symmetrical accross the hour. The schedule begins at 1300 ends at 1400, How much energy is actually transferred in the period from 1255 to 1405?
100 mwh
A system has experienced a blackout from a major storm that has moved through a large portion of the interconnection. All are true except
ok..
if a generator is supplying reactive power the generator is operating in a condition called
over excited
Maintenace personnel are working in your control center when their actions cause a computer system failure. In the event that your BA’s AGC system fails you would
assume manual control of the generation control process.
All BA’S and TO’s must participate in
the interregional security network (ISN)
An RE has requirements that each of its member systems shed 10% of their load at 59.3hz, 10% at 59.0 hz, and 10%at 58.7 hz. If a member system has 10, 000MW of load and the frequency declines to 59.8 hz, how many MW of load would the member system shed?
0 MW
When closing a circuit breaker between two systems (or islands) thru a synchcheck relay, the circuit breaker will close when?
the two systems are within the relay settings
a mid-week, non holiday time period from 2100 to 200 is an ___hour in TRE.
on peak
A power line carrier (PLC) telecommunication system uses what element as the carrier of the communication signal?
three phase conductors
following the operation of a system’s automatic underfrequency load shedding plan, if overfrequency is likely, the amount of load shedding should be reduced or ___should be provided.
automatic overfrequency load restoration
If a 345 to 115kv transformer has 1000 amps and 500MW flowing into its hi side, what is the current and MW flowing out of the low side?
3000 amps and 500 MW
Who routes tag information
Interchange Authority
Who ensures planning reserves
resource planning
Who monitors IROLS
reliabilty coordinator
Who secures energy
load serving entity
Who Administers Tarriff
transmission service provider
Who coordinates activities of TP’s and RP’s
planning coordinator