NEC Terms Flashcards

1
Q

Accepted Programme

A

Programme in contract data or last accepted programme by PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Completion

A

Done all work in the WI & corrected notified Defects which would have prevented the Employer from using the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Works Information

A

Specifies and describes the works and states any constraints on how contractor provides the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Manager

A

Appointed and acts on the behalf of the Employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Supervisor

A

Check for compliance with the WI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Early Warning

A

A communication to the other party as soon as they become aware of a matter which has the potential to increase total price, delay completion, delay a Key Date or impair the performance of the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Risk Register called in NEC4?

A

Early Warning Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Items to include on programme

A

Access dates, completion dates, key dates, order and timing of the works, float, TRA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reasons for not accepting programme

A

1) Plans not practicable, 2) Does not show the information the contract requires, 3) Not realistic, 4) Does not comply with WI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How long does PM have to accept/reject programme?

A

2 weeks, with obligation to meet within 1 week. If PM fails to respond its a CE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Clause 32 programme

A

Is the revised programme - actual progress, implemented CEs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Defect

A

Part of the works which is not in accordance with the WI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Defect Date

A

Period identified within contract data for which Contractor is responsible for defects - 104 weeks - 2 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Defect Correction Period

A

Period within which individual defects should be corrected - 2 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost components of defined cost

A

People, Equipment & plant, Materials, Charges, Manufacture & fabrication, Design, Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Disallowed Costs (Option C-F)

A

not justified by contractors accounts, incurred because contractor did not give EW, correcting defects,

17
Q

Compensation Event

A

Matters that occur that are not the Contractor’s risk under the contract and should not of been allowed for within their tender price

18
Q

Stage of CES

A

1) Notification, 2) Quotation, 3) Assessment, 4) Implementation