NEC Articles/Sections Flashcards
690
PV systems
705
Interconnections (includes AC microgrids)
706
Energy Storage Systems
710
Standalone systems
712
Direct current microgrids
100
Definitions
110
Requirements for general installations
110.14 (C)
Terminal temperatures
110.16
Arc-flash hazard warning
110.21 (B)
Field applied hazard markings (ANSI references)
110.26 (A) (1)
Working spaces
NEC 110.28
Enclosure selection (NEMA)
200
Use and identification of grounded conductors
200.6
6AWG and smaller can be marked white for PV
230
Services
240
Overcurrent protection
240.4 (D)
Small conductor rule
240.6
Standard fuse and breaker sizes
250
Grounding and bonding
250.52
Electrodes
250.52 (A)
Electrodes permitted
250.53
Grounding electrode system installation
250.66
AC GEC
250.166
DC GEC
250.122 (Table)
ECG (ac and dc)
300.5 (Table)
Minimum cover requirements (how deep to bury conduit)
300.7
Raceways exposed to different temperatures
310
Conductors for general wiring (wire sizing)
310.15 (B) (2) (a)
Ambient temperature correction factors
310.15 (B) (3) (a)
Adjustment for >3 current carrying conductors in conduit
310.16
Conductor ampacity in raceway cable or buried
310.17
Conductor ampacity in free air
314
Junction boxes, enclosures, outlets
320-362
Raceways (conduit) and cables
330
Metal-clad: MC cable
334
Non-metallic sheathed cable: NM, NMC and NMS
338
Service entrance cable: SE, USE (USE-2)
342
Intermediate metal conduit: IMC
344
Rigid metal conduit: RMC
352
Rigid PVC
352.44
Expansion joints required for rigid PVC if > 14” expansion
356
Liquid tight flexible non-metallic conduit: LFNC
358
Electrical metallic tubing: EMT
Chapter 4
Equipment for general use
480
Batteries (also in articles 706, 710, and 712)
Chapter 6
Special equipment
690.2
Definitions
690.7
Maximum voltage
690.8
Circuit sizing and current
690.9
Overcurrent protection
690.11
Arc-fault protection (dc)
690.12
Rapid shutdown
690.13-.15
Part III Disconnecting means
690.31-.34
Part IV Wiring methods
690.41-.50
Part V Grounding
690.51-.56
Part VI Marking
Article 691
Large-scale photovoltaic (P) electric power production facilitv
Chapter 7
Special conditions
705.10
Directory
705.12
Point of connection
705.12(A)
Supply-side
705.12(B)
Load side
705.12(B)(2)(1)
Feeders
705.12(B)(2)(2)
Taps
705.12(B)(2)(3)
Busbars
705.12(B)(2)(3)(a)
100% rule
705.12(B)(2)(3)(b)
120% rule
705.12(B)(2)(3)(c)
Sum rule (loads + breakers < or = busbar)
705.31
Location of supply-side connection disconnect < 10 ft
705.32
Connect to supply-side of ground-fault protection (with exception)
Chapter 9 Table 1
Percentage cross-section of conduit
Chapter 9 Table 4
Internal area of conduit for wires
Chapter 9 Table 5
Dimensions of conductors
Chapter 9 Table 8
Conductor properties (used for voltage drop calculations)
690.31 (D) (1)
PV DC circuits entering into a building must be in conduit