Multiple Choice Flashcards

1
Q

Drawings and specifications are the output of what stage of a project

a. Concept and feasibility
b. Procurement
c. Engineering and design
d. Startup and implementation
e. None of the above

A

c. Engineering and design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Traditionally, concept and feasibility studies are handled by the…

a. Owner
b. Architect
c. Contractor
d. Subcontractor

A

a. Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The term fast track means

a. Design/build
b. Construction starts before the design completes
c. Cost plus fixed fee
d. None of the above

A

b. Construction starts before the design completes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The developer of a 40-story high-rise office building desires the shortest possible construction time. What contractual arrangement would be the best?

a. Construction management
b. Design/build
c. Design/bid/build
d. Either of a) or b)
e. None of the above

A

d. Either of a) or b)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Value engineering can be best described as…

a. Reducing cost by reducing quality
b. Getting the best value for the least cost
c. Reducing scope to achieve the budget
d. Recognizing project team to achieve the greatest efficiency
e. None of the above

A

b. Getting the best value for the least cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following term is used to describe the “unofficial/informal” relationship established between two workers in two different departments

a. Matrix
b. Pooled relationship
c. Gangplank
d. Leadership
e. Responsibility

A

c. Gangplank

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following legal forms of business organization/s is perpetual (continuous)?

a. Sole proprietorship
b. Partnership
c. Corporation
d. All of the above
e. None of the above

A

c. Corporation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Long-lead items are materials or equipment typically ordered and bought by the

a. Owner
b. Designer
c. Construction manager
d. Trade contractor
e. Sub-contractor

A

a. Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IAR is the main output of the project planning phase. The term IAR stands for

a. Internal analysis report
b. Internal advancement report
c. Investment advancement report
d. Investment analysis report
e. Information analysis report

A

d. Investment analysis report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Two main perspectives of project commissioning is

a. Design and Planning
b. Engineering and Planning
c. Engineering and Contractual
d. Operational and Planning
e. Operational and Contractual

A

c. Engineering and Contractual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Owner involvement is highest during what project phase?

a. Construction
b. Engineering and design
c. Concept and feasibility
d. None of the above

A

c. Concept and feasibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which category of construction would typically be contracted out as a design/build?

a. Residential
b. Building construction
c. Industrial
d. Heavy/infrastructure construction

A

c. Industrial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In what project phase are the bud package advertised and the project contracted out (so construction can begin)?

a. concept and feasibility
b. engineering and design
c. procurement
d. construction
e. operation and utilization

A

c. procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In design/bid/build, the architect signs a contract with the…

a. owner
b. construction manager
c. general contractor
d. subcontractor
e. none of the above

A

a. owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Construction management is superior to design/bid/build approaches at addressing which of the following?

a. increased government regulations
b. larger projects
c. increased organizational size
d. increased organizational complexity
e. all of the above

A

e. all of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following is true of a GMP contract?

a. GMP is the same as lump sum bid
b. the contractor passes all costs to the owner up to a predetermined maximum
c. the owner assures all project risks
d. the construction manager assures all project risks
e. none of the above

A

b. the contractor passes all costs to the owner up to a predetermined maximum