Multiple Choice Flashcards
Drawings and specifications are the output of what stage of a project
a. Concept and feasibility
b. Procurement
c. Engineering and design
d. Startup and implementation
e. None of the above
c. Engineering and design
Traditionally, concept and feasibility studies are handled by the…
a. Owner
b. Architect
c. Contractor
d. Subcontractor
a. Owner
The term fast track means
a. Design/build
b. Construction starts before the design completes
c. Cost plus fixed fee
d. None of the above
b. Construction starts before the design completes
The developer of a 40-story high-rise office building desires the shortest possible construction time. What contractual arrangement would be the best?
a. Construction management
b. Design/build
c. Design/bid/build
d. Either of a) or b)
e. None of the above
d. Either of a) or b)
Value engineering can be best described as…
a. Reducing cost by reducing quality
b. Getting the best value for the least cost
c. Reducing scope to achieve the budget
d. Recognizing project team to achieve the greatest efficiency
e. None of the above
b. Getting the best value for the least cost
Which of the following term is used to describe the “unofficial/informal” relationship established between two workers in two different departments
a. Matrix
b. Pooled relationship
c. Gangplank
d. Leadership
e. Responsibility
c. Gangplank
Which of the following legal forms of business organization/s is perpetual (continuous)?
a. Sole proprietorship
b. Partnership
c. Corporation
d. All of the above
e. None of the above
c. Corporation
Long-lead items are materials or equipment typically ordered and bought by the
a. Owner
b. Designer
c. Construction manager
d. Trade contractor
e. Sub-contractor
a. Owner
IAR is the main output of the project planning phase. The term IAR stands for
a. Internal analysis report
b. Internal advancement report
c. Investment advancement report
d. Investment analysis report
e. Information analysis report
d. Investment analysis report
Two main perspectives of project commissioning is
a. Design and Planning
b. Engineering and Planning
c. Engineering and Contractual
d. Operational and Planning
e. Operational and Contractual
c. Engineering and Contractual
Owner involvement is highest during what project phase?
a. Construction
b. Engineering and design
c. Concept and feasibility
d. None of the above
c. Concept and feasibility
Which category of construction would typically be contracted out as a design/build?
a. Residential
b. Building construction
c. Industrial
d. Heavy/infrastructure construction
c. Industrial
In what project phase are the bud package advertised and the project contracted out (so construction can begin)?
a. concept and feasibility
b. engineering and design
c. procurement
d. construction
e. operation and utilization
c. procurement
In design/bid/build, the architect signs a contract with the…
a. owner
b. construction manager
c. general contractor
d. subcontractor
e. none of the above
a. owner
Construction management is superior to design/bid/build approaches at addressing which of the following?
a. increased government regulations
b. larger projects
c. increased organizational size
d. increased organizational complexity
e. all of the above
e. all of the above