Multiple Choice Flashcards

1
Q

Which one is most suitable if the designer knows what items are required but design is not sufficiently progressed?
A. Lump sum fixed priced contract
B. Re-measured firm price contract
C. Guaranteed maximum price contract (GMP)
D. Target cost contracts

A

Re-measured (firm price) contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does the fast tracking approach include?
A. Overlapping between design and construction stages.
B. Design and build procurement route
C. Potential rework due to incomplete information
D. All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
Which one of the following documents is dangerous for contractors?
A. Letter of intent 
B. Letter of acceptance 
C. Letter of award
D. All of the above
A

Letter of intent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

GMP contract is usually selected when;
A. Design is incomplete at start of construction
B. Projects are fast-tracked
C. Lump sum pricing can’t be accurately calculated
D. All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The main advantage of target price contract pricing is to:
A. Reduce overall design and construction schedule to meet a deadline.
B. Enable construction to start in phases
C. Encourage better value engineering in the project
D. All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
In which procurement option clients may seek subcontract nomination? 
A. Traditional
B. Design & Construct 
C. Management contracting 
D. A&B
A

Traditional & Design and Construct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
In which type of procurement route can the contractor not be sued for negligence?
A. Construction management
B. Early Contractor Involvement 
C. Alliancing 
D. None of the above
A

Alliancing. The only way you can sue through alliancing is through wilful conduct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
What are the potential project risks of subcontract nomination?
A. Scope conflict
B. Late nomination
C. Adversarial relationships 
D. All of the above
A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Which type of contract is associated with a lack of knowledge of the client's financial commitment and lack of incentive for the contractor?
A. Re-measured contract
B. Target cost contract
C. GMP contract
D. Cost Plus contract
A

Cost-plus contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following are least achieved when using traditional lump sum procurement route?
A. Control over the design and materials
B. Price certainty before commencement to build
C. Suitability for complex design
D. Control over site planning

A

Control over site planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
Which of the following documents are not used to determine the scope of work in a project?
A. Bill of Quantity
B. Specifications
C. Drawings
D. Letter of acceptance
A

Bill of Quantities as it is only a schedule of rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
Which type of contract is most appropriate where the particular physical conditions are too variable?
A. Cost plus contract
B. Target price contract 
C. GMP contract 
D. Re-measured contract
A

Cost Plus contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
Which of the following are not forms of contractor side abuse in tendering?
A. Bid rigging
B. Price fixing 
C. Price signalling 
D. Market division
A

Price signalling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How can you maximise your value for money in management contracting procurement option?
A. Get collateral warranties from trade contractors
B. Establish incentive scheme with management contractor
C. Appoint an external consultant to oversee the work
D. All of the above

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Which form of contract is used if the contractor has to design some elements in the project alongside construction scope?
A. AS2124
B. AS4000
C. AS4300
D. A&B
A

AS2124 & AS4000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Project procurement is associated with: 
A. How the project participants are organised
B. The tendering process 
C. Contract strategy 
D. All of the above
A

All of the above

17
Q

Design & Build approach in procurement can be positive because;
A. Clients can finish project earlier
B. Buildability is improved
C. Input by the contractor can lead to more economic design
D. All of the above

A

All of the above

18
Q
Client flexibility is the highest in the following procurement route:
A. Design bid build 
B. Construction management 
C. Design & build 
D. Management contracting
A

Construction management

19
Q
Bid rigging can take the following form:
A. Cover pricing 
B. Price signalling 
C. Technical levelling 
D. All of the above
A

Cover pricing

20
Q

A shared risk culture is basically achieved by the following delivery method
A. Traditional cost Plus with guaranteed maximum price
B. Alliancing
C. Public private partnerships
D. All of the above

A

All of the above