MSTE Flashcards

1
Q

Standard shape of stop sign

A

octagon

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Standard shape for GIVE WAY sign

A

equilateral triangle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Color of no loading/unloading zone markings

A

red

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Device mounted on a fixed support
(permanent signs) or portable support
(temporary signs) whereby a specific message
is conveyed by means of words or symbols
placed or erected for the purpose of
regulating, warning or guiding traffic.

A

Traffic Signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Signs which inform and advise road users
of directions, distances, routes and the
location of services for road users and point
of interest.

A

Guide Signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Signs used to guide drivers through a
change in horizontal alignment of the road.

A

Chevron Signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The design element which is the most
affected by the volume of traffic.

A

Number of Traffic Lanes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The primary consideration in the design
of geometric cross sections for highways,
runways and taxiways is _______.

A

Drainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reaction times vary widely. As a result,
the usual practice is to use a single, rather
conservative value. AASHTO suggests a value
of ____ in its Policy on Geometric Design of
Highways and Streets.

A

2.5 sec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

It provides the detailed requirements
for the materials, equipment and workmanship
to be incorporated into the project.

A

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

This refers to drawing, usually
accompanied by notes, of various aspects or
components of the design.

A

Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

It include cost estimates for various
parts of the project and are used to evaluate
the acceptability of bids and the financial
feasibility of the project.

A

Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

It is the process where a load is
prepared for lifting using a lifting
machine. The main part of this process is
the tying up of the load with sling and other
connecting devices so that the load could be
hooked onto a crane.

A

Rigging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Complete or partial dismantling of a
building or structure by pre
-planned and
controlled methods or procedures.

A

Demolition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It is capable of spreading,
consolidating, and finishing a concrete slab
without the use of conventional forms.

A

Slipform Paver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

It is a very versatile machine that has
the longest reach for digging and dumping of
any member of the crane shovel family
.

A

Dragline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The bucket volume contained within the
bucket when following the outline of the
bucket sides is called:

A

Plate line capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Assumes a level of material flush with
the lowest edge of the bucket.

A

Waterline Capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The bucket capacity when the load is
struck off flush with the bucket sides.

A

Struck Capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

It represents those components of cycle
time other than travel time.

A

Fixed Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

This represents the travel time required
for a unit to haul material to the unloading
site and return

A

Variable Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Construction workers who are working
from unguarded surfaced _________ or more
above grade, temporary or permanent floor
platform, scaffold or where they are exposed
to the possibility of falls hazardous to life
or limb, must be provided with safety
harnesses and lifelines.

A

6 meters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Every construction project shall have a
suitable _________________, which must be in
accordance with these rules, and other
orders and issuances issued by the
Department of Labor and Employment.

A

Construction Safety and Health Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

This refers to a method of protecting
employees from cave-ins, from material that
could fall or roll from an excavation face
or into an excavation, and from the collapse
of adjacent structures.

A

Protective System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

This refers to structures such as
underpinning, bracing, and shoring that
provide support to an adjacent structure or
underground installation or to the sides of
an excavation or trench.

A

Support System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

It is the movement of plastic concrete
into its final position (usually within
forms).

A

Placing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

In general, ________ may be done when
the water sheen has disappeared and the
concrete will support the weight of the
finisher.

A

Floating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

This is done on slabs that are to be left
exposed or to receive thin finishes, such as
resilient flooring, carpet, tile, or paint.

A

Troweling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

It is defined as the fraction of time
that vehicles are present at a point in
space.

A

Occupancy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

It is the maximum number of vehicles,
passengers, or the like, which can be
accommodated by a given facility or system
under given conditions at a given level of
service.

A

Service Volume

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

The points at which the cut or fill
slopes intersect the existing ground are
referred to as _______.

A

Catch Points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

A comprehensive list of parts, items,
assemblies, subassemblies, intermediate
assemblies, documents, drawings, and other
materials required to create a product.

A

Bill of Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

A list of materials and services required
to perform a project. The list includes
materials, labor, and quantities of each.

A

Bill of Quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

The amount by which the outer edge of a
curve or a railroad is banked above the inner
edge to help offset the centripetal force
developed as the vehicle goes around a curve.

A

Superelevation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Cracks approximately at right angles to
the pavement centerline. These may be caused
by shrinkage or differential thermal stress
of the asphalt concrete or maybe reflective
cracks.

A

Transverse Cracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Cracks approximately parallel to the
pavement centerline. These are caused by
poorly constructed construction joints and
shrinkage of asphalt concrete surface.

A

Longitudinal Cracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Wearing way of the pavement surface
caused by dislodging of aggregated particles
and binder. This is usually a result of
insufficient asphalt binder in the mix or
stripping of asphalt from particles of
aggregate.

A

Raveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Progressive disintegration of the
surface between the wheel paths caused by
dripping of gasoline or oil from vehicles.

A

Drip Track Raveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

The extruding of bitumen onto the
pavement surface, causing a reduction in
skid resistance. It is generally caused by
excessive amounts of asphalt in the mix or
low air voids content. It occurs when asphalt
fills the voids in the mix during hot weather
and then exudes out onto the surface of the
pavement.

A

Bleeding or Flushing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Elevation differences between adjacent
slabs at transverse joints. It is usually
the result of pumping and is a major source
of Portland Concrete pavement structure.

A

Faulting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Localized upward buckling and shattering
of the slabs at transverse joint or cracks.
They can occur when transverse joints are
filled with incompressible solid materials.

A

Blowups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

A series of interconnected or interlaced
cracks caused by fatigue failure of the
asphalt concrete surface under repeated
traffic loading.

A

Alligator Cracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Cracks forming large interconnected
polygons, usually with sharp corners or
angle. These cracks are generally caused by
hardening and shrinkage of the asphalt and
or reflection cracking from underlying
layers such as cement-treated base.

A

Block Cracking

44
Q

A method of protecting workers from cave-ins by excavating the sides of an excavation
to form one or a series of horizontal levels
or steps, usually with vertical or near
vertical surfaces between levels.

45
Q

Protects workers by using trench boxes
or other types of supports to prevent soil
cave-ins.

46
Q

This requires installing aluminum
hydraulic or other types of supports to
prevent soil movement and cave-ins.

47
Q

It is defined as the maximum safe speed
that can be maintained over a specified
section of a highway when conditions are so
favorable that the design features of the
highway govern.

A

Design Speed

48
Q

The basic lane width appropriate for
national road is _______.

49
Q

It is advisable for a site plan to
contain a large-scale map of the overall area
and to indicate where the project is located
on the site.

A

Vicinity Map

50
Q

This drawing has elevation as its
vertical axis and horizontal distance as
measured along the centerline of the
facility as its horizontal axis.

51
Q

This applies to curved facilities, suc
as highways or railways only. It consists of
a graph with a roadway or railway cross slope
versus horizontal distance.

A

Superelevation Diagram

52
Q

This view has elevation as its vertical
axis and horizontal distance, measured
perpendicular to the centerline, as its
horizontal axis.

A

Geometric Cross Section

53
Q

It is a violation of an accepted safe
procedure which could permit the occurrence
of an accident.

A

Unsafe Act

54
Q

A hazardous physical condition or
circumstance which could directly permit the
occurrence of an accident.

A

Unsafe Condition

55
Q

Rule is the guidelines regarding
Personal Protective Equipment (PPE).

56
Q

How do you test the relative consistency
of concrete?

A

Slump-test

57
Q

Most important process to prepare
concrete:

58
Q

The number of days final curing for a
concrete cement pavement is done for:

59
Q

Joints placed in concrete pavements,
which are usually placed transversely, at
regular intervals, to provide adequate
expansion space for the slab to expand when
the pavement is subjected to an increase in
temperature.

A

Expansion Joint

60
Q

Joints placed in concrete pavements,
which are usually placed transversely
regular intervals across the width of the
pavement to release some of the tensile
stresses that are due to a decrease in
temperature.

A

Contraction Joint

61
Q

Joints placed in concrete pavements,
which are usually placed transversely across
the pavement width to provide suitable
transition between concrete placed at
different times or on different days.

A

Construction Joint

62
Q

Joints placed in concrete pavements at
right angles to the center line of the
pavement is called:

A

Transverse Joint

63
Q

It is a type of thermoplastic lane
marking designed to aid and provide motorist
with visual, audio, and warning on the road.

A

Rumble Strips

64
Q

Generally, the dry materials used in
making quality concrete are heavier than
water. Thus, shortly after placement, they
have a tendency to settle to the bottom and
displace the mixing water to the surface,
which is called _____.

65
Q

The surface of newly placed concrete is
struck off by moving a straightedge back and
forth with a saw-like motion across the top
of the forms.

66
Q

The bringing of a concrete surface to
true grade with enough mortar to produce the
desired finish.

67
Q

Immediately following or during edging,
pre-molded inserts are placed in concrete
slabs to control cracking in the concrete as
a result of shrinkage.

68
Q

When inside the building, one may notice
unusual sounds and change in the building.
What causes these events?

A

Temperature

69
Q

Any temporary elevated platform used for
supporting employees or materials or both in
the course of any construction works.

70
Q

What are the capacity requirement for
all scaffoldings?

A

4 times its own weight

71
Q

It is the timing of signals in
relationship to one another so that vehicles
travelling at a predetermined speed can pass
through the greens of successive signals.

A

Signal Coordination

72
Q

The speed at which vehicles are presumed
to travel through coordinated signal system
is known as:

A

Speed of Progression

73
Q

The time difference between the
beginning and end of through band at any
point is known as:

74
Q

The red, yellow, or green light that is
displayed to driven in a given movement is
called an:

A

Indication

75
Q

The time required for one complete
sequence of signal indication is called
____.

76
Q

The simplest rail capacity problem is
that involving rail rapid transit systems.
These usually have the following
characteristics:
I. One-way operation
II. A common speed profile for all trains.
That is, each train traverses each section
of track at the same speed as all other
trains; consequently, trains do not overtake
or pass one another.
III. Common station dwell times. That is,
each train spends the same amount of time
stopped at each station as all other trains;
dwell times may vary from station to station
IV. A fixed minimum front-to-back time gap
between trains.

A. I-III
B.II and IV only
C. III only
D. All of the above

A

All of the Above

77
Q

There are three basic ways of resolving
crossing conflicts.
I. Time sharing solutions
II. Space sharing solutions
III. Grade separation solutions
IV. Crossing conflict solutions

A. I-III only
B. II and III only
C. II only
D. All of the above

A

I-III Only

78
Q

It is the difference between the actual
travel time and a given segment of a
transportation system and some ideal travel
time for that segment.

79
Q

The time spent in decelerating and
accelerating the vehicle in opening and
closing doors.

A

Clearance Time

80
Q

Headways such that the vehicles are just
filled at the maximum load point on the
route.

A

Capacity Headway

81
Q

________ is the process of increasing
the density of a soil by mechanically
forcing the soil particles closer
together, thereby expelling air from the
void spaces in the soil.

A

Compaction

82
Q

________ is an increase in soil density
of a cohesive soil resulting from the
expulsion of water from the soil’s void
spaces.

A

Consolidation

83
Q

Compactor production is based on the
following data:
I. Number of paces required
II. Width compacted per pass
III. Compactor speed
IV. Compacted lift thickness
V. Job Efficiency

A. I, III, IV and V
B. I, II, IV, and V
C. all of the above
D. II, III, IV and V

A

All of the above

84
Q

The process of giving natural soils
enough abrasive resistance and shear
strength to accommodate traffic or
design loads is called.

A

Ground Modification

85
Q

It involves dropping a heavy weight from
a crane onto the ground surface to
achieve soil densification.

A

Dynamic Modification

86
Q

________ or placing additional weight
on the soil surface, has long been used
to densify cohesive soils.

A

Surcharging

87
Q

________ is the process of densifying
cohesionless soils by inserting a
vibratory probe into the soil.

A

Vibroflotation

88
Q

Workers in an excavation be protected
from cave-ins by one of the following
methods:
I. Sloping or benching of the sides of
the excavation.
II. Supporting the sides of the
excavation by shoring.
III. Placing a shield between workers
and the sides of the excavation.
IV. Drying soil to prevent collapsing.

A. all of the above
B. I, II, and IV
C. I, II, and III
D. II, III, and IV

A

I, II, and III

89
Q

In highway construction, the process of
cutting down high spots and filling in
low spots of each roadway layer is
called.

90
Q

Estimates expected activity times in a
PERT network.
I. Make use of three estimates
II. Puts the greatest weight on the
most likely time estimate
III. Is motivated by the beta
distribution

A. III only
B. I only
C. II only
D. All of the above

A

All of the Above

91
Q

Of all paths through the network, the
critical path:

A

has the maximum expected time

92
Q

The calculation of the probability
that the critical path will be
completed by time T
I. Assumes that activity times are
statistically independent.
II. Assumes that total time of the
critical path has approximately
a beta distribution
III. Requires knowledge of the
standard deviation for all
activities in the network

A. II only
B. I only
C. II only
D. All of the above

93
Q

The CPM time-cost trade off function

A

cost decreases linearly as time increases

94
Q

The marginal cost of crashing a
network could change when

A. The activity being crashed
reaches its crash time
B. The activity being crashed
reaches a point where another path
is also critical
C. Both A and B
D. None of the above.

A

Both A and B

95
Q

Fundamental ideas in the LP network
models are activity time equals normal
time + crash time
I. Earliest start time for an
activity leaving a node equals
the Max of the earliest finish
times for activities leaving
that node
II. Earliest finish time equals
latest finish time minus
activity time.

A. I only
B. II only
C. I and II
D. None of the above

A

None of the Above

96
Q

The PERT/COST model assumes that
I. Each activity achieves its
optimistic time
II. The costs are uniformly
distributed over the life of the
activity
III. Activity times are statistically
independent.

A. I only
B. II only
C. III only
D. None of the above

97
Q

The PERT/Cost control report
I. Requires a budget for each
activity
II. Requires a report on the
percentage of completion of each
activity
III. Calculate overruns

A. I only
B. II only
C. III only
D. All of the above

A

All of the above

98
Q

The process of bringing each roadway
layer to its final grade

99
Q

It is the breaking away of hardened
concrete surface of a slab to a depth
of about 1.6 to 4.8 mm. It is usually
occurs at an early age of slab.

100
Q

It is the occurrence of numerous fine
hair cracks in the surface of a newly
hardened slab to surface shrinkage.

101
Q

Appearance of powdery material on the
surface of newly hardened concrete
slab.

102
Q

Bringing of a concrete surface to true
grade with enough mortar to produce
the desired finish.

103
Q

The surface of newly placed concrete
is struck off by moving a straightedge
back and forth with a sawlike motion
across the top of the forms and
screeds.

104
Q

Is done on slabs that are to be left
exposed or to receive thin finishes,
such as resilient flooring, carpet,
tile or paint

105
Q

Arrange the following in chronological
order:
I. Broom Finishing
II. Screeding
III. Bleeding
IV. Leveling
V. Jointing
VI. Edging
VII. Floating
VIII. Troweling

A. I,II,III,IV,V,VI,VII,VIII
B. III,II,IV,VI,V,VII,VIII,I
C. VIII, VII,VI,V,IV,III,II,I
D. II,IV,V,VIII,I,III,VI,VII