MS Project Flashcards
Series of tasks that don’t need to be completed on time for a project to finish on schedule
Non critical path
A tasks______is the latest date that a task can commence without delaying the project finish date
Late start
A task that comes before a specific task on a project schedule
predecessor
The amount of time a task can slip before it has an effect on other tasks or the project finish date
slack
the date at which assigned work is schedule to commence
assignment date
a tasks____ is the latest date that a task can be completed without delaying the project finish date
late finish
The earliest date provided in a project plan, this date determines when work or task can commence
project start date
A task that must be completed as schedule for the project to finish on schedule
critical task
the schedule ending date
finish
the latest due to complete all tasks in a project plan
project finish date
a project activity that has a beginning and an end
task
the total time require to complete a task
duration