MS Project Flashcards

1
Q

Series of tasks that don’t need to be completed on time for a project to finish on schedule

A

Non critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A tasks______is the latest date that a task can commence without delaying the project finish date

A

Late start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A task that comes before a specific task on a project schedule

A

predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The amount of time a task can slip before it has an effect on other tasks or the project finish date

A

slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

the date at which assigned work is schedule to commence

A

assignment date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

a tasks____ is the latest date that a task can be completed without delaying the project finish date

A

late finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The earliest date provided in a project plan, this date determines when work or task can commence

A

project start date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A task that must be completed as schedule for the project to finish on schedule

A

critical task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

the schedule ending date

A

finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

the latest due to complete all tasks in a project plan

A

project finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

a project activity that has a beginning and an end

A

task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

the total time require to complete a task

A

duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly