MRP2 Framework Flashcards
1
Q
The four main functions in MRP2
A
Sales and Operations Planning [S&OP]
Master Production Planning/Schedule [MPS]
Material Requirements Planning [MRP]
Production Activity Control [PAC]
2
Q
What is MRP2?
A
Hierarchical planning structure
3
Q
Input for S&OP
A
Sales forecast
4
Q
Output for S&OP
A
Production plan
5
Q
Input for MPS
A
Production plan
6
Q
Output for MPS
A
Mater plan
7
Q
Input for MRP
A
Master plan
8
Q
Output for MRP
A
Production and puschase order
9
Q
Input for PAC
A
Production order
10
Q
Output for PAC
A
Sequencing
10
Q
Horizon for S&OP
A
1-5 years
11
Q
Horizon for MPS
A
1/4 - 1 year
11
Q
Horizon for MRP
A
1-6 months
11
Q
Horizon for PAC
A
1-4 weeks
11
Q
Period and re-scheduleing for S&OP
A
Quarter/Month