MPC Flashcards

1
Q

What is Input for the Strategic Business Plan?

A

Market Analysis
Financial Goals
Business Objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Output for the Strategic Business Plan?

A

C-Suite decisions on Supply chain strategy
Overall strategic plan of the company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Input for the Master Production Schedule?

A

Production Plan
Specific end item requirements
Capacity checks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Input for the Production Plan?

A

Quantity of each product group for each period
Desired Inventory levels
Resource requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Output for the Production Plan?

A

Aggregate production rates (production strategy)
Identification of resource needs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is FLH for the Strategic Business Plan?

A

Frequency: 6-12 months
Level: Major markets to serve
Horizon: 2-10 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is FLH for the Production Plan?

A

Frequency: 1-3 months
Level: Product groups or families
Horizon: 6-18 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Output for the Master Production Schedule?

A

Quantity of each item per period
Detailed production schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Input for the Material Requirement Plan?

A

Master Production Schedule
Bill of Materials
Inventory levels
Lead times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is FLH for the Master Production Schedule?

A

Frequency: Weekly or monthly
Level: End items
Horizon: 3-18 months (lead time dependent)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Output for the Material Requirement Plan?

A

Specific components to be produced/purchased
Production/Purchasing Schedules
Daily “work to be completed” list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is FLH for the Material Requirement Plan?

A

Frequency: Daily or Weekly
Level: Components
Horizon: 3-6 months (lead time dependent)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Input for the Production Activity Control & Purchasing?

A

Material Requirement Plan
Production Orders
Purchase Orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Output for the Production Activity Control & Purchasing?

A

Detailed execution plan for production orders
Monitor & Control of production activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is FLH for the Production Activity Control & Purchasing?

A

Frequency: Hourly or Daily
Level: Execution
Horizon: Daily

How well did you know this?
1
Not at all
2
3
4
5
Perfectly