Module 6: Monitoring and Control Flashcards
Define monitoring and control in project management.
Process of tracking, reviewing and reporting overall progress to meet the performance objectives.
Monitoring goes through the whole project.
What does it focus on?
Collecting, assessing and distributing info.
SO PM and the team can respond to the problem with control actions.
Define Controlling.
Coorective/ …
…preventive actions to maintain/improve project performance
Outline 3 sub-processes within monitoring and control.
- Track
- Review
- Orchestrate
* Identify areas where changes are required.
* Initiate required changes to the plan.
Progress and performance.
Identify 8 elements to monitor in project management.
- Scope
- Schedule
- Budget
- Risks
- Issues
- Stakeholders
- Documents
- Product/Service/Result
During 1. Scope monitoring we need to ensure that creep is not occuring.
What is a Scope Creep?
Scope is expanded without integrating changes or without approval.
When monitoring scope we are managing changes to the scope baseline.
What Scope monitoring focuses on?
1. Control…, 2. Work…, 3. Oversee…
- Control of what causes project scope changes & control of the impact of those changes.
- Work hand-in-hand with integrated change control.
- Oversee the implementation of aproved scope changes.
Define 2. Schedule Monitoring
Ensure task are on…
…time, overall project stay on track in respect to baseline schedule
As a part of inetgrated change control process.
What 4 things 2. Schedule Monitoring focuses on?
1. Monit… , 2. Controlling… , 3. Determining… , 4. Monitor…
- Monitoring current(schedule)
- Controlling factors leading to changes
- Determining when schedules has changed-based on performance report input
- Monitor and control actual project changes when they occur
Budget monitoring focus on costs and manage changes to the cost baseline
What are the 4 elements of it?
1. Monitoring… 2. Controlling… 3. Determining… 4. Monitoring
Part of inetgrated change control process.
- Monitoring current vs baseline
- Controlling factors that lead to change
- Determining when the cost variance, based on performance report input.
- Monitoring an controlling the actual project changes when they occur.
Critical proj. control principles are efforts to keep project on track.
What are its 4 primary activities?
- Planning performance
* Scope, Schedule, Cost Management plan. - Measuring status of work being done
* Actuals & Staying on the schedule - Comparing to Baseline
* Are there any Variances? - Taking corrective actions if needed.
Response
4 Project control principles are:
1. Control
Guide the course of action to meet project objectives. Not dominate through power and authority.
2. Work is controlled not the workers.
Control help the team to be more efficient and effective.
3. Control based on work completed.
Use concrete deliverables.
4. Balance
Micromanaging vs neglect, Too much tracking details vs too little.
What are 3 key Progress Monitoring Questions?
- What is the actual status?
- If there’s a variance, what is cause?
- What to do about it?
What are possible responses to 3 key Progress Monitoring Questions?
- Ignore
- Take corrective action
- Review the plan
Monitoring rates need to be discussed : Daily/weekly/monthly?
If problem occur then you need to adjust, what is the recommended solutions?
Usually theres 1 or more areas under closer scrutiny(obserwacja)
You may need to monitor certain areas closer for some period of time
What is EVM Methodology?
Scope+schedule+resource measurements to asses project performance and progress.
Integrates baselines of all 3 to form PERFORMANCE MEASUREMENT BASELINE
What do we compare during Earned value analysis?
Performance measurement baseline to the actual schedule and cost performance.
3 things that Earned value analysis does?
- Combines variables of cost and time
- Compares tasks actually completed with original plan
- Provides performance indexes to gauge progress
What is Earned Value(EV)?
Measure of…
…work performedexpressed in terms of the budget authorized for that work.
What are the 10 steps to successfully apply EVA?
- Create Work Breakdown Structure
- Identify the activities required to complete the entire project
- Allocate the Duration and Cost of each activity
- Establish the logic of each activity in a network diagram
- Analyse the schedule to ensure it is realistic and achievable
- Set the Baseline
- Update the schedule by reporting activity progress
- Enter the actual costs on the activities
- Execute the Earned Value calculation
- Analyse the data and write the performance narrative. (EVA is performed here)
What is the Planned Value (PV)?
Authorized budget assigned to scheduled work(in WBS).
PV is cumulative total + planned = rises each month
It can be added to a chart
What is: Actual Cost of Work Performance (AC)
The realized cost incurred for the work performed on an activity during specific time period.
Using Performance Measures we can calculate 3 variances. What are they?
- Cost Variance(CV)
- Schedule variance(SV)
- Total Variance(TV)
How do we calculate: Cost Variance(CV)?
EV - AC
Positive number= Under Budget;
Negative number = Over Budget;
Zero = On Budget
How do we calculate: Schedule variance(SV)?
EV - PV
Positive number= Ahead of schedule; Negative number = Behind Schedule;
Zero = On Schedule
How do we calculate: Total Variance(TV)
PV - AC
Positive number= Good ; Negative number = Bad;
Zero = On track
What are 2 Performance Indexes? And how do we calculate them?
- Cost Performance Index (CPI) = EV / AC
Greater than 1 = Under budget
1 = On budget
Less than 1 = Over Budget - Schedule Performance Index (SPI) = EV / PV
>1 = Ahead of Schedule
1 = On Schedule
<1 = Behind Schedule
What are the 4 Completion Metrics?
- Budget at Completion - BAC
- Estimate a C - EAC
- Variance a C
- Estimate to C
How do we measure:
1. Budget at Completion - BAC
2. Estimate a C - EAC
3. Variance a C
4. Estimate to C
- Sum of all budgets established for the work to be performed.
- BAC / CPI
Expected total cost of completing all the work expressed as sum of actual cost to date and estimated to complete. - BAC - EAC
Projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion - EAC - AC
Expected cost to finish all the remaining project work.
What are the 5 reasons to use Performance Measures?
-
Catch deviation from the curve early.
Easy to see and help to get back on track. -
Dampen oscillation.
a. Plan v actual performance should display similar pattern over time.
b. Wild fluctuations - may mean project is not under control. - Allow early corrective action.
- Determine weekly schedule variance.
-
Determine weekly effort (person hours) variance.
a. Difference in planned v actual effort has direct impact on planned cumulative cost and schedule.
b. If effort is < planned = potential schedule slippage.
3 things risk monitoring is concerned with:
- Identifyig, analyzing, and planning for new risks that arise in the course of the project
- Tracking identified risks and monitoring residual risks
- Monitoring trigger conditions for risks