Module 5- Risk Identification Flashcards

1
Q
  1. Which of the following is not an input to the identify risks process?

A. Risk management plan
B. Activity cost estimates
C. Project scope statement
D. Cost management plan

A
1.	C
PMBOK Guide - The inputs to the identify risks process include:
-	Risk management plan
-	Cost management plan
-	Schedule management plan
-	Quality management plan
-	Human resource management plan
-	Scope baseline
-	Activity cost estimates
-	Activity duration estimates
-	Stakeholder register
-	Project documents
-	Procurement documents
-	Enterprise environmental factors
-	Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Which of the following is not an input to the identify risks process?

A. Scope baseline
B. Human resource management plan
C. Schedule management plan
D. Risk register

A
2.	D
PMBOK Guide - The inputs to the identify risks process include:
-	Risk management plan
-	Cost management plan
-	Schedule management plan
-	Quality management plan
-	Human resource management plan
-	Scope baseline
-	Activity cost estimates
-	Activity duration estimates
-	Stakeholder register
-	Project documents
-	Procurement documents
-	Enterprise environmental factors
-	Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Which of the following is not an input to the identify risks process?

A. Work performance information
B. Activity cost estimates
C. Activity duration estimates
D. Procurement documents

A
  1. A

PMBOK Guide - The inputs to the identify risks process include:

  • Risk management plan
  • Cost management plan
  • Schedule management plan
  • Quality management plan
  • Human resource management plan
  • Scope baseline
  • Activity cost estimates
  • Activity duration estimates
  • Stakeholder register
  • Project documents
  • Procurement documents
  • Enterprise environmental factors
  • Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Which of the following is an input to the identify risks process?

A. Cost management plan
B. SWOT analysis
C. Risk related contracts
D. Technical performance measurements

A
4.	A
PMBOK Guide - The inputs to the identify risks process include:
-	Risk management plan
-	Cost management plan
-	Schedule management plan
-	Quality management plan
-	Human resource management plan
-	Scope baseline
-	Activity cost estimates
-	Activity duration estimates
-	Stakeholder register
-	Project documents
-	Procurement documents
-	Enterprise environmental factors
-	Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Which of the following is not a tool or technique used in the identify risks process?

A. Documentation review
B. Risk categorization
C. Information gathering techniques
D. Checklist analysis

A
5.	B
PMBOK Guide - The tools and techniques of the identify risks process include:
-	Documentation review
-	Information gathering techniques
-	Checklist analysis
-	Assumption analysis
-	Diagramming techniques
-	SWOT analysis
-	Expert judgment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Which of the following is not a tool or technique used in the identify risks process?

A. Information gathering techniques
B. Checklist analysis
C. Risk urgency analysis
D. SWOT analysis

A
6.	C
PMBOK Guide - The tools and techniques of the identify risks process include:
-	Documentation review
-	Information gathering techniques
-	Checklist analysis
-	Assumption analysis
-	Diagramming techniques
-	SWOT analysis
-	Expert judgment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Which of the following is not a tool or technique used in the identify risks process?

A. SWOT analysis
B. Expert judgment
C. Risk assessment
D. Checklist analysis

A
7.	C
PMBOK Guide - The tools and techniques of the identify risks process include:
-	Documentation review
-	Information gathering techniques
-	Checklist analysis
-	Assumption analysis
-	Diagramming techniques
-	SWOT analysis
-	Expert judgment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Which of the following is a tool or technique used in the identify risks process?

A. SWOT analysis
B. Risk assessment
C. Risk urgency assessment
D. Risk categorization

A
8.	A
PMBOK Guide - The tools and techniques of the identify risks process include:
-	Documentation review
-	Information gathering techniques
-	Checklist analysis
-	Assumption analysis
-	Diagramming techniques
-	SWOT analysis
-	Expert judgment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Which of the following is an output from the identify risks process?

A. Organizational process assets updates
B. Project management plan updates
C. Risk register
D. Project document updates

A
  1. C

PMBOK Guide - The output from the identify risks process is the risk register.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly