Module 5- Risk Identification Flashcards
- Which of the following is not an input to the identify risks process?
A. Risk management plan
B. Activity cost estimates
C. Project scope statement
D. Cost management plan
1. C PMBOK Guide - The inputs to the identify risks process include: - Risk management plan - Cost management plan - Schedule management plan - Quality management plan - Human resource management plan - Scope baseline - Activity cost estimates - Activity duration estimates - Stakeholder register - Project documents - Procurement documents - Enterprise environmental factors - Organizational process assets
- Which of the following is not an input to the identify risks process?
A. Scope baseline
B. Human resource management plan
C. Schedule management plan
D. Risk register
2. D PMBOK Guide - The inputs to the identify risks process include: - Risk management plan - Cost management plan - Schedule management plan - Quality management plan - Human resource management plan - Scope baseline - Activity cost estimates - Activity duration estimates - Stakeholder register - Project documents - Procurement documents - Enterprise environmental factors - Organizational process assets
- Which of the following is not an input to the identify risks process?
A. Work performance information
B. Activity cost estimates
C. Activity duration estimates
D. Procurement documents
- A
PMBOK Guide - The inputs to the identify risks process include:
- Risk management plan
- Cost management plan
- Schedule management plan
- Quality management plan
- Human resource management plan
- Scope baseline
- Activity cost estimates
- Activity duration estimates
- Stakeholder register
- Project documents
- Procurement documents
- Enterprise environmental factors
- Organizational process assets
- Which of the following is an input to the identify risks process?
A. Cost management plan
B. SWOT analysis
C. Risk related contracts
D. Technical performance measurements
4. A PMBOK Guide - The inputs to the identify risks process include: - Risk management plan - Cost management plan - Schedule management plan - Quality management plan - Human resource management plan - Scope baseline - Activity cost estimates - Activity duration estimates - Stakeholder register - Project documents - Procurement documents - Enterprise environmental factors - Organizational process assets
- Which of the following is not a tool or technique used in the identify risks process?
A. Documentation review
B. Risk categorization
C. Information gathering techniques
D. Checklist analysis
5. B PMBOK Guide - The tools and techniques of the identify risks process include: - Documentation review - Information gathering techniques - Checklist analysis - Assumption analysis - Diagramming techniques - SWOT analysis - Expert judgment
- Which of the following is not a tool or technique used in the identify risks process?
A. Information gathering techniques
B. Checklist analysis
C. Risk urgency analysis
D. SWOT analysis
6. C PMBOK Guide - The tools and techniques of the identify risks process include: - Documentation review - Information gathering techniques - Checklist analysis - Assumption analysis - Diagramming techniques - SWOT analysis - Expert judgment
- Which of the following is not a tool or technique used in the identify risks process?
A. SWOT analysis
B. Expert judgment
C. Risk assessment
D. Checklist analysis
7. C PMBOK Guide - The tools and techniques of the identify risks process include: - Documentation review - Information gathering techniques - Checklist analysis - Assumption analysis - Diagramming techniques - SWOT analysis - Expert judgment
- Which of the following is a tool or technique used in the identify risks process?
A. SWOT analysis
B. Risk assessment
C. Risk urgency assessment
D. Risk categorization
8. A PMBOK Guide - The tools and techniques of the identify risks process include: - Documentation review - Information gathering techniques - Checklist analysis - Assumption analysis - Diagramming techniques - SWOT analysis - Expert judgment
- Which of the following is an output from the identify risks process?
A. Organizational process assets updates
B. Project management plan updates
C. Risk register
D. Project document updates
- C
PMBOK Guide - The output from the identify risks process is the risk register.