The project team has completed the scope baseline and has started to break down each of the work packages in into individual activities. What process should the team do next?
Sequence activity
After the team has created the activity list in the process of define activity, the next process should be sequencing the activities. This should be done before the team develops a schedule. Creating WBS and defining scope will come before defining activities.
The project manager has taken all the work performance information that has been created so far on the project. He has to create the overall project status report to present to the project stakeholders. WHAT PROCESS IS THE PROJECT MANAGER CONDUCTING?
MONITOR AND CONTROL PROJECT WORK
Monitor and control project work process has an input of work performance information and an output of work performance report.
While planning a major network upgrade project, one stakeholder has given a requirement to upgrade the switches. The project manager has determined that this would be too costly to be included in the project and has decided to exclude it. What process will the project manager use to document this exclusion?
DEFINE SCOPE
The project scope statement would have a list of deliverables and include things such as acceptance criteria, exclusions, constraints, and assumptions.
The scope statement is created in the process of define the scope.
The product owner has added three new changes to the product backlog. The agile project manager has met with the team and they have decided immediately how to implement these new changes, although these changes will be implemented in three iterations from now. The product owner informs the agile project manager that he is not happy about this. What should the agile project manager do?
TELL THE TEAM THEY SHOULD NOT HAVE COMMITED TO DOING THESE CHANGES UNTIL THEY WERE READY TO IMPLEMENT THEM
One of the core principles of agile is to defer decisions. What this means is to make decisions about potential changes or features until the very last minute.
Team members Mark and Bill are currently experiencing conflict in the office move project. Mark believes that it would be best if they move the furniture first and then the computers, whereas Bill believes it’s best to move the computers and then the furniture. This conflict is causing a serious delays to the project, and both Mark and Bill have decided they will make a decision on what to move first a a later date.
What conflict resolution technique best describes this scenario?
Withdrawal
The conflict resolution technique Illustrated in this question is withdrawal, which is when they postpone the issue to a later date to be better prepared. Compromise is when the two sides reach an agreement but both sides have to give up something. Postponing is a made-up term.
While working on a tablet redesign project for a large technology company, the project manager received a change request from a key stakeholer. The change request would change the position of the power button from the top to the side of the tablet. After an assessment of the change, the change control board (CCB) declined the change due to concerns about redesigning the motherboard.
What should the project manager do next?
Update Change Log
Once a change is approved or denied, the project manager should update the change log to list the status of the change. if a change is approved, the project management should be updated.
While working with the system administrator, the project manager identifies many different types of resources required for the project to be completed successfully. The project manager classifies them as HR, material, equipment, and consumable resources.
Where can the project manager best document these resources?
Resource Breakdown Structure (RBS)
The resource breakdown structure is a breakdown of the resources by categories or types. .
The resource requirements describe all the resources needed to complete an activity.
Over the last three weeks, the project team has finally been able to establish a shared vision of what the product would look like when it is complete. This is an example of?
Progressive Elaboration
Progressive elaboration occurs when more information in details emerges over time.
While analyzing the budget of a project, the project manager notices that the current CPI (Cost Performance Index) of the project is .93 (7% over budget) and the SPI (Schedule Performance Index) is 1.1 (10% ahead).
What best describes what is taking place on this project?
Crashing
Crashing involves adding more resources to a project to decrease the schedule. In this scenario, the project is 7% over budget but is 10% ahead of schedule. Fast tracking and resource leveling generally do not increase costs.
The project manager is having a very difficult time collecting the requirements from the customers. The customers are having a difficult time putting the requirements into logical groupings.
What tool can best help them group the requirements?
Affinity Diagram
An affinity diagram is used to group large numbers of ideas to be analyzed.
During the datacenter development project, the project manager has noticed that some of the work being done on the project is not in the baseline scope. The project manager has analyzed the work completed by the project team and then compared that to the project management plan to see where the differences are.
What process best describes the work of the project manager?
Control Scope
Control scope is a process where you compare the work that has been completed to the project management plan to see if they line up. If there is a variance, the project manager should initiate actions to fix the variance.
The project manager has to present the risk assessment to the senior management and has decided to take the most graphical representation of the probability and impact assessment.
What tool should the project manager use?
Bubble chart
Bubble charts are tools in the perform quantitative analysis process and can show the probability, impact, and ranking of risk.
While compiling all the work performance information into the work performance report, a project manager notices that the SPI of the project is .6 and the CPI is .7.
What action should the project manager take next on this project?
Create a change request to correct the project
In this scenario, an SPI of .6 and a CPI of .7 indicates that the project is behind schedule and over budget. The project manager should initiate change requests to correct the budget and schedule of the project.
While monitoring and controlling the project, the project manager and the team have consistently received broken equipment from a particular vendor. They have spoken with the vendor and implemented a new process that will ensure the equipment does not show up broken. This seems to have solved the problem.
What is the next step the project manager should take?
CHECK THE SOLUTION
When encountering any problem on a project, the project manager should first identify the problem, define the problem, investigate, analyze, solve, and then check the solution.
In this situation, the problem has already been solved, so the next step would be to check the solution to ensure the problem has actually been solved.
While planning a project, the project manager is given many requirements that the customers would like to add to the project. Upon further investigation, the project manager decides that a few of the requirements will not be feasible within the limited time and cost allocated to the project.
What document would best list the requirements that will not be added to this project?
Project Scope Statement
The project scope statement includes a list of all the project deliverables as well as any requirements that should be excluded from the scope.
The project team has just assigned costs to each of the activities on the project. They will now use these costs to find the overall budget of the project.
What tool can the project team use to complete this task?
COST AGGREGATION
If the activities have been assigned costs, then the process of estimate costs has been completed. The next process would be to determine budget and use the cost aggregation tool to integrate all the activitites into the overall budget of the project.
The project manager is informed that a manager in the finance department has requested to be included in the weekly status updates on the project.
What document should the project manager update immediately?
STAKEHOLDER REGISTER
The stakeholder register can be updated at any point during the project. The register contains a list of all stakeholders and their contact information, communication requirements , and impact on the project. Once this is done, then the project manager can update the communication management plan to add the new stakeholder.
The project manager is conducting a presentation with a few of the senior stakeholders, and they are not happy with the progress of the project. The project manager has informed them that the delay is due to a contractor that was affected by a major flood a few weeks ago.
What process does this best describe?
MANAGE COMMUNICATION
Manage Communication is done in the executing section of the project to update the stakeholders on the project’s progress.
Plan communication management is used to create the communications management plan that describes how communication will take place on the project. Control and conduct communication are made-up processes.
The project manager has just spoken to one of the software developers, Bill, about the project and has asked for an estimate of how long it will take to code a specific function. Bill said that it would take a maximum of 10 days (P), but that most likely (M/R) it will be 6 days. The project manager has calculated the PERT estimated duration of this activity to be 6 days.
What is the least amount of days (O) it will take to complete this activity?
2 DAYS
You have to use the PERT formula, which is (O+4*R+P)/6 to find the opttimistic number. The question gives the answer to the formula -6 days- and you will need to figure out the other components. In the question, the pessimistic number given is 10, the realistic number is 6, and you have to find out the optimisitc number.
Plug numbers into the formula like this: (O+4*6+10)/6=6 based on this equation, equals to 2.