MOCK 2 Flashcards

1
Q
  1. The WBS represents all product and project work, including project management. It is sometimes called the—
    a. Control account level
    b. 100% rule
    c. Integration of scope, cost, and schedule for comparison to the earned value
    d. The code of accounts
A
  1. b. 100% rule

The WBS is a deliverable-oriented, hierarchical decomposition of work to be done by the project team. Sometimes called the 100% rule, it shows the total of the work at the lowest levels must roll up to the higher levels so that nothing is left out and no extra work is done. [Planning]

PMI®, PMBOK® Guide, 2013, 131

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Your company is in the project management training business. In addition, the company publishes several exam study aids for the PMP® and CAPM® exam. You have your PMP®, and you have been appointed as the project manager to make sure your company’s training materials are updated to be aligned with the new PMBOK® Guide. You must complete your project in six months. You are now in month four. Many of your team members have been working on other projects as the company uses matrix management. In a performance review meeting today, you informed your Governance Board that you did not think you could complete this project in the remaining two months. You were informed that additional resources were not available, but you had to complete your project on time. Your best course of action is to—
    a. Revise your schedule baseline
    b. Use fast tracking
    c. Adjust leads and lags now in your schedule
    d. Use modeling techniques
A
  1. b. Use fast tracking

Fast tracking or crashing the schedule for the remaining work to be done are examples of schedulecompression techniques to find ways to bring project activities that are behind into alignment with the project management plan. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 190

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

  1. You are trying to determine whether or not to conduct 100% final system tests of 500 ground-based radar units at the factory. The historical radar field failure rate is 4%; the cost to test each unit in the factory is $10,000; the cost to reassemble each passed unit after the factory test is $2,000; the cost to repair and reassemble each failed unit after factory test is $23,000; and the cost to repair and reinstall each failed unit in the field is $350,000. Using decision tree analysis, what is the expected value if you decide to conduct these tests?
    a. $5.5 million
    b. $5.96 million
    c. $6.42 million
    d. $7 million
A
  1. c. $6.42 million

Test: $5M + $960K + $460K = $6.42M; Don’t Test: $7M. [Planning]

PMI®, PMBOK® Guide, 2013, 339

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Motivation is dynamic and complex. The statement, “Motivation is an intrinsic phenomenon. Extrinsic satisfaction only leads to movements, not motivation” is attributed to which of the leading theories of motivation?
    a. Maslow’s Hierarchy of Needs Theory
    b. Herzberg’s Motivator-Hygiene Theory
    c. Morse and Lorsch’s Contingency Theory
    d. McGregor’s Theory X/Theory Y
A
  1. b. Herzberg’s Motivator-Hygiene Theory

Frederick Herzberg’s Motivator-Hygiene Theory asserts that some job factors lead to satisfaction, whereas others can only prevent dissatisfaction. There are two types of factors associated to the motivation process: hygiene factors, which relate to the work environment, and motivators, which relate to the work itself. Hygiene factors, if provided appropriately, can prevent dissatisfaction, while motivating factors can increase job satisfaction and are more permanent. [Executing]

Verma 1996, 56, 64–65

Meredith and Mantel, 2012, 200

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Each time you meet with your project sponsor, she emphasizes the need for cost control. To address her concerns, you should provide—
    a. Work performance information
    b. Cost baseline updates
    c. Resource productivity analyses
    d. Trend analysis statistics
A
  1. a. Work performance information

The project’s work performance information should document and communicate the CV, SV, CPI, SPI, TCPI, and VAC for the WBS components in particular for specific work packages and control accounts. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 225

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. One output of the control costs process is cost forecasts, which is when—
    a. Modifications are made to the cost information used to manage the project and are communicated to stakeholders
    b. Trend analyses are performed and communicated to stakeholders
    c. A budget update is required and communicated to all stakeholders
    d. A calculated EAC value or a bottom-up EAC value is documented and communicated to stakeholders
A
  1. d. A calculated EAC value or a bottom-up EAC value is documented and communicated to stakeholders

Cost forecasts are another output of control costs, and the EAC is used to show the expected total costs of completing all work expressed as the sum of the actual cost to date and the estimate to complete. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 224–225

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. You work for an electrical utility company and will be managing a project to build a new substation that will serve a new industrial park. This project was authorized because of a—
    a. Business need
    b. Market demand
    c. Technological advance
    d. Customer request
A
  1. d. Customer request

Projects can be authorized as a result of a market demand, organizational need, customer request, technological advance, legal requirement, ecological impact, or a social need. The new industrial park is an example of a project authorized because of a customer request. [Initiating]

PMI®, PMBOK® Guide, 2013, 69

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. A final project report is a recommended best practice. Although this report can be organized in a variety of ways, how should each item that is covered in the report be addressed?
    a. A recommendation for changing current practice should be made and defended.
    b. The focus should be solely on items that did not work well on the project.
    c. Individuals who did not contribute successfully as team members should be noted.
    d. An earned value discussion is warranted.
A
  1. a. A recommendation for changing current practice should be made and defended.

It is important to capture lessons learned, which then can be used on subsequent projects. The more detailed the lessons the better. However, when it comes to personnel lessons learned, the information should be handled in a confidential manner. [Closing]

Meredith and Mantel 2012, 570

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. At the time the risk register is first prepared, it should contain all the following entries EXCEPT—
    a. Root causes of risk
    b. Structure for describing risks
    c. List of risks requiring near-term responses
    d. List of potential responses
A
  1. c. List of risks requiring near-term responses

The primary outputs from identify risks are initial entries into the risk register. It ultimately contains outcomes of other risk management processes as they are conducted. As an output of identify risks, the risk register should contain a list of identified risks, a list of potential responses, root causes that gave rise to the identified risks, and a structure for describing risks. [Planning]

PMI®, PMBOK® Guide, 2013, 327

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Which of the following theorists stated that people generally are motivated according to the strength of their desire either to achieve high levels of performance or to exceed in competitive situations?
    a. David McGregor
    b. David McClelland
    c. Victor Vroom
    d. B. F. Skinner
A
  1. b. David McClelland

According to David McClelland, there are three relevant motives or needs in work situations: the need for achievement, power, and affiliation or association. This theory supports the view that there is a high correlation between achievement, affiliation, and power motives and the overall motivation and performance achieved in a project. [Executing]

Verma 1996, 68

Levin, 2010, 88–91

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Your project is considered very risky. You plan to perform numerous what-if scenarios on your schedule using simulation software that will define each schedule activity and calculate a range of possible durations for each activity. The simulation then will use the collected data from each activity to calculate a distribution curve (or range) for the possible outcomes of the total project. Your planned approach is an example of which following technique?
    a. PERT
    b. Monte Carlo analysis
    c. Linear programming
    d. Concurrent engineering
A
  1. b. Monte Carlo analysis

Simulation is a tool and technique for the develop schedule process by which multiple project durations with different sets of activity assumptions are calculated. Monte Carlo analysis is the most commonly used simulation technique. [Planning]

PMI®, PMBOK® Guide, 2013, 180, 340, 562

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Project execution must be compared, and deviations must be measured for management control according to the—
    a. Scope baseline
    b. Performance measurement baseline
    c. Schedule baseline
    d. Control system
A
  1. b. Performance measurement baseline

The PMB is an approved, integrated scope-schedule-cost plan for the project work against which project execution is compared in order to measure and manage performance. It includes contingency reserve but not management reserve. It typicallyintegrates scope, schedule, and cost parameters of the project, but it may also include technical and quality parameters. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 302, 549

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. A number of items may be part of the schedule data for the project. The amount of additional detail will vary, but the data should include all the following items EXCEPT—
    a. Schedule activities
    b. Activity attributes
    c. Identified assumptions
    d. Resource breakdown structure
A
  1. d. Resource breakdown structure

Schedule data for the project schedule includes a number of items as it collects the information used to describe and control the schedule. It includes schedule milestones, schedule activities, activity attributes, and assumptions and constraints. It may include resource histograms, alternate schedules, contingencyreserves cash-flow projections, and order and deliveryschedules [Planning]

PMI®, PMBOK® Guide, 2013, 184, 191, and 561

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. If a team member, when facing schedule delays and cost overruns, develops several alternatives for completing the project successfully on schedule and within budget and asks questions such as, “Can we do it?,” “If we do it what are the consequences?,” and “Is it really worth the effort involved?,” he or she is primarily motivated by the—
    a. Contingency Theory
    b. Expectancy Theory
    c. Reinforcement Theory
    d. Equity Theory
A
  1. b. Expectancy Theory

Developed by Victor Vroom, Expectancy Theory asserts that people think seriously about how much effort they should put into a task before doing it. Motivation is linked to an expectation of a favorable outcome. It is based on the concept that people choose behaviors that they believe will lead to desired rewards and outcomes. [Executing]

Verma 1996, 73

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Which tool or technique is NOT used for schedule control?
    a. Performance reviews
    b. Project management software
    c. Work performance information
    d. Leads and lags
A
  1. c. Work performance data

Work performance data is an input to control schedule. [Planning]

PMI®, PMBOK® Guide, 2013, 185

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. All the following are examples of project document updates from the manage project team process EXCEPT—
    a. Issue log
    b. Roles description
    c. Project staff assignments
    d. Personnel skills
A
  1. d. Personnel skills

Personnel skill updates are an example of an enterprise environmental factor that may require updates as a result of the manage project team process along with inputs to the organizational performance appraisals. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 285

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Recording and reporting information regarding when appropriate configuration information should be provided and regarding the status of proposed and approved changes effectively is done through—
    a. Configuration status accounting
    b. Configuration verification and audit
    c. Project management methodology
    d. A project management information system (PMIS)
A
  1. a. Configuration status accounting

Configuration status accounting captures, stores, and accesses the needed configuration information to manage products and product information effectively. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 97

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. Decomposition is a technique used to break larger, complex items into smaller and more manageable items. Which following statement best describes the role decomposition plays in creating the WBS?
    a. Final output of creating the WBS is described in terms of phases of a project life cycle.
    b. Final output of creating the WBS is described in terms of schedule activities.
    c. Final output of creating the WBS is described in terms of verifiable products, services, or results.
    d. Final output of creating the WBS is described in terms of the scope of the project.
A
  1. c. Final output of creating the WBS is described in terms of verifiable products, services, or results.

By using decomposition, the upper-level WBS components are subdivided for the work for each of the deliverables or subcomponents into its most fundamental elements, where the WBS components then represent verifiable products, service, or results. [Planning]

PMI®, PMBOK® Guide, 2013, 131

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. The schedule management plan is a key document. It is—
    a. An output of the develop schedule process
    b. A tool and technique used in the develop schedule process
    c. The first time management process
    d. A separate planning effort completed in conjunction with the time management processes
A
  1. c. The first time management process

The schedule management plan is the output of plan schedule management, the first of the seven time management processes. It is a subsidiary plan to the project management plan. [Planning]

PMI®, PMBOK® Guide, 2013, 143

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. Activity attributes are used to extend the description of the activity and to identify its multiple components. In the early stages of the project, an example of an activity attribute is—
    a. Activity codes
    b. Activity description
    c. Predecessor and successor activities
    d. Activity name
A
  1. d. Activity name

The components for each activity evolve over time. In the initial stages of the project, they include the activity ID, WBS ID, and the activity name. Later, additional information is added as other time management processes are performed. [Planning]

PMI®, PMBOK® Guide, 2013, 153

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
  1. You are working on a new project in your city to construct an environmentally friendly landfill. The existing site is so undesirable that many residents have moved to other neighboring cities because of their proximity to it. However, even though the project has the support of the public, you need to have a number of hearings of the city’s government before you are authorized to begin work. As you are in the planning phase of the project, you are waiting for these hearings to be scheduled and held before you can begin site preparation. These hearings are an example of—
    a. A milestone
    b. An external dependency
    c. An item to be scheduled as a fragnet
    d. A mandatory dependency
A
  1. b. An external dependency

Some dependencies are external ones, and they involve a relationship between project activities and nonproject activities. In sequencing activities, the project management team must determine which dependencies are external as they are usually outside of the team’s control. [Planning]

PMI®, PMBOK® Guide, 2013, 158

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  1. You are working on a project and want to know how many activities in the previous month were completed with significant variances. You should use a(n)—
    a. Control chart
    b. Inspection
    c. Scatter diagram
    d. Trend analysis
A
  1. d. Trend analysis

Trend analysis is used in many control processes in project management. The trend analysis examines the performance of the project over time to determine whether performance is improving or deteriorating. Graphical analysis techniques are valuable in trend analysis to understand performance to date and to compare it to future performance goals in the form of completion dates. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 188

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
  1. Your project has a budget of $1.5 million for the first year, $3 million for the second year, $2.2 million for the third year, and $800,000 for the fourth year. Most of the project budget will be spent during—
    a. Starting the project
    b. Organizing and preparing
    c. Carrying out the work
    d. Closing the project
A
  1. c. Carrying out the work

The implementation phase (carrying out the work) is when all interfaces affecting the project must be coordinated and when the product or service of the project is created. In most projects, this phase is also where a large portion of the project budget is spent. [Executing]

PMI®, PMBOK® Guide, 2013, 56

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
  1. If you decide to follow an open subordination approach to resolving conflict, you are using which style of conflict resolution?
    a. Avoiding
    b. Accommodating
    c. Compromising
    d. Collaborating
A
  1. b. Accommodating

Open subordination is much like an accommodating or smoothing style of conflict management in which negotiators are more concerned about positive relationships than about substantive outcomes. It can dampen hostility, increase support and cooperation, and foster more interdependent relationships. This is an effective style for project managers to use with support staff. It concedes one’s position to the needs of others to maintain harmony and relationships. [Executing]

Verma 1996, 157

PMI®, PMBOK® Guide, 2013, 283

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q
  1. Typically, the seller receives formal written notice that the contract has been completed by the—
    a. Project manager
    b. Authorized procurement administrator
    c. Member of the project management team responsible for daily contract administration
    d. Purchasing department head
A
  1. b. Authorized procurement administrator

The buyer, through its authorized procurement administrator, is responsible for providing the seller with formal written notice of contract completion. The procurement administrator does so when the seller has met all contractual requirements as articulated in the contract. [Closing]

PMI®, PMBOK® Guide, 2013, 389

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q
  1. Working in the control procurements process since your project is using five contractors, you need to update a number of organizational process assets. An example is—
    a. Procurement management plan
    b. Procurement documentation
    c. Correspondence
    d. Warranties
A
  1. c. Correspondence

Contract terms and conditions often require written documentation of certain aspects of buyer/seller communications. Examples include any warnings of unsatisfactory performance and requests for changes in the contract or clarification. Other organizational process assets to update include payment schedules and requests and seller performance evaluation documentation. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 386

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q
  1. You are beginning a new project staffed with a virtual team located across five different countries. To help limit conflict and misunderstandings concerning the justification, objectives, and high-level requirements of the project among your team members and their functional managers, you ask the project sponsor to prepare a—
    a. Memo to team members informing them that they work for you now
    b. Project charter
    c. Memo to functional managers informing them that you have authority to direct their employees
    d. Human resource management plan
A
  1. b. Project charter

Although the project charter cannot stop conflicts from arising, it can provide a framework to help resolve them, because it describes the project manager’s authority to apply organizational resources to project activities. The project charter also documents the business needs, justification, objectives, and high-level requirements of the project. [Initiating]

Meredith and Mantel 2012, 228–229

PMI®, PMBOK® Guide, 2013, 71–72

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q
  1. To anticipate and help develop approaches to deal with potential quality problems on your project, you want to use a variety of root-cause analysis techniques including all the following approaches EXCEPT—
    a. Fishbone diagrams
    b. Ishikawa diagrams
    c. System or process flowcharts
    d. Checklists
A
  1. d. Checklists

Checklists are used to verify that the work of the project and its deliverables fulfill a set of requirements. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 242 and 250

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
  1. All of the following are examples of ways to generate options for mutual gain during negotiations EXCEPT—
    a. Separating inventing from deciding
    b. Options broadening
    c. Zero-sum game analysis
    d. Multiplying options by shuttling between the specific and the general
A
  1. c. Zero-sum game analysis

Achieving mutual gain during negotiations means that each party benefits by the decisions made. A zero-sum game is where one side wins at the expense of the other. [Executing]

Ward 2008, 474

PMI®, PMBOK® Guide, 2013, 517

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q
  1. Recently, your company introduced a new processing system for its products. You were the project manager for this system and now have been asked to lead a team to implement needed changes to increase efficiency and productivity. To help you analyze the process outputs, you and your team have decided to use which following technique?
    a. System flowcharts
    b. Design of experiments
    c. Pareto analysis
    d. Control charts
A
  1. d. Control charts

Control charts help to determine whether or not a process is stable or has predictable performance. This function of control charts is achieved through the graphical display of results over time to determine whether differences in the results are created by random variations or are unusual events. In a manufacturing environment, such charts are used to track repetitive actions such as manufactured lots. In a project management environment, they can be used to monitor processes such as cost and schedule variances, number requirements, and errors in project documents. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 238

31
Q
  1. Effective leadership is one key to successful project management. There are several theories of leadership. One model is Hershey and Blanchard’s situational leadership model that describes directive behavior and supportive behavior. Of the following, which one is NOT a key word for supportive behavior?
    a. Listen
    b. Structure
    c. Praise
    d. Facilitate
A
  1. b. Structure

Supportive behavior is relationship oriented and is the extent to which the leader engages in two-way communication, listens, provides support and encouragement, facilitates interaction, and involves the followers in decision making. Structure connotes a certain level of rigidity and inflexibility and is not a term associated with supportive behavior. [Executing]

Verma 1996, 216–217

Kerzner, 2009, 222–223

32
Q
  1. Based on quality control measurements on your manufacturing project, management realizes that immediate corrective action is required to the material requirements planning (MRP) system to minimize rework. To implement the necessary changes you should follow—
    a. The organization’s quality policy
    b. The quality management plan
    c. Established operational definitions and procedures
    d. A defined integrated change control process
A
  1. d. A defined integrated change control process

If the recommended corrective or preventive actions or a defect repair require a change to any of the project management plans, a change request should be prepared in conformance with the perform integrated change control process. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 253

33
Q
  1. You are the project manager on a project to improve traffic flow in the company’s parking garage. You decide to use flowcharting to—
    a. Help anticipate how problems occur
    b. Show dependencies between tasks
    c. Show the results of a process
    d. Forecast future outcomes
A
  1. a. Help anticipate how problems occur

Flowcharts depict the interrelationship of a system’s components and show the relationships among process steps. They are often referred to as process maps as they display the sequence of steps and the branching possibilities for a process that transforms one or more inputs into one or more outputs. Flowcharts show activities, decision points, branching loops, parallel paths, and the order of processing. As such, they aid the team in anticipating where quality problems might occur, which helps in developing approaches for dealing with these potential problems. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 236

34
Q
  1. Successful project management involves both project leadership as well as project management skills. Several different leadership styles are appropriate in different phases of the project life cycle. Assume that you are working on a project, and it is in the execution phase. The leadership style that is most appropriate should consist of a blend of all but which one of the following?
    a. Change master
    b. Decision maker
    c. Team and synergy
    d. Trustworthiness
A
  1. a. Change master

During the execution stage, the major attributes and emphasis is on realignment. The leadership style/blend that is most appropriate is one who is a decision maker, balances work and fun, is trustworthy, and promotes the team concept and synergy. [Executing]

Verma 1996, 225

35
Q
  1. Schedule control is one important way to avoid delays. While planning and executing schedule recovery, one tool available to you for control schedules is—
    a. Changing the schedule management plan
    b. Immediately rebaselining
    c. Adjusting leads and lags
    d. Changing all project and resource calendars
A
  1. c. Adjusting leads and lags

Corrective action is anything that brings expected future schedule performance in line with the project plan. Adjusting leads and lags is one of many tools available to identify the cause of variation. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 190

36
Q
  1. You have been the project manager for your nuclear submarine project for four years. While you did not assume this position until the project management plan had been prepared and approved, you find you spend a significant amount of time collecting data and communicating. You also spend time reviewing the impact of project changes and implementing ones that have been approved. Often you have had to modify a non-conforming product, which means you are spending time on—
    a. Corrective actions
    b. Updating the project’s requirements
    c. Updating the traceability matrix
    d. Defect repair
A
  1. d. Defect repair

Defect repair is an intentional activity to modify a nonconforming product or project component. [Executing]

PMI®, PMBOK® Guide, 2013, 81

37
Q
  1. You were assigned recently as the project manager of a program management office project to implement a new enterprise-wide scheduling system for use throughout your company. You identify the need for a project charter to provide you with appropriate authority for applying resources, completing the project work, and formally initiating the project. Who should issue the project charter?
    a. The project manager—you
    b. The customer
    c. The person who formally authorizes the project
    d. A member of the training and development department as they will own the training on the new system
A
  1. c. The person who formally authorizes the project

The charter is issued by the project initiator or sponsor who formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. [Initiating]

PMI®, PMBOK® Guide, 2013, 71

38
Q
  1. In which of the following methods of resolving conflict will the conflict typically reappear again in another form?
    a. Smoothing
    b. Compromising
    c. Collaborating
    d. Confronting
A
  1. a. Smoothing

Smoothing emphasizes areas of agreement while avoiding points of disagreement. It tends to keep peace only in the short term. [Executing]

Adams et al. 1997, 181–189

Verma 1996, 118

PMBOK® Guide, 2013, 283

39
Q
  1. Statistical sampling is a method in perform quality control to determine the conformance to requirements for some component or product of a project. Its greatest advantage is that it—
    a. Does not require a large expenditure of resources
    b. Is accurate enough with a sampling of less than 1%
    c. Does not require 100% inspection of the components to achieve a satisfactory inference of the population
    d. Needs to be conducted only when a problem is discovered with the end product or when the customer has some rejects
A
  1. c. Does not require 100% inspection of the components to achieve a satisfactory inference of the population

The application of the statistical concept of probability has proven, over many years in many applications, that an entire population of products need not be inspected, if the sample selected conforms to a normal distribution of possible outcomes (the “bell” curve). Sample frequency and sizes should be determined as the quality management plan is prepared in order that the cost of quality includes the number of tests and expected scrap. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 240 and 252

40
Q
  1. Your project sponsor wants to know whether process variables are within acceptable limits. To answer this question, you should—
    a. Conduct a process analysis
    b. Conduct a root cause analysis
    c. Use a control chart
    d. Use a run chart
A
  1. c. Use a control chart

A control chart is one of the seven basic tools of quality control that determines whether or not a process is stable or has predictable performance. It also illustrates how a process behaves over time. When a process is within acceptable limits, it need not be adjusted; when it is outside acceptable limits, an analysis should be conducted to determine the reasons why. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 238

41
Q
  1. All the following statements are true about the grassroots estimate, EXCEPT—
    a. Its accuracy rate is from –5% to +10%
    b. It is also called an engineering estimate
    c. It is used primarily for Level 1 of the WBS
    d. It may take months to prepare
A
  1. c. It is used primarily for Level 1 of the WBS

Estimates are categorized according to accuracy and the time to prepare them. Grassroots or engineering-type estimates are definite estimates and are prepared when detailed information about the project is available. These estimates would use the work-package level of the WBS. [Planning]

Kerzner 2009, 574

PMI®, PMBOK® Guide, 2013, 201

42
Q
  1. You are planning a project and want to account for how the project will be managed in the future. While building your cost performance data, you want to provide guidance for when the project is later executed, because you know that different responses are required depending upon the degree of variance from the baseline. For example, a variance of 10 percent might not require immediate action, whereas a variance of 20 percent will require more immediate action and investigation. You decide to include the details of how to manage the cost variances as part of which following plan?
    a. Cost management plan
    b. Change management plan
    c. Performance measurement plan
    d. Variance management plan
A
  1. a. Cost management plan

The management and control of costs focuses on variances. Certain variances are acceptable, and others, usually those falling outside a particular range, are unacceptable. The actions taken by the project manager for all variances are described in the cost management plan. [Planning]

PMI®, PMBOK® Guide, 2013, 198–199

43
Q
  1. Assume that you are managing a project team. Your team is one in which its members confront issues rather than people, establish procedures collectively, and is team oriented. As the project manager, which of the following represents your team’s stage of development and the approach you should use during this time?
    a. Storming; high directive and supportive approach
    b. Norming; high directive and low supportive approach
    c. Norming; high supportive and low directive approach
    d. Performing; low directive and supportive approach
A
  1. c. Norming; high supportive and low directive approach

There are four stages of team development: forming, storming, norming, and performing. Different leadership styles in terms of the amount of required supportive and directive behavior are appropriate when a team is in a certain development stage. At the norming stage, the third stage in team development, leaders provide high support and low direction. [Executing]

Verma 1996, 227

PMI®, PMBOK® Guide, 2013, 276

44
Q
  1. You are finalizing all the contracts and ensuring that they are closed. The close procurements process involves all the following administrative actions EXCEPT—
    a. The procurement administrator is reassigned
    b. Finalizing open claims
    c. Updating the project records to show the final contractresults
    d. Archiving the contracts and contract records for future use
A
  1. a. The procurement administrator is reassigned

The close procurements process looks at the administration of the contract and not the people responsible or involved with the contract. [Closing]

PMI®, PMBOK® Guide, 2013, 387

45
Q
  1. You are working on a project and want to identify the cause of problems in a process by the shape and width of the distribution of the process variables. You should use a—
    a. Histogram
    b. Pareto chart
    c. Scatter diagram
    d. Trend analysis
A
  1. a. Histogram

In a histogram, or a special form of bar chart, each column represents an attribute or characteristic of a problem or situation. The height of each column represents the relative frequency of the characteristic. It describes the central tendency, dispersion, or shape of a statistical distribution. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 238

46
Q
  1. You are working on a construction project in a city different from your headquarters’ location. You and your team have not worked in this city, City B, previously, and you lack knowledge of the local building codes. You had a team member review the codes, and he said they were in far greater detail than those in your city, City A. When you asked him how much time he would need to spend to gain a complete understanding of these codes, he estimated that at least five weeks would be needed. You then decided it would be more cost effective to hire a local person from City B who specializes in this area. As a result, as you prepare your schedule and estimate your resource requirements for this project, you should coordinate this work closely with which of the following processes:
    a. Estimate costs
    b. Define activities
    c. Determine budgets
    d. Develop schedule
A
  1. a. Estimate costs

The estimate activity resources process involves estimating the type and quantities of material, people, equipment, or supplies needed to perform each activity. This means close coordination with the estimate costs process is needed. [Planning]

PMI®, PMBOK® Guide, 2013, 141, 162

47
Q
  1. Assume that you were the first person in your company to be PMP® certified and also that you earned a doctorate in project management. People throughout the organization admired your achievements. Based on your success in managing projects, your company now has adopted a management-by-projects philosophy. You have been appointed head of your company’s project management office to lead the organization as it transitions to this new way of working. So far, people seem to willingly comply with your demands and requests. In this situation, you are using which type of power?
    a. Legitimate
    b. Expert
    c. Contacts
    d. Referent
A
  1. a. Legitimate

Legitimate power is formal authority based on a person’s position within the organization. It comes with the right to give orders or make requests. [Executing]

Adams et al. 1997, 174–180

Verma 1996, 233

Levin 2010, 161–162

48
Q
  1. The nature of project work is such that it inevitably causes stress. Project managers thus need to learn how to cope with and manage stress and understand what stress is and why it is created. Project managers need to note that it can be a positive experience depending on how people perceive stress and should work to mentorteam members accordingly. As you strive to become more aware of stress, which one of the following is NOT considered a stress-creating factor that is related to the project environment?
    a. Role ambiguity
    b. Corporate politics
    c. Career development
    d. Selection of team members
A
  1. a. Role ambiguity

The main sources of stress are grouped into four categories of stress-creating factors: those related to roles and relationships, those related to the job environment, personal factors, and factors related to the project environment or climate. Role ambiguity is an example of factors related to roles and responsibilities. It occurs when an individual is not clear about his or her job responsibilities. [Monitoring and Controlling]

Verma 1996, 180, 183–184; Levin, 2010, 176–183

49
Q
  1. Assume you are working as the project manager on the first project in your company to use the critical chain approach to scheduling. You are a PMP® and also are certified in critical chain. You are getting ready for a performance review with your Governance Board, and you can expect they will ask questions about—
    a. The magnitude of variance against the schedule baseline
    b. Schedule risk
    c. Performance to date since the past review meeting
    d. The buffer needed and buffer remaining
A
  1. d. The buffer needed and the buffer remaining

Critical chain is an approach in scheduling in which the project team can place buffers on any project schedule path to account for limited resources and project uncertainties. During a performance review, comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date can help to determine schedule status. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 180, 189

50
Q
  1. You are in the early stages of a project to manufacture disposable medical devices. You need a number of engineers including ones with specialties in mechanical, environmental, and systems engineering. In the early stages of this project, your resource pool includes a large number of both junior and senior engineers in the various specialty areas. However, as the project progresses—
    a. Fewer systems engineers will be needed
    b. The resource pool can be limited to those people who are knowledgeable about the project
    c. To complete the project on time, you will continue to require access to a large number of engineers in their specialty areas
    d. You will only need junior level engineers as the senior level people can be used early in the project to mentor and train them
A
  1. b. The resource pool can be limited to those people who are knowledgeable about the project

Resource calendars are an input to the estimate activity resource process and to the estimate activitydurations process. They are used to estimate resource use. Early in a project, the resource pool might include people at different levels of expertise in large numbers, but as the project progresses, the resource pool then can be limited to those people who are knowledgeable about the project because of their work on it. [Planning]

PMI®, PMBOK® Guide, 2013, 163, 167–168

51
Q
  1. A number of approaches can be helpful when estimating resource requirements for activities on a project. Assume you are managing a project and you have already prepared your WBS. When you decomposed your WBS, it has 45 work packages. You then prepared an activity list. Now, you are preparing your schedule and determining your resource requirements. You found there were about 30 activities that you could not estimate with a reasonable degree of confidence, so you and your team decided to use which one of the following approaches to help with these activity resource estimates:
    a. Resource breakdown structure
    b. Published estimating data
    c. Alternatives analysis
    d. Bottom-up estimating
A
  1. d. Bottom-up estimating

When an activity cannot be estimated with a reasonable degree of confidence, the work then needs to be decomposed into more detail. The estimates then are aggregated into a total quantity for each of the activity’s resources through a bottom-up approach. These activities may or may not have dependencies between them. However, when dependencies exist, this pattern of use of resources then is documented in the estimated requirements for each activity. [Planning]

PMI®, PMBOK® Guide, 2013, 164

52
Q
  1. To practice effective schedule control, your project team must be alert to any issues that may cause problems in the future. To best accomplish effective schedule control, the team should—
    a. Review work performance information
    b. Allow no changes to the schedule
    c. Update the schedule management plan on a continuous basis
    d. Hold status reviews
A
  1. a. Review work performance information

The calculated SV and SPI time performance indicators for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders as an outputof the control schedule process. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 190

53
Q
  1. Functional managers play a vital role in ensuring project success. Since most projects operate in a matrix environment, there is shared authority between project managers and functional managers. Functional managers tend to focus on—
    a. Who will do the task
    b. Why the project manager needs resources
    c. How much time and money is available for the task
    d. Why will the task be done
A
  1. a. Who will do the task

In a matrix environment, project resources (that is, people) come from the functional departments. Therefore, it is the functional manager’s job to identify who will work on specific project tasks. [Executing]

Verma 1995, 56–57

PMI®, PMBOK® Guide, 2013, 37

54
Q
  1. You are a member of a project selection committee that uses the net present value technique. Using this approach, the project is acceptable if the—
    a. Sum of the net present value of all estimated cash flow during the life of the project equals the profit
    b. Net present value of the inflow is greater than the specified amount or percentage threshold
    c. Gross present value of all future expected cash flow divided by the initial cash investment is greater than one
    d. Net present value of the inflow is less than the specified amount or percentage threshold
A
  1. b. Net present value of the inflow is greater than the specified amount or percentage threshold

The discounted cash-flow approach—or the present value method—determines the net present value of all cash flow by discounting it by the required rate of return. The impact of inflation can be considered. Early in the life of a project, net cash flow is likely to be negative because the major outflow is the initial investment in the project. If the project is successful, cash flow will become positive. [Initiating]

Meredith and Mantel 2012, 51

55
Q
  1. A watch list of low priority risks is documented in the—
    a. Work performance information
    b. Risk register
    c. Fallback plans
    d. Risk response plan
A
  1. b. Risk register

The monitor and control risks process includes keeping track of those risks on the watch list. Low-priority risks are inputs to the monitor and control risks process and are documented in the risk register. Other inputs that are part of the risk register include identified risks and risk owners, agreed-upon risk responses, control actions to assess the effectiveness of response plans, specific implementation actions, symptoms and warning signs of risk, residual and secondary risks, and the time and cost contingency reserves. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 350

56
Q
  1. You are the project manager for a major logistics installation project and must obtain specific services from local sources external to your project. Your subcontracts administrator has told you to prepare a product or service description, which is referenced in a—
    a. Project statement of work
    b. Contract scope statement
    c. Request for proposal
    d. Contract
A
  1. a. Project statement of work

The project statement of work describes in a narrative form the products, services, or results that the project will deliver. It references the product scope description as well as the business need and strategic plan. [Initiating]

PMI®, PMBOK® Guide, 2013, 68

57
Q
  1. It often is advantageous to appoint a termination manager in the closing phase of the project and release the project manager so that he or she is available to work on another project. If this is the case, the termination manager should focus attention on all but which one of the following?
    a. Ensuring that documentation is complete
    b. Ascertaining any product support requirements
    c. Receiving formal acceptance of the project from the client
    d. Preparing personnel performance evaluations
A
  1. d. Preparing personnel performance evaluations

The project manager, or whoever supervised the work of each individual team member, should prepare the personnel evaluations because they have an intimate understanding of the work performed by the team members. The termination manager focuses instead on the administrative requirements of termination and the environment within which the project will be operating if it is continued in any way. [Closing]

Meredith and Mantel 2012, 564–566

58
Q
  1. You are working on a project to upgrade the existing fiber-optic cables in your province. You have determined that a resource can install 25 meters of cable per hour, so the duration required to install 1,000 meters would be 40 hours. This means you are using—
    a. Productivity efficiency factors
    b. Parametric estimating
    c. Analogous estimating
    d. PERT
A
  1. b. Parametric estimating

Parametric estimating uses statistical relationships between historical data and other variables to calculate an estimate for activity parameters such as cost, budget, and duration. The activity durations then are determined quantitatively by multiplying the quantity of work to be performed by the labor hours per unit of work. This technique can produce higher levels of accuracy depending on the reliability of the data in the model. [Planning]

PMI®, PMBOK® Guide, 2013, 170

59
Q
  1. During the stages of team development, your team is in which stage when there is problem solving and interdependence along with achievement and synergy?
    a. Storming
    b. Forming
    c. Norming
    d. Performing
A
  1. d. Performing

The performing stage of team development is noted by a theme of productivity. Management skills involve consensus building, problem solving, decision making, and rewarding, with leadership shown through management by walking around, stewardship delegation, mentoring, being a futurist, and being a cheerleader/champion. [Executing]

Verma 1997, 40

PMI®, PMBOK® Guide, 2013, 276

  1. b. Terms and conditions in the contract

The terms and conditions can prescribe specific procedures for the various ways that a contract could be terminated. [Closing]

PMI®, PMBOK® Guide, 2013, 378, 387

60
Q
  1. When you are about to terminate a contract, the one place to look for specific procedures for contract closure is in the—
    a. Statement of work in the contract
    b. Terms and conditions in the contract
    c. Product description
    d. Organizational process assets
A
  1. b. Terms and conditions in the contract

The terms and conditions can prescribe specific procedures for the various ways that a contract could be terminated. [Closing]

PMI®, PMBOK® Guide, 2013, 378, 387

61
Q
  1. Today, the primary cause of why projects are not completed on time and within cost and are terminated early is due to—
    a. Contractual issues
    b. Complexity of the project
    c. An increase in the allocated time
    d. Behavioral-oriented reasons
A
  1. d. Behavioral-oriented reasons

Behavioral reasons, rather than quantitative reasons, account for more project terminations because it is much more difficult to manage people than things. Issues such as poor morale, poor human relations, poor labor productivity, and no commitment from those involved in the project combine to thwart project success in many industries. [Closing]

Kerzner 2009, 452–453

62
Q
  1. Life-cycle phase definitions are different in different industries. For example, all of the following are terms that could be used in the closing phase of a project EXCEPT—
    a. Testing and commissioning
    b. Conversion
    c. Implementation
    d. Final audit
A
  1. c. Implementation

Regardless of the many terms used across many industries, implementation would be considered a term used in the executing phase in which the work is carried out and done. [Closing]

Kerzner 2009, 69

PMI®, PMBOK® Guide, 2013, 39

63
Q
  1. Your company is embarking on a project to launch a new product delivery service. You are the project manager for this project and have just finished the concept phase. The various outputs/deliverable(s) for this phase include—
    a. Project management plan
    b. Scope of work and requirements
    c. Project charter and stakeholder register
    d. Roles and responsibilities of the project manager
A
  1. c. Project charter and stakeholder register

The project charter signifies official sanction by top management and starts the planning, or development, phase. This document formally recognizes the existence of the project and provides the projectmanager with the authority to apply organizational resources to project activities. The stakeholder registeris an output of identify stakeholders and also an output during the initiating processes. [Initiating]

PMI®, PMBOK® Guide, 2013, 71–72, 398

64
Q
  1. Behavior roles of team members influence the team’s process, behavior, and effectiveness. An example of a task-oriented role to perform is that of a(n)—
    a. Harmonizer
    b. Initiator
    c. Devil’s advocate
    d. Group observer
A
  1. b. Initiator

To initiate something means to get it started. In the project environment, that typically means a task. [Executing]

Verma 1997, 78–79

65
Q
  1. You are managing a project in which your team members all work in the same geographic location and have worked together previously on many projects. Everyone is aware of the various strengths and weaknesses of the individual team members and their key areas of expertise. As a result—
    a. A kickoff meeting is recommended
    b. Team-building activities will not be needed on your project
    c. You should expect minimal conflicts and changes to occur
    d. Rewards and recognition will be handled smoothly throughout the project
A
  1. a. A kickoff meeting is recommended

Even if team members already know one another, a kickoff meeting should still be held because the meeting always includes more than meeting team members. Specific expectations for the project can be discussed as well as other important administrative details. It also gives people an opportunity to express their commitment to the project’s objectives. [Executing]

Verma 1997, 135

Meredith and Mantel, 2012, 224–225

66
Q
  1. Team building should be ongoing throughout the project life cycle. However, it is hard to maintain momentum and morale, especially on large, complex projects that span several years. One guideline to follow to promote team building is to—
    a. Consider every meeting a team meeting, not the projectmanager’s meeting
    b. Conduct team building at specific times during the project through off-site meetings
    c. Engage the services of a full-time facilitator before any team-building initiatives are conducted
    d. Develop the project schedule using the services of a project control officer and then issue it immediately to the team
A
  1. a. Consider every meeting a team meeting, not the project manager’s meeting

Team building should be made as important a part of every project activity as possible. Given that there are many meetings on projects, each team member should be made to feel that it is his or her meeting and not just the project manager’s meeting. This will foster greater contribution by each team member. [Executing]

Verma 1997, 137

PMI®, PMBOK® Guide, 2013, 278

67
Q
  1. You have been assigned as the project manager for a major project in your company where the customer and key supplier are located in another country. You have been working on your project for six months. Recently, you traveled to this country, and at the conclusion of a critical design review meeting, which was highly successful, you realized you were successful in building a high-performing team. You had your own team members, who work in a weak matrix structure, on a conference call during this meeting. Although it was difficult to reach agreement on some key issues, you therefore relied on your interpersonal skills in—
    a. Facilitation
    b. Negotiating
    c. Influencing
    d. Decision making
A
  1. c. Influencing

All are useful skills for project managers. In this situation influencing was necessary as the project manager has little or no direct control over tem members as they work in a weak matrix. The ability of the project manager to influence stakeholders in a timely basis is critical to project success. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 284

68
Q
  1. You are leading a team to review and improve the project selection and prioritization method. You know that the two most important questions to answer are “can we do the project?” (feasibility study) and “should we do the project?” (cost-benefit analysis). The team is considering many different management concerns, including financialreturn, market share, and public perception. The most important criterion for building a project selection model is—
    a. Risks
    b. Realism
    c. Ease of use
    d. Benefits realization
A
  1. b. Realism

A project selection model should reflect the objectives of the company and its managers; consider the realities of the organization’s limitations on facilities, capital, and personnel; and include factors for risk—the technical risks of performance, cost, and time as well as the market risk of customer rejection. [Initiating]

Meredith and Mantel 2012, 64–65

69
Q
  1. Because risk management is relatively new on projects in your company, you decide to examine and document the effectiveness of risk responses in dealing with identified risks and their root causes. You therefore—
    a. Conduct a risk audit
    b. Hold a risk status meeting
    c. Ensure that risk is an agenda item at regularly scheduled staff meetings
    d. Reassess identified risks on a periodic basis
A
  1. a. Conduct a risk audit

The risk audit is a tool and technique in the control risks process with two purposes: to assess the effectiveness of risk responses and to evaluate the effectiveness of the risk management process. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 351

70
Q
  1. Thinking back to lessons that your company learned from experiences with its legacy information systems during the Y2K dilemma, you finally convinced management to consider systems maintenance from the beginning of the project. However, maintenance should—
    a. Always be included as an activity to be performed during the closeout phase
    b. Have a separate phase in the life cycle for information systems project because 60% to 70% of computer systems’ life-cycle costs generally are devoted to maintenance
    c. Not be viewed as part of the project life cycle
    d. Be viewed as a separate project
A
  1. c. Not be viewed as part of the project life cycle

Projects are efforts that occur within a finite period of time with clearly defined beginnings and ends. Maintenance is ongoing and of an indefinite duration. A maintenance activity, such as revision of an organization’s purchasing guidelines, may be viewed as a project but is a separate and distinct undertaking from the initial project that generated it. At this point, the project has been completed, and its deliverables are transferred to operations for implementation. [Initiating]

Frame 2003, 16–17

PMI®, PMBOK® Guide, 2013, 13

71
Q
  1. On your systems development project, you noted during a review that the system had less functionality than planned at the critical design review. This note suggests that duringthe control risks process you used which following tools and techniques?
    a. Risk reassessment
    b. Variance analysis
    c. Technical performance measurement
    d. Reserve analysis
A
  1. c. Technical performance measurement

Technical performance measurement compares technical accomplishments to date to the project plan’s schedule of technical achievement. Deviation, such as less functionality than planned at a key milestone, can help to forecast the degree of success in achieving the project scope. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 352

72
Q
  1. The workaround that you used to deal with a risk that occurred should be documented and included in which following processes?
    a. Report performance and monitor and control risks
    b. Validate scope and perform quality assurance
    c. Direct and manage project work and perform integrated change control
    d. Monitor and control project work and control risks
A
  1. d. Monitor and control project work and control risks

A workaround is a form of corrective action, as it is a response to a threat that has occurred for which a prior response had not been planned or was not effective. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 93, 353, and 567

73
Q
  1. Contested changes are requested changes when the buyer and seller cannot agree on compensation for the change. They are also known as all but which one of the following?
    a. Disputes
    b. Demands
    c. Appeals
    d. Claims
A
  1. b. Demands

Claims administration is a tool and technique in the control procurements process. When the buyer and seller cannot agree, this is also called claims, disputes, or appeals and should be documented, processed, monitored, and managed throughout the contract life cycle. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 384

74
Q
  1. A structured review of the seller’s progress to deliver projectscope and quality within cost and schedule is known as a(n)—
    a. Procurement performance review
    b. Procurement audit
    c. Inspection
    d. Status review meeting
A
  1. a. Procurement performance review

These reviews are a tool and technique of the control procurements process, which can include a review of seller-prepared documentation and buyer inspections. They seek to identify performance successes or failures, progress with respect to the contract statement of work and contract noncompliance. [Monitoring and Controlling]

PMI®, PMBOK® Guide, 2013, 383