Misc. Flashcards
Ufer is to be #_______.
4
Ufer is to be a minimum of ________ feet in length. Extend ______ feet up out of the footing.
25’
5’
The ufer should be supported ________ inches up off the soil.
1 1/2”
What goes on the end of the ufer (the end out of the slab)?
Shepherds hook
What’s the minimum diameter for a bollard post?
3”
What’s the minim height on a bollard post?
5’2”
What schedule steel is the bollard post?
Schedule 40 steel
What’s the minimum embedment of the bollard post?
And what is the minimum size footing?
18”
16” X 16” X 20”
The bollard post is to be plumb within _______ of an inch.
1/4”
The bollard post is to be filled with __________, and capped ___________.
Concrete
Capped smooth
What are the two acceptable type/sizes of landscape sleeves used under the driveway?
(1) - 3” or (2) - 2” diameter PVC pipe.
Where is the landscape sleeve installed?
Under the first tooled joint from the citywalk, extend a minimum of 6” past the edge of the driveway.
Where can you find the location of the courtyard drain pipes?
Architectural blueprints
Courtyard drain pipes are to be a minimum of ________ inch pipe with _________ __________ at each end.
3”
Drain caps
All toilet and vent stacks should be kept a minimum of _______ inch(s) from the exterior form boards.
1”
The main water service should be kept ________ to _______ inches from the form boards.
6” - 8”
The STHD hold-downs should be plumb within _______ inch(s).
1 1/2”
The MASA hold-downs are to be plumb within _________ inch(s).
1/2”
All slab penetrations should be ________ and ________.
Boxed
Wrapped
Verify all exterior door openings are marked where? And how?
On the form boards with paint or nails.
Verify all stakes and vertical rebar have what on the ends?
Safety caps or Shepard’s hook
What should you verify on your proceed when doing a pre-slab?
1.
2.
3.
- Room options
- Centric (if applicable)
- Plumbing options (if not verified at soils)