Misc Flashcards

1
Q

Bidding/Procurement Docs

A

Project Manual
Contract Drawings
Addenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is bidding in DBB

A

Bidding after CDs are complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bidding in Multiple Prime

A

Bidding after CD but multiple bidding process occur for each portion of work (faster, shorter sched, needs more owner involvement, good for CMa or experienced owners)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bidding in DNB

A

owners request proposals (not bids) from multiple contractors at the end of CD, then can negotiate with one or more to come to an agreement (bids are not negotiated, may not be permitted on public projects, good for people with pre-established relationships)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bidding in CMc/CMAR

A

CMc is brought on in the design phase, there is no bidding process but owner and CMc negotiate the GMP (normally in DD) owner and CM have pre-agreed upon strategy for splitting savings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bidding in DB

A

Owner negotiate an upfront price DB firm bases on owner’s program, No bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Bidding in Bridge DB

A

Owner can bid SD drawings from design architect to multiple DB firms, can be more accurate then normal DB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bidding in IPD

A

no bidding or negotiating bc all on the same team. All members agree to a project cost at beginning and work toward that budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project Manual Includes

A

Instructions for bidding or negotiation
instructions for project completion
Owner/contractor agreement
General conditions (A201)
May include Supplementary conditions (A503)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A503 Supplementary conditions

A

A separate document that enables altering of A201 without altering the document itself (can be easier to keep track of changes this way)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A701 Instructions to Bidders

A

Includes bid deadline, process for submission, process for RFI, bid bond or bid security

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bid Bond

A

covers the difference between the lowest bidder and the second lowest bidder for the owner if the lowest bidder decides not to do the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A305 Contractor’s Qualification Statement

A

staffing capabilities, financial informations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Bid Form

A

Form provided to contractors by the architect and owner to standardize bids for easier comparison

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Specifications include

A

Specific product
Desired Qualities (grade, color)
Required Submittals
Required testing standards
Installation Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Reports included in Bidding Instructions

A

Geotech
Environmental Reports
Surveys

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Proprietary Specification

A

Aka closed specification
if the owner/arch will only accept a specific type, lists the specific product
not allowed on publicly funded projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Descriptive specifications

A

Just describes the look, dimensions, quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Performance Spec

A

Lists the standards the item needs to meet (not ideal for aesthetic items)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Reference Specs

A

used in conjunction with reference specs, references ANSI, ASTM, or UL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Addenda

A

rfi in bidding process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Types of Open Specs

A

Performance, Descriptive, Reference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A good project delivery method for quality

A

Design-Negotiate Build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How a bidder is selected in publicly funded projects

A

Lowest Responsible Bid
OR
(sometimes permitted)
Value-Based Selection - can consider quality or schedule (anything other than cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Qualification Based Selection
considers the quality of work, speed of work, and other subjective criteria
26
Stipulated sum
lump, all in price, usually for competitively bid projects. good for clear scope, complete CDs
27
GMP
good for incomplete CDs (like in fast track) contractor anticipates costs good for owner bc they get pricing earlier usually large comtingency
28
Cost-plus / time and materials
costs + overhead and profit good for smaller projects of renovations where unforeseen circumstances are typical
29
Unit price
fixed fee but for a specific unit, like a sf cost for drywall, booths for a restaurant, fixtures
30
Target Price Method
typ for Design Build, owners give a budget and DB work toward it
31
Construction Cost
just cost of construction (materials, labor, waste removal, temp facilities, mock-ups, taxes, insurance, bonds, mobilization)
32
Bid Bond
33
Contingency
included in bids to cover unforeseen costs
34
Overhead and Profit
Similar to net multiplier, office supplies, support staff, etc
35
Can you have a shard savings clause between owner and contractor in a stipulated sum contract?
No
36
When is a building considered enclosed
when the openings are installed and the thermal and moisture protection is complete
37
Best time to establish project roles
Preconstruction meeting with an authority matrix
38
CMa
CMa direct contract with owner, may prep cost estimates but ultimately just an advisor
39
Cm-A
Advisor but can act in capacity of the owner, may act as an owners rep
40
CMC
Good for fast track Coordinate cost with design throughout pd-cd Price around DD Often uses GMP
41
Pre construction meeting
Architect leads Define roles and responsibilities Arch makes & distributes agenda OAC and some consultants
42
Pre con meeting topics
Rfi processes Submittal schedule Payment applications G702/G703 Schedule of values Changes in the work processes G701 Architect prepares the change order Close out requirements Sustainability reps Mock ups Site signage Consultants
43
Standard time for submittal review
10 days
44
Standard time for rfi review
3-5 days
45
Pre installation meeting
Indicate need on specs Could be contractor and subs but arch and owner should be notified in case they need to join
46
Value based selection (for contractor bidding)
Considers other, more subjective criteria (other that price)
47
A101
Owner - Contractor: DBB with stipulated sum payment structure
48
Initial decision maker
Mediation facilitator (Mediation is non binding)
49
Binding forms of conflict resolution
Arbitration and litigation
50
IDM in the default owner - contractor agreement A101
Architect
51
Architect is not responsible for
Means and methods Site safety Sequences Contractor failure
52
Architect is responsible for
Scheduling site visits due to contract Keep the owner informed and report deviations
53
How to record non conforming work
In a spreadsheet and on drawings
54
Where to find reqs for testing and inspection
IBC CHAPTER 17
55
Slump test
Determines the workability of concrete before each pour Determines if it’s the right mix
56
Cylinder test
Determines the strength of the concrete at certain intervals, typically 28 days after pouring Can test periodically before 28days for indicative results
57
Who is required to test for soils
Owner
58
Project schedule vs construction schedule
Project schedule includes design and construction
59
CMC and schedules
Cmcs are responsible for whole project schedule, not just construction
60
Most typical construction schedule chart type
Gantt with critical path
61
Float time
Amount of time a task can slide without effecting the critical path
62
How to calculated deflection
Length (in inches) / deflection limit
63
Three ways to modify construction contract
Change order Construction change directive Minor change in the work
64
Minor change in work
Does not effect contract sum or time Can be handled in ASI to document change AIA G710_
65
Change order
Effects contract sum and/or time AIA G701 Everyone agrees about change and price/plab
66
Construction Change Directive
Effects contract sum and/or time AIA G714 Not agreed upon, contractor begins work before agreement is reached Owner and arch sign Faster - can use even if everyone agrees to save time Once contractor signs is it a change order
67
5 steps for an rfi
Catalog- file in system Assess validity - is rfi the proper format for this question? Distribute to reviewers - any consultants need input? Review information - ensure response is consistent with design intent Submit final response - send to contractor
68
RFIs are used for
Clarification Additional information Confirming code or contract information
69
Invalid RFIs
Incomplete or errors Does not ask a question Asks about means and methods Submittal Substitutions Adjustments to contract time / sum
70
Who prepares submittal schedule?
Contractor - who shares with arch ahead of construction
71
Contractor submittal responsibilities
Quantities Dimensions Conforming to CDs Means and methods Contractor reviews and approves before sending to arch
72
Delegated design
Arch delegates design to a contractor sub, passes liability to sub
73
Reviewing submittal
Catalog with number, date and subject Assess validity - req by specs? Complete? Has contractor reviewed? Determine Action vs informational Determine who responds - arch? Subs? Coordinate multiple disciplines Prep review- compliance with CDs, provide submittal action Catalog submittal and distribute responses
74
Action submittals
Require action for review
75
Informational submittals
Do not require action, things like technical data sheets (paint)
76
CSI division 1
General requirements
77
CSI division 2
Existing conditions
78
CSI division 3
Concrete
79
CSI division 4
Masonry
80
CSI division 5
Metals
81
CSI division 6
Wood, plastics and composites
82
Division 7
Thermal and moisture protection
83
Division 8
Openings
84
CSI division 9
Finishes
85
CSI division 10
Specialties
86
CSI division 11
Equipment
87
CSI division 12
Furnishings
88
CSI division 13
special construction
89
Division 14
Conveying equipment
90
Division 00
Procurement and contracting requirements
91
Division 21
Fire suppression
92
Division 22
Plumbing
93
Division 23
HVAC
94
Division 25
Integrated automation
95
Division 26
Electrical
96
Division 27
Communications
97
Division 28
Electronic safety and security
98
Division 6 digit formation
03-30-00 Division-section-identifier
99
Submittal names should include
Six digit spec csi number
100
Three parts of a spec
General Products Execution
101
Spec part 1 - general
Summary - related sections Submittals QA
102
Spec part 2 - products
Required tests Materials or their properties
103
Spec part 3 - execution
Testing reqs Placement requirements Protection reqs Allowable tolerances
104
In standard A201 how long does an arch have to certify a pay app
7 days
105
Retainage ( in pay app)
The amount of money withheld by the owner on each payment application item to be paid at the end of construction (motivates contractor to finish project well and stores money for owner if contractor can’t complete the work)
106
Standard amount of time someone has to make a claim during construction
21 days after condition is discovered
107
Standard amount of time the IDM has to make a decision
10 days
108
Which is preferred between arbitration and litigation
Arbitration - can use an arbiter familiar with construction, cheaper, quicker
109
Liquidated damages
Amount, usually paid daily, that a contractor owes if they go over the agreed upon date of substantial completion
110
Punch list items
Items to be done but do not affect occupation of the space Usually prepared by contractor but can be done by architect as an add service
111
G704
Certificate of substantial completion Consultants should issue their own too
112
When is retainage released to the contractor?
At substantial completion but owner can withhold 2x the cost of lunch list items
113
When do warranty periods begin?
At substantial completion
114
When do site and security costs turn back over to owner from contractor?
At substantial completion
115
Docs submitted prior to final payment
Certificate of project insurance Written statement Outstanding warranties Consent of surety to final payment Final lien waiver - has paid all subs
116
Commissioning
Testing building systems to determine if they are functioning as they are designed to
117
Phases of commissioning
Design - systems to be commissioned are determined Construction - site visit performed Acceptance - when systems are tested Post-acceptance - staff are trained
118
When is a commissions agent hired
During design to ID systems to be comissioned
119
Post occupancy evaluation
Optional add service to evaluate building operation. This is in addition to the 1-year review meeting which is a basic service Site visit, interviews
120
Things to review at 1-year meeting
Operations Maintenance Building systems Utility usage Warranties
121
Post occupancy add services
Record drawings Facility support - operations and maintenance Tenant improvement FF&E
122
Who decides whether or not something meets design intent during construction?
the architect
123
Two tests for building wide structural testing during construction
structural analysis in situ load tests
124
How long must an owner wait for a contractor to fix inadequate work before hiring another contractor for the scope?
2 weeks
125
Types of submittals
cut sheets mock ups shop drawings
126
Who pays for an architect to have work uncovered to be inspected
if the work doesn't conform to CDs: the contractor if the work is does conform to CDs: the owner
127
3 roles of an RFI
To obtain information that the requesting party cannot obtain through research, document review, or other reasonable means For the architect, owner, contractor, or other party to request further information from each other during construction A means for the sender, who is seeking a solution or answer to a site or construction condition, to include a recommended solution based on the sender’s expertise and the options available, including any known effects on cost or schedule
128
What is the role of a low voltage consultant
communications, security, audio, and video systems throughout the project. Coaxial cabling would fall under the low voltage consultant's specifications (Division 27)
129
What is bidding contingency for?
the uncertainty of the marketplace and fluctuating prices
130
what is construction contingency for?
unforeseen site and field conditions
131
What are Soldier beams and lagging planks used for
excavation support
132
payment bond
legal contract and type of surety bond that guarantees that a contractor will pay their subcontractors, material suppliers, and other project entities
133
who signs a construction change directive
the owner and architect
134
Advantages of fly ash over portland cement
better workability and lower embodied carbon
135
when is bulletin used
drawing revisions that have been made after the contract is awarded
136
when is final cleaning done
prior to final completion
137
A305
Contractor statement of qualifications
138
How is a HVAC system comissioned
A smoke pen or pencil is used to test HVAC equipment and air movement by emitting a trail of smoke vapor to detect thermal currents, drafts, and pressure differences.
139
A701
Instructions to bidders
140
Is being asked to review a submittal out of sequence with the agreed upon schedule an add service?
Yes
141
How long after the final certificate of payment is issued does the owner have to pay?
no later than 30 days after the issuance of the architect’s final certificate for payment
142
Amount something can vary from it's designed STC rating in field
5-15 dB
143
Who are RFIs signed by
no one!
144
Who signs A201
no one!