Midterm Flashcards

1
Q

Types of Estimates

A

Conceptual, Schematic, Design Development, GMP or Construction Documents (CD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Four steps to an estimate

A
  1. Break the project into WBS tasks
  2. Assign a cost to each WBS task
  3. Summarize the “Direct Construction Costs”
  4. Add all “Indirect Construction Costs”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Four principals to develop the WBS

A
  1. No overlap of scope between work packages
  2. Each work package should have a definitive start and end date
  3. No overlap of cost between work packages
  4. Final breakdown work package should be at level where progress can be measured precisely
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CORE Construction Presentation - Living Estimate

L S I G E Q G F

A
  • Listen
  • Study Cost History
  • Investigate
  • Gather Subcontractors Feedback
  • Explore Options
  • Quantity Scope
  • Generate Detailed Estimate
  • Forecast Future Market Conditions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Documents needed to estimate costs

C G D S S S C I I B

A
  • Contract Agreement
  • General Conditions
  • Drawings
  • Specifications
  • Soil Report
  • Schedule
  • Clarifications
  • Inclusions
  • Insurance requirements
  • Bonds requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CSI MasterFormat Groups (2)

A
  • Procurement/Contracting Requirements Group

- Specifications Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Divison 01

A

General Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Division 02-19

A

Facility Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Divison 20-29

A

Facility Services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Division 30-39

A

Site and Infrastructure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Division 40-49

A

Process Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

3 Parts of SectionFormat

A

General, Products, Execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Earthwork Units

A

BCY/LCY and CCY and Acres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Concrete Units

A

CY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Concrete Formwork Units

A

SFCA (SF of Contact Area)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Masonry Units

A

SF to #of blocks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Rebar Units

A

lbs. or tons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Roofing Units

A

Square

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Carpet

A

Square Yard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Structural Steel

A

tons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Direct Construction Costs =

A

Materials + Labor + Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Indirect Construction Costs=

A

Fees + Insurances + Bonds + Taxes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Sources of Cost Information

A
  • Historical costs database
  • Subcontractor/Vendor Quotations
  • Published Cost Data (RS Means)
  • Experience
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Unit Cost Pricing =

A

Material + Labor + Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Labor Hours per Unit=

A

total crew labor hours/daily output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Labor Dollars per Unit=

A

Daily Crew Labor Cost/Daily output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Work hours per unit=

A

crew work hours expended/daily output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

units per work hour=

A

daily output/crew work hours expended

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

total work hours=

A

work hours per unit x planned quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

total number of crew days=

A

planned quantities/daily output

31
Q

Loose Volume=

A

bank volume x (1 + swell)

32
Q

Bank Volume (imported soil)=

A

compacted volume/shrinkage factor

33
Q

Imported soil (lcy)=

A

Compacted volume/shrinkage factor

34
Q

Which document describes quality of work and the quality of the material and the construction execution procedures?

A

Technical Specifications

35
Q

Which document issued by the architect illustrates what is to be built at the time of bid?

A

Plans

36
Q

Which type of estimate is most appropriate when the contract documents are 30% to 90% complete?

A

Semi-Detailed estimate

37
Q

Which estimate will give you the most level of details and be the most accurate?

A

Detailed estimate

38
Q

During the design process, in which order are the different drawing sets completed?

A

Conceptual - Schematic Design - Design Development - Construction Drawings

39
Q

T or F: In a CM@R delivery method, it is highly recommended to wait until the Design Professional has completed the 100% construction documents to hire the contractor and get pricing from its estimating department. This will prevent any change orders in the future.

A

False

40
Q

List at least 3 factors that could affect the productivity rate of a crew on a jobsite

A
  • Number of men in crew
  • Other subs being behind
  • Materials are not coming on time
41
Q

Which type of insurance covers injuries to construction site workers employed at the job site?

A

Workers compensation

42
Q

How does a construction company typically structure its accounting cost codes?

A

Typically organized following the CSI Materformat divisions, with some adaptions by companies

43
Q

Accuracy of a detailed estimate is

A

2% to 4%

44
Q

Accuracy of a conceptual estimate is

A

+/- 20%

45
Q

Accuracy of a semi-detailed estimate is

A

+/- 5% to 10%

46
Q

Division 01

A

General Requirements

47
Q

Division 02

A

Existing Conditions

48
Q

Division 03

A

Concrete

49
Q

Division 04

A

Masonry

50
Q

Divison 05

A

Metals

51
Q

Division 06

A

Wood, Plastics and Composites

52
Q

Division 07

A

Thermal and Moisture Protection

53
Q

Divison 08

A

Openings

54
Q

Division 09

A

Finishes

55
Q

Divison 10

A

Specialties

56
Q

You can find Electrical specifications under which division in the CSI MasterFormat?

A

Division 26

57
Q

Which of the following items would not be included in a division 7 scope of work?

A

Architectural louvers/screens

58
Q

Which type of insurance covers workers being laid off from their job?

A

Unemployment

59
Q

What is a Work Breakdown Structure?

A

A list of tasks braking down the project into manageable work packages

60
Q

T or F: Contingency is typically used to cover the risks that occur during a CM at risk project

A

True

61
Q

A WBS typically includes which of the following for each work package?

A

The budgeted cost of the work scheduled

62
Q

T or F: The “art” of estimating is being able to account for the unknown, the unseen and the unexpected

A

True

63
Q

T or F: It is not important to verify that the General Project Description provided in a Geotechnical Report is accurate

A

False

64
Q

What is the soil state called after the soil is put in place at its final location and final compaction ratio?

A

compacted

65
Q

What is the earth material drawn from an excavation called?

A

Spoil

66
Q

When excavating for utility trenches, it is important to note the soil characteristics/classification to:

A

Know if we will need to dig through hard rock that will require special equipment, and if we will need to use shoring

67
Q

Trying to save cost on the geotechnical investigation scope by not doing as many soil borings as needed may result in:

A

All of the proposed answers and potential litigations on the project

68
Q

T or F: The swell/shrink factor of a soil indicated in a soil geotechnical investigation report is the same thing as the swell factor used by earthwork contractors to estimate LCY of soils to be exported

A

False

69
Q

The soil conditions indicated in the geotechnical report will help us price the following potential added cost to earthwork scope:

A

Hard rock digging, dewatering and over excavation

70
Q

What is the soil state called if it is in its natural, or in place, or in situ, or undisturbed state?

A

Bank

71
Q

Under which conditions would you want to epoxy coated rebar and welded wire fabric?

A

To prevent corrosion of the rebar/WWF

72
Q

A welded wire fabric is called for on the drawings as WWF 8 x 8 - W6xW6
What does that mean?

A

It comes in sheets that are 8’ x 8’ and weighs 600 pounds

73
Q

Other than the concrete strength expressed in PSI (i.e. 3,000 PSI concrete), list at least 3 concrete specifications that could add cost to the price of concrete CY:

A

Different admixtures that are required in the mix (mix design)
Reinforcement required in the specifications
Formwork required - what kind (earth form, reused, etc.)

74
Q

T or F:Reinforcing bars are listed by the bar number, which corresponds to the bar diameter in 10th of an inches.
For example, a No. 7 bar (also referred to as a # 7) has a 0.7 inch nominal diameter.

A

False