Midterm Flashcards
One advantage of the design/build approach is that usually a firm project cost is established
before construction begins.
False
One advantage of a Design/Bid/Build delivery method is known project costs before
construction begins.
True
In the case of design/build, the constructor acts as the general contractor with single-firm
control of all subcontractors.
True
In the case of Construction Management delivery method, the general contractor forms
contracts with the sub-contractors.
False
In the construction management approach, the construction manager usually guarantees the
overall price and quality of work.
False
If an owner has only fixed amount to spend and would not build a project if its cost would
exceed this amount, construction management would be the preferred delivery method.
False
If an owner has only fixed amount to spend and would not build a project if its cost would
exceed this amount, design-bid-build would be the preferred delivery method.
True
In a guaranteed maximum price (GMP) contract, cost above the GMP is covered by the
contractor.
True
An addendum is a change issued to a bidder after the contract award.
False
In a limited partnership, all the partners are liable to a limited amount
False
Call for tenders by the owner is treated as an Invitation in Canada.
False
Call for tenders by the owner is treated as an Offer in Canada.
True
Safety of a construction project is the responsibility of the general contractor
False
Safety of a construction project is the ultimate responsibility of the Safety Manager
False
Safety of a construction project is the ultimate responsibility of the Safety Manager
False
Unionized construction workers are generally paid higher than open-shop in Canada
True
Which category of construction would typically be contracted out as design/build
a. Residential
b. Building construction
c. Industrial
d. Heavy/Infrastructure construction
Industrial
Drawings and specifications are the output of what stage of a project
a. Concept and feasibility
b. Procurement
c. Engineering and design
d. Startup and implementation
e. None of the above
Engineering and design
Traditionally, concept and feasibility studies are handled by the……
a. Owner
b. Architect
c. Contractor
d. Subcontractor
Owner
In what project phase are the bid package advertised and the project contracted out (so construction can begin)? a. Concept and feasibility b. Engineering and design c. Procurement d. Construction e. Operation and utilization
Procurement
Owner involvement is highest during what project phase?
a. Construction
b. Engineering and design
c. Concept and feasibility
d. None of the above
Concept and feasability
In design/bid/build, the architect signs a contract with the…..
a. Owner
b. Construction manager
c. General contractor
d. Subcontractor
e. None of the above
Owner
The term fast track means
a. Design/build
b. Construction starts before the design completes
c. Cost plus fixed fee
d. None of the above
Construction starts before the design completes