Midterm 1 Flashcards

1
Q

Activities

A

A distinct, scheduled portion of work performed during the course of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical Path

A

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Free Float

A

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Precedence Diagramming Method

A

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show a sequence in which the activities are to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Finish-To-Start

A

A logical relationship in which a successor activity cannot start until a predecessor activity has finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk

A

An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Risk Management Plan

A

A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Risk acceptance

A

A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Risk Transfer

A

A risk response strategy whereby the project team shifts the impact of the threat To a third-party, together with ownership of the response.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Issue

A

An important topic or problem for a debate or discussion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Opportunity

A

A risk that would have a positive effect on one or more project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Residual risk

A

The risk that remains after risk responses have been implemented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Secondary risk

A

A risk that arises as a direct result of implementing a risk response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Communications management plan

A

A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Critical path method

A

A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the scheduled model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Network path

A

A sequence of activities connected biological relationships in a project schedule network diagram

17
Q

Program evaluation and review technique

A

A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity durations when there is uncertainty with the individual activity estimates

18
Q

Precedence diagramming method

A

A technique used for constructing a schedule model in which activities are represented by nodes in our graphically linked by one or more logical relationships to show a sequence in which the activities are to be performed

19
Q

Duration

A

The total number of work Periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks