MB5-705 Managing Microsoft Dynamics Implementations Flashcards
You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft
Dynamics products for your customers.
Your customer’s major stakeholders identify significant changes that will increase the scope of a project.
Which two risk response strategies for the project definition update should you use? (Each correct answer
presents part of the solution, Choose two.)
A.Exploit B.Avoid C.Enhance D.Transfer E.share
B.Avoid
D.Transfer
Which document should you use to manage project deliverables?
A.project scope statement
B.project objectives
C.technical requirements
D.functional requirements
A.project scope statement
You are a project manager.
You find that the personnel in the Human Resources department are new and not experienced in project
work.You need to manage the project resources to accommodate the lack of project experience in the
project.What should you do?
A.Add more time for the project activities.
B.Release the project team.
C.Document the problem and the impact on the scope of the project to the major stakeholders.
D.Document the impact of the lack of experience on the legal requirements.
A.Add more time for the project activities.
You are a project manager, and you use Microsoft Dynamics Sure Step Methodology to manage
projects.You need to ensure that quality assurance is part of a project that you are managing.Which item
should you include as part of the project?
A.a comprehensive review with the project stakeholders at the end of the project
B.a review process done at the beginning and checked off at the end of the project with the project
stakeholders
C.quality assurance reviews with stakeholders, scheduled early and often across all project phases
D.a comprehensive review process performed if problems occur during the project or at a stakeholder’s
request
C.quality assurance reviews with stakeholders, scheduled early and often across all project phases
As a project manager, you need to incorporate a change request into the project.
Which two tasks must be completed to correctly handle this request when you use the Microsoft
Dynamics Sure Step Methodology? (Each correct answer presents part of the solution.Choose two.)
A.Complete a customer review and approval. B.Complete a plan-do-check-act cycle. C.Complete a change request form. D.Complete a work breakdown structure. E.Complete a risk identification.
A.Complete a customer review and approval.
C.Complete a change request form.
Which activity is a precondition for communication management?
A.defining project roles
B.identifying project stakeholders
C.analyzing risk
D.defining project scope
B.identifying project stakeholders
Which statement is an objective of solution envisioning?
A.Create and approve a Fit Gap Analysis.
B.Complete a functional design for a solution.
C.Finalize and approve a project plan.
D.Understand solution requirements.
D.Understand solution requirements.
You are performing a new Microsoft Dynamics GP implementation for a customer who has 10 users.The
customer does not want to use customizations or independent software vendor (ISV) solutions.Which
project type should you use to deliver the implementation?
A.rapid
B.standard
C.agile
D.enterprise
A.rapid
.What is an objective of diagnostic preparation?
A.to lead an internal kickoff meeting
B.to gain a preliminary understanding of the customer’s needs
C.to plan the running of diagnostic accelerators
D.to prepare high-level project documents
B.to gain a preliminary understanding of the customer’s needs
You are performing a Decision Accelerator Offering.In which order should you perform the steps?
A.
1. Meet internally to discuss the Decision Accelerator Offering
2. Meet with the customer to discuss the Decision Accelerator Offering
3. Review the presentation and customer sign-off
4. Perform activities
B.
1. Meet with the customer to discuss the Decision Accelerator Offering
2. Meet internally to discuss the Decision Accelerator Offering
3. Perform activities
4. Review the presentation and customer sign-off
C.
1. Meet with the customer to discuss the Decision Accelerator Offering
2. Meet internally to discuss the Decision Accelerator Offering
3. Review the presentation and customer sign-off
4. Perform activities
D.
1. Meet internally to discuss the Decision Accelerator Offering
2. Meet with the customer to discuss the Decision Accelerator Offering
3. Perform activities
4. Review the presentation and customer sign-off
A.
- Meet internally to discuss the Decision Accelerator Offering
- Meet with the customer to discuss the Decision Accelerator Offering
- Review the presentation and customer sign-off
- Perform activities
.Which two activities are included in the Diagnostic phase? (Each correct answer presents part of the
solution.Choose two.)
A.Gather the development standards.
B.Conduct an architecture assessment,
C.Present a solution overview.
D.Finalize the product specification.
C.Present a solution overview.
D.Finalize the product specification.
Which two statements differentiating projects from operational work are correct? (Each correct answer
presents part of the solution.Choose two.)
A.The purpose of a project is to create a unique product, service, or result; the purpose of operations is to
sustain the customer’s business.
B.The duration of a project is temporary; the duration of operational work is ongoing.
C.The output of a project is variable; the output of operational work is continuous, daily, and predictable.
D.The purpose of a project is to sustain the new business requirements; operations end with the adoption
of a new set of objectives, and then the work continues.
E.a project ends when it is replaced by a new process; operations end when its specific objectives have
been attained.
A.The purpose of a project is to create a unique product, service, or result; the purpose of operations is to
sustain the customer’s business.
B.The duration of a project is temporary; the duration of operational work is ongoing.
Which item is a project management process?
A.communication
B.risk
C.initiation
D.integration
C.initiation
You are a project manager.You use the classic triple constraint model.If one constraint is changed,
what happens to the other constraints?
A.The project’s quality constraint will change.
B.The project’s expectations constraint will change.
C.At least one of the other constraints must also change.
D.The customer’s benefits constraint will change.
C.At least one of the other constraints must also change.
You need to illustrate the dimensions of the project management diamond.Which dimension should
you place at the center of the diamond?
A.quality B.cost C.time D.expectations E.scope
D.expectations
You need to create 3 project management diamond.
Which constraints should you use at each corner?
A.cost, quality, scope, risk
B.expectations, scope, time, risk
C.cost, expectations, scope, time
D.cost, quality, scope, time
D.cost, quality, scope, time
.You are performing the solution envisioning process with a customer.
The customer requests that you use all of the Decision Accelerator Offerings.
What is the first step you should use in the process?
A.architecture assessment
B.Fit Gap and Solution Blueprint
C.requirements and process review
D.scoping assessment
C.requirements and process review
You must complete a Requirements and Process Review during an engagement.
What should you identify and document at the completion of the exercise?
A.implementation approaches and associated costs
B.customer requirements and business processes within the scope
C.degree of fit to the business
D.infrastructure and hardware requirements
B.customer requirements and business processes within the scope
Which Decision Accelerator is a pre-condition for the Fit Gap and Solution Blueprint?
A.requirements and process review
B.scoping assessment
C.proof of concept
D.business case
A.requirements and process review
Which two categories should be used for requirements in the Fit Gap Analysis spreadsheet? (Each
correct answer presents part of the solution.Choose two.)
A.additional purchase
B.configuration
C.gap
D.standard feature
B.configuration
D.standard feature
Which project types does the Microsoft Dynamics Sure Step Model use?
A.waterfall, iterative
B.diagnostic, analysis, design, development, deployment, and operation
C.standard, rapid, enterprise, agile, and upgrade
D.diagnostic, development, and operational
C.standard, rapid, enterprise, agile, and upgrade
You are responsible for creating and managing projects in a project repository.
Which two actions can you perform on existing projects in the repository? (Each correct answer presents
part of the solution- Choose two.)
A.clone a project
B.share a project
C.change a project type
D.delete a project
A.clone a project
D.delete a project
.You need to create a project by using the Sure Step Project Creation Wizard.
Which two properties must you identify in order to proceed? (Each correct answer presents part of the
solution.Choose two.)
A.engagement type
B.product
C.project implementation phase
D.product version
A.engagement type
B.product
As a project manager, you need to ascertain which human resources are involved in the project and Fit
Gap documents on the Decision Accelerators.
Which two Microsoft Dynamics Sure Step Methodology tree nodes provide this information for the
implementation project? (Each correct answer presents part of the solution.Choose two.)
A.Solution Envisioning B.Resources C.Roles D.Deliverables E.Preferences
B.Resources
C.Roles
.Which document is generated as a result of the functional requirements document (FRD)? A.solution design document (SDD) B.Fit Gap Analysis worksheet C.functional design document (FDD) D.technical design document (TDD)
B.Fit Gap Analysis worksheet
You are delivering a project by using the waterfall delivery method.
You approve the project charter and project plan.
Which three actions should you do next? (Each correct answer presents part of the solution.Choose
three.)
A.Document the configuration of the overall Microsoft Dynamics solution.
B.Create the deployment plan.
C.Perform and document the Fit Gap Analysis.
D.Complete the design specifications.
E.Develop future state business process models.
F.Conduct the Executive and Project Team kickoff meetings.
C.Perform and document the Fit Gap Analysis.
E.Develop future state business process models.
F.Conduct the Executive and Project Team kickoff meetings.
You are a project manager.You are running a project by using the waterfall delivery method.The project
is in the development phase.Which Microsoft Dynamics Sure Step Methodology supplemental documents
are created to support the training?
A.performance test documents
B.data migration documents
C.user test documents
D.user guides
D.user guides
During which phase of a waterfall delivery is the creation and delivery of a complete system configuration performed?
A.development
B.data migration
C.analysis
D.design
A.development
You are a project manager.You are taking over a Microsoft Dynamics implementation.
The project is in the design phase.
You need to identify the test activities.
Which two activities should you include? (Each correct answer presents part of the solution.Choose two.)
A.create a data subset for testing B.create system maintenance procedures C.create system configurations D.develop performance test scripts E.identify process testing scenarios
C.create system configurations
E.identify process testing scenarios
Which two components are critical to the success of user acceptance testing? (Each correct answer
presents part of the solution.Choose two.)
A.the completion of the end user training
B.the building of the disaster recovery environment
C.the usage of user acceptance test scripts
D.the transactions to use for the tests
A.the completion of the end user training
C.the usage of user acceptance test scripts