Mapping Processes Flashcards

1
Q

As a project manager you’ll need to gather the stakeholder requirements your project is required to satisfy to consider the project complete:

A) Develop the project management plan
B) Plan scope management 
C) Collect project requirements 
D) Define the project scope 
E) Create the work breakdown structure
A

C) Collect project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Once you’ve created the project scope and the WBS, the project manager and project team will define the exact activities that need to be completed in order to define the exact elements of the WBS and scope:

A) Plan schedule management 
B) Define the project activities 
C) Sequence the project activities
D) Estimate the activity duration 
E) Develop the project schedule
A

B) Define the project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the first project management process group you’ll be working with in this scenario?

A) Executing
B) Closing
C) Monitoring and Controlling
D) Initiating
E) Planning
A

D) Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How many project management processes exist within Initiating?

A)24
B) 10
C) 2
D) 12
E) 1
A

C) 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List all of the processes in the first process group of the project management life cycle?

A

Develop Project Charter and Identify Stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

This quick, subjective review of the identified risks helps determine which risk events demand additional analysis:

A) Plan risk management
B) Identify the project risks 
C) Perform qualitative risk analysis
D) Perform quantitative risk analysis 
E) Plan risk responses
A

C) Perform qualitative risk analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

You’ll examine the project work and put the activities in the correct order:

A) Plan schedule management 
B) Define the project activities 
C) Sequence the project activities 
D) Estimate the activity duration 
E) Develop the project schedule
A

C) Sequence the project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Based on the needs of the project, the organizational procedures, and the project budget, the procurements for the project are identified and planned for:

A

Plan Procurement Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Once you’ve created the Project Scope Statement, you’ll decompose the project scope into this document:

A

Scope Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

This process comes well after you’ve created the WBS. You can examine the aggregate costs of the individual elements to create a budget and a cost baseline

A

Determine Budget (Maybe Plan Cost Management or Estimate Costs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly