M3 Flashcards

1
Q

Plan Schedule Management Inputs

A

PC
PMP
EEF
OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan Schedule Management Tools & Techniques

A

EJ
DA
M

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan Schedule Management Outputs

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a diagram that shows activities with scheduling relationships

A

network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

an entity on the network diagram representing an activity

A

node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

a node following one or more nodes

A

successor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

a node before one or more nodes

A

predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

the longest path in schedule

A

critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

a management planning and control tool and is considered as a road map for a particular program or project in which all of the major elements (events) have been completely identified, together with their corresponding interrelations

A

PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

AOA

A

Activity on Arrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

has “activities” on nodes

A

AON
Activity on Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

has “events” on nodes and that is the focus

A

AOA
Activity on Arrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

activities that have to be completed in a sequence

A

serial (sequential) activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

activities that can be completed at the same time

A

concurrent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

activities that have 2 or more immediate predecessors

A

merge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

activities that have 2 or more immediate successors

A

burst

17
Q

Schedule Management Plan can include

A

methodology and tool
level of accuracy
units of measure
OPL
Schedule maintenance
CT
RPM
RF
PD

18
Q

requires us to follow some carefully laid-out steps, in a specific order, for the schedule to take shape

A

Project scheduling

19
Q

the identification of the project objectives and the ordered activities necessary to complete the project including the identification of resource types and quantities required to carry out each activity task

A

project planning

20
Q

creation of activity list based on work packages from WBS

A

define activities