M1 Construction contracts Flashcards

1
Q

What method of revenue recognition does a long-term construction contract use?

A

The input method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is construction contract revenue recognized over time?

A
  1. The entity’s performance creates or enhances an asset that the customer controls as the asset is created or enhanced
  2. The entity’s performance does not create an asset with alternative use to the entity, and they have enforceable right to receive payment for performance completed to date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 4 steps to calculate gross profit for long-term construction contracts with revenue recognized over time?

A
  1. Compute gross profit of completed contract
    Gross profit = Contract price - estimated total costs
  2. Compute % of completion
    Total cost to date / total estimated cost of contract
  3. Compute gross profit earned
    Gross profit * % of completion = PTD
  4. Compute gross profit earned for current year
    current PTD - PTD at beginning of period = Current year to date GP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If a gross loss is recognized how does revenue recognized over time differ from revenue recognized at a point int time?

A

If a loss is recognized using the revenue recognized over time method, previously recognized gross profit must be unwound in the year of the loss increasing the current year gross loss

if a loss is recognized using the revenue recognized at a point in time method, then no previous gain had been reported and only the current loss is reported.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a difference between construction revenue recognized at a point in Time and over time

A

At a point in time does not include gross profit as part of construction in progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How are each of the following reflected on the Balance Sheet?

  1. Construction costs and accumulated gross profit
  2. Billings on construction
A
  1. Construction in progress - inventory
  2. Progress billings - contra inventory
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is an expected loss on total contract determined?

A
  1. Adding to advances any additional revenue expected
  2. Adding estimated costs to complete to the recorded costs to date
  3. Subtracting 2 from 1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the JE to record construction costs

A

DR Construction in progress
CR Materials, cash

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the JE to record billings on contract

A

DR A/R
CR Progress billings on construction contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the JE to record estimated gross profit during construction

A

DR construction expense
DR Construction in progress
CR Revenue from LT construction contracts*

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the JE to close construction accounts (revenue recognized over time)

A

DR Progress billings
CR Construction in progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the JE to close construction accounts (revenue recognized at a point in time)

A

Close billings to revenue
DR Progress billings
CR Revenue

Close construction in progress to expense
DR Cost of LT construction contract
CR Construction in progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is the JE to record billings on contracts?

A

DR Contracts receivable
CR Progress Billings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the final JE once the project is completed?

A

Close out the total amount billed
DR Progress billings
CR Revenue

Close out total costs
DR Construction expense
CR Construction in progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the JE to record revenue / costs (only for revenue recognized over time)

A

DR Construction expense
DR Construction in progress (gp %)
CR Revenue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the JE once a construction contract is complete to close out progress billings and construction in progress?

A

DR Progress billings (total bill amount)
CR Revenue

	DR Construction Expense (total costs)
            CR Construction in progress