LTCC FORMULA AND NOTES Flashcards

1
Q

Total Estimated Cost

A

Cost incurred to date
+ Estimated cost to complete
_______________________
Total Estimated Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

POC%

A

Cost Incurred * Construction In Progress
___________________ or ______________________
Total Estimated Cost Contract Price

  • use only if there is profit cant use if lost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Revenue

A

POC% x CP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimated Gross Profit

A

(POC% x CP) - Cost Incurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

cumulative Realized Gross Profit

A

CP - Total Estimated Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

NOTES

A

Cumulative RGP if first year yun na yon agad. pero pag second year always deduct first yr. kung loss ang last yr magiging negative negative then positive lol algebra

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CIP

A
Cost Incurred
\+
_ G/L
\_\_\_\_\_\_\_\_\_\_\_\_\_\_
    CIP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EXPENSED OUTRIGHT

A

CP < Total Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly