Low Pressure Steam Boilers 2nd Yr Flashcards

0
Q

Which firetube boiler is built with a firebox that is not completely surrounded by water?

A

Firebox boiler

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

A boiler rated for hot water service at 120 psig (827kpa) and 240F (116C) maximum would be constructed under the rules of which code?

A

ASME section IV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which boiler consist of an arrangement of drums and headers interconnected by tubes?

A

Watertube

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How many fans are used to control the draft through a balanced draft boiler ?

A

2: one on the inlet and one on the outlet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which boiler would be classified as a firebox boiler

A

HRT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the minimum clearance required in front of a access panel on a gas-fired boiler?

A

24” regardless of whether it is insulated or not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the installer have to do with the boiler and piping system before turning them over to the owner?

A

Inspect and test for leak tight service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the cause of the most common problems encountered after start-up of steam boilers and systems?

A

Improper cleaning and flushing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is likely to occur if there is a heavy concentration of dissolved or suspended particles in the boiler water?

A

The water may foam and could cause foaming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should be done if the water in the sight glass is not clear after cleaning and flushing?

A

Repeat the cleaning procedure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What should be done with the results of all pertinent test results during the test , start and balance phases of a system start-up?

A

Record the results and have the results verified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Where is the appliance’s gross rating ?

A

Boiler nozzle outlet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where is the appliances’s net rating taken

A

Heat emissions units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the term pass in the boiler mean ?

A

The number of times the products of the combustion travel the length of the boiler

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the main advantage of steam over hydronic systems?

A

Speed of transmission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the usual maximum circulating speed of water for a low temperature hot water heating system?

A

4ft/sec

16
Q

What does load tracking refer to when discussing boilers

A

That ability of a boiler to respond to changes in steam or hot water demand

17
Q

Which boiler has the ability to respond to sudden demands for large volumes of steam for a short period of time ?

A

Firetube

18
Q

Which boiler has the ability to handle wide variations in load over a long period of time ?

A

Watertube

19
Q

Why is clean condensate considered to be ideal for feeding back into boiler ?

A

Condensate is essentially distilled water so it contains no dissolved solids n

20
Q

How often should a pop test be done on a safety valve house on an Lo steam heating boiler?

A

Annually

21
Q

What is the suggested method of determining whether water is flowing through a water feeder valve?

A

Listen with stethoscope

22
Q

What is the most probable cause of the water level in a gauge glass fluctuating rapidly ,?

A

Foaming or priming inside the boiler