Long term construction contracts Flashcards

1
Q

Two methods

A

Completed contract method

percentage of completion method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Completed contract method

A

US GAAP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Income reognition

A

When the contract is complete or substantially complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Substantially complete

A

contract is considered substanitally complete if remaining costs are insignificant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acceptable to use completed contract method when

A

1) Difficult to estimate costs of a contract in progress
2) there are many contracts in progress so that an equal amount are completed each year and unequal income is not recognized each year
3) projects are of short duration and the collections are not certain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Two accounts

A

Progress billings and construction in progress- represent the same contract asset and should be shown net of their related contra accounts; liability account is advances account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

progress billing or construction in progress

A

billing performed without billing actual time or expenses; put in the software even before work is performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Current Asset Accounts

A

a/r and cost of completed contracts in excess of progress billings that means you’ve performed more work than what youve billed the customer for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Current Liability Account

A

Progress billings on uncompleted contracts in excess of costs; bill more than what you’ve completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Measured

A

Completion= cost incurred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Applicable overhead and direct costs

A

should be charged to a construction in progress or an asset account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Billings and or cash received

A

should be credited to advances on construction in progress account or liability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Gross profit or loss

A

contract price- total costs; except loss recognize like complete
2 years in a row -> year 1 loss; year 2 remove loss from prev year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

at interim balance sheet dates

A

both the asset and the liability accounts are classified as current

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

conservatism

A

losses should be recognized in full in the year they are discovered; calculated by using the recorded costs to date + estimated costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Advantage

A

based on final results and not estimates

17
Q

Disadvantage

A

does not properly match the matching principle

18
Q

IFRS

A

this method cannot be used, if the final outcome of the project cannot be reliably estimated, the cost recovery method is used and revenue can only be recognized to the extent that cash collected exceeds the costs incurred

19
Q

Percentage of completion methods

A

Gaap and IFRS

20
Q

Income recognition

A

recognize income as work progresses on the contract

21
Q

Exception to the basic realization principle

A

based on the evidence that ultimate proceeds are available and the consensus that a better measure of periodic income results by the principle of matching revenue and costs

22
Q

Determination of revenues recognized

A

costs incurred TO DATE/total estimated costs

23
Q

Loss conservatism

A

provision for loss on the entire contract made when current estimates of a the total contract costs indicate a loss; loss recognized immediately in the year in which it is discovered. any prior year profit or loss must be adjusted for when calculating total estimated loss.

24
Q

Current Asset

A

A/R; costs and estimated earnings of uncompleted contracts is excess of progress billings or the bill

25
Q

Current Liability

A

Progress billings in excess of cost and estimated earnings on uncompleted contracts

26
Q

Advantage

A

Reflects matching principle

27
Q

Disadvantage

A

relying on estimates

28
Q

Journal entry

A

Debit construction in progress account and credit realized gross profit

29
Q

Calc

A

1) Est GP = Contract Price -Est Total Cost
2) % completion = (total cost to date/ total estimated cost of contract)
3) Gross profits earned till date = Step 1 * Step 2
4) Gross profit earned till date - gross profit bb = current year to date gp

30
Q

Problem on page 32**

A

When there is a loss (step 1 is negative) 100% of that amount is recognized; if you previoulst recognized 200 of loss and this year loss is 300 then only need to recognize an additional 100 in loss this year

31
Q

Problem on page 32***

A

completed contract- don’t recognize anything till either loss or complete the contract

Total GP:
If profit then %
that gives you total estimable costs - remove profits or losses from all previous years

if loss whole thing but then remove stuff from all previous years so if 200 loss this year and 600 profit prior year
then -200-600–> loss 800

32
Q

total est cost to complete

A

year 2 includes cost of year 1 + actual year 2 costs + est costs at yr 2