Long Term Construction contract Flashcards
Haft Construction Co. has consistently used the percentage-of-completion method. On January 10, Year 1, Haft began work on a $3,000,000 construction contract. At the inception date, the estimated cost of construction was $2,250,000. The following data relate to the progress of the contract:
Income recognized at 12/31/Year 1 $ 300,000
Costs incurred 1/10/ Year 1 through 12/31/Year 2 1,800,000
Estimated cost to complete at 12/31/Year 2 600,000
In its income statement for the year ended December 31, Year 2, what amount of gross profit should Haft report?
a.
$150,000
b.
$262,500
c.
$300,000
d.
$450,000
Contract price $ 3,000,000 Cost to date 1,800,000 Estimated cost to complete 600,000 Total cost $ 2,400,000 Expected gross profit 600,000 Percentage complete (18/24) 75% Profit to date 450,000 Profit previously recognized (300,000) Year 2 profit $ 150,000
A company used the percentage-of-completion method of accounting for a 5-year construction contract. Which of the following items will the company use to calculate the income recognized in the third year?
When a company uses the “percentage-of-completion” method of accounting for a five-year construction contract, income previously recognized would be used to calculate the income recognized in the second year (but not progress billings to date).
exmaple Year 2 Total contract sales price $ 4,000 Less total estimated cost of contract 3,200 Total gross profit 800 × % of completion × 75% Gross profit earned to date (cumulative) 600 Less income previously recognized 500 Income recognized in current year $ 100
A company uses the completed-contract method to account for a long-term construction contract under U.S. GAAP. Revenue is recognized when recorded progress billings:
- Are collected
- exceeds recorded cost
When a company uses the U.S. GAAP “completed contract” method to account for a long-term construction contract, revenue is recognized when the job is completed, not when progress billings are collected or when they exceed recorded costs.
When the “percentage of completion” method of recording revenue is used, engineering estimates of completion or “costs incurred to date” vs. “total estimated costs” is the basis for recognizing revenue, not progress billings.
Rule of conservatism
Recognizing anticipated loss on on both completed contract and %of completion method
the completed contract method and gross profit
under the completed contract method. Although Gross Profit is not recognized the project is completed, you have to check for potential loss (the cost incurred is higher the original contract price).
Gross profit calculation under the % of completion method.
1- calculate total gross profit
= contract price - estimated total cost
2= Calculate % of completion:
= cost incurred to date/(estimated total cost to complete the project)
The calculation of the income recognized in the third year of a five-year construction contract accounted for using the percentage-of-completion method includes the ratio of:
The formula to calculate the percentage of completion is:
Total cost to date/ Total estimated cost
How to find whether a current liability or current asset exists on a % of completion method
1- Calculate Gross profit on project
= Contract Price - total cost to complete the project
2- calculate ( actual cost on project to date + Gross profit to date) - Excess progress billing.
if the result is +, therefore it’s a current asset. If the result is -, therefore it’s a liability.