A developer usually needs to meet several milestones in a project to begin a construction draw from the bank.

Usually milestone would be pre-sale status (condo), equity contribution, partial building permit.

If there is an existing land loan, the first loan usually includes work done up to date and equity so that it pays off all previous loan on the land.

Typically a developer is required to (with the help from GC) fix at least 67% of the construction contracts.

A quantity surveyor reviews all plans, contracts, work up to date, permits, and issue a QS report for the bank to release funds.

A

FIRST LOAN DRAW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Loan draw conditions

A

DEVELOPMENT

MARKETING

OTHER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Development (Loan draw conditions)

A

PERMITS (STAGED BP)

ENVIRONMENTAL CLEARANCE

GEOTECHNICAL FULL REPORT

RELIANCE LETTERS ISSUED BY THE CONSULTANTS, ADDRESSED TO THE LENDER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Marketing (Loan draw conditions)

A

PRE-SALE TARGET ( PRE-SALE NEEDS TO COVER THE LOAN VALUE)

Ex. If the construction loan is $100M, the pre-sale value needs to cover at least $100M

PRE-SALE DEPOSIT TARGET (AGREED BY THE LENDER AND PRE-SALE INSURANCE COMPANY)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Other (Loan draw conditions)

A

SUFFICIENT EQUITY HAS BEEN CONTRIBUTED TO THE PROJECT

PROJECT TAXES PAID

PROJECT INSURANCE IN PLACE

QUANTITY SURVEYOR VERIFY ALL COSTS IN PLACE AND OR EQUITY IN PLACE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Pre-sale condo equity stack.

A

SOURCE OF FUNDS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Equity injected into the project.

A

LAND EQUITY

CONSULTANTS FEE

MARKETING AND FINANCING

CITY PERMIT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Other loan conditions

A

LENDER NEEDS TO COMPLETE THE KYC PROCESS (KNOW YOUR CLIENT)

LENDER ISSUE COMMITMENT LETTER

LENDER AND BORROWER’S LAWYERS COMPLETE LEGAL BACKGROUND SEARCH, REGISTRATION OF SECURITY DOCUMENT, EXPRESS LEGAL OPINIONS ON LEGAL OWNERSHIP, AND ALL REQUIRED DOCUMENT SIGNING PROCESS.

LENDER DRAFT CLOSING STATEMENT TO FINALIZE THE EXACT AMOUNT OF LOAN FUNDING

LENDER TYPICALLY NEEDS 3-5 DAYS TO SECURE FUNDS TO BE ADVANCED.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

KYC Process

A

BANK WILL PERFORM DUE DILIGENCE ON THE BORROWER’S BACKGROUND

GUARANTOR’S FINANCIAL STRENGTH WILL BE DETERMINED.

LEGAL ENTITY FORMATION, LEGAL AGREEMENT, TRUST DECLARATION, AND ALL OTHER AGREEMENT WILL BE REVIEWED.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Subsequent draw process

A

EACH MONTH, GC ISSUES ITS PROGRESS BILL TO A DEVELOPER. THE DEVELOPER RECORDS THE TOTAL INTO HARD COSTS. IT ALSO INCURS SOFT COSTS SUCH AS CONSULTANTS AND INTEREST.

THE DEVELOPER SENDS ALL DRAW INFORMATION AND BACKUP (INCLUDING INVOICES, COMMITMENT REPORT, BUDGET CHANGES) TO QUANTITY SURVEYOR.

QUANITY SURVEYOR VERIFIES THAT ALL COSTS ITEMS ARE WITHIN BUDGET, AS WELL ALL THE WORK HAS HAPPENED AND CAN BE VERIFIABLE.

QUANTITY SURVEYOR WOULD REQUEST AND RECOMMEND FUNDS FROM THE BANK.

BOTH THE GC AND THE DEVELOPER NEEDS TO SIGN STAT DEC TO REQUEST FUNDS, AND DECLARE THAT ALL PREVIOUSLY FUNDED AMOUNT HAS BEEN PAID TO TRADES.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Timing of loan draw

A

BEFORE 10TH OF THE MONTH - A DEVELOPER SENDS ITS DRAW REQUEST PACKAGE TO QUANTITY SURVEYOR.

BEFORE 15TH OF THE MONTH -THE QS WILL REVIEW AND ISSUE THE REPORT TO THE BANK.

AROUND 17TH OF THE MONTH - STAT DECS WILL BE SIGNED ON.

25-27TH - TYPICALLY BANK FUNDS AFTER RECEIVING THE REQUEST WITHIN 3 DAYS

31ST OF EACH MONTH - DEVELOPERS PAYS GC

31ST OR 1ST - GC RELEASES PAYMENTS TO TRADES AND SUBTRADES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Architect (Sign off plans and COP)

A

PROVIDE DRAWINGS AND COORDINATE ALL DRAWINGS SETS.

SIGN OFF ON COP PRIOR TO EACH DRAW.

PERFORM SITE VISITS AND SIGN OFF ON THE PROJECT PROGRESS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Appraiser

A

PROVIDE INITIAL LAND VALUE ASSESSMENT.

PROVIDE A TRANSMITTAL LETTER SO THAT BANKS CAN RELY ON THE REPORTS DIRECTLY.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Insurance broker

A

PROVIDE AN INSURANCE CERTIFICATE TO ENSURE THAT THERE IS SUFFICIENT INSURANCE PLACED ON THE PROJECT.

INCLUDE BANKS AS ADDITIONAL INSURED / FIRST MORTGAGE / AND LOSS PAYABLE TO PARTY.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Quantity Surveyor (QS)

A

HIRED BY THE LENDER AND IS TO VERIFY COSTS IN PLACE OF THE PROJECT ON BEHALF OF THE LENDER.

VERIFY BUDGET.

VERIFY EQUITY INJECTION IN THE PROJECT.

VERIFY PROGRESS ON THE PROJECT.

VERIFY COSTS HAVE BEEN PAID (SELECT INVOICES AND VERIFY PAYMENTS)

VERIFY COST OVERRUN AND INFORM THE LENDER.

VERIFY DEPOSIT IN TRUST.

VERIFY FUNDING AMOUNT AND PORTION FROM DEPOSIT AND CONSTRUCTION LOAN.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Loan draw process

A

AP ENTERS INVOICES INTO THE SYSTEM

PM APPROVES INVOICES

INVOICES ARE POSTED INTO THE SYSTEM AND JOB COST REPORTS ARE GENERATED.

PROJECT ACCOUNTANT PICKS UP THE JOB COST-TO-DATE NUMBERS AND ENTERS THEM INTO THE LOAN DRAW SPREADSHEET.

PROJECT ACCOUNTANT SUBMITS THE LOAN DRAW SCHEDULE, BACK UP INVOICES, THE ARCHITECT - ISSUED COP, STATUTORY DECLARATION, ARCHITECT REVIEW OF SITE PROGRESS, AND LOAN REQUEST FORMS TO QS.

QS ISSUES THE REPORT FOR REVIEW WITHIN ONE WEEK.

PROJECT ACCOUNTANT APPROVES THE QS DRAFT REPORT.

BANK RECEIVES THE FINAL REPORT.

BANK FUNDS THE LOAN DRAW.

MONEY IS USED TO PAY FOR TRADES’ INVOICES

17
Q

Example of milestone would be.

A

PRE-SALE STATUS (CONDO)

EQUITY CONTRIBUTION

PARTIAL BUILDING PERMIT