1
Q

State the system code for the primary circuit

A

M

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List the 3 containment boundaries

A
  1. Primary
  2. Intermediate
  3. Secondary
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the function of the steam generators?

A
  1. To produce high quality steam to power the MT’s, TG’s and the auxiliary steam system.
  2. Remove Decay heat (DH) from the reactor core.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the function of the auxiliary steam system?

A
  1. The auxiliary steam system supplies steam at 14 bar to:
    a. Main air ejectors
    b. Gland steam system
    c. Braby
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

State 2 components of the steam drain system

A
  1. Yarway steam trap
  2. Key trap
  3. Back pressure regulating valve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is there a separating wall between the ahead/astern sections of the MT?

A

To prevent steam leakage between them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the primary system code for the primary relief system?

A

R

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the functions of the main circulating water system?

A
  1. Provide cooling water to the main condenser so that optimum condenser vacuum and steam conditions can be maintained.
  2. Supply the after stern tube bearing with water for cooling and lubrication
  3. Provide a supply of water to the clean sea water system.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Describe the construction of the clean sea water system pump.

A

A glandless, canned centrifugal pp. It is mounted on it’s own side main condenser hotwell.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

list 4 items cooled by the ships FWD fresh water cooling system.

A
  1. CW plants
  2. 70KW MG sets
  3. 35KW MG sets
  4. 10KW MG sets
  5. H2 Burners
  6. R12 removal units
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does SLIV stand for and what does it do?

A

Surge line isolation vv it provides a means of isolating the pressuriser in the event of a pressure leak.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In what order do the primary relief valves reset?

A
  1. High
  2. Low
  3. Steam
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the function of the coolant treatment system?

A
  1. To remove fission products from the coolant in order to allow access to the reactor core after shutdown.
  2. Gives a connection to the sampling system before and after the ion exchange column.
  3. Ensures water discharged is at the lowest possible radioactive level.
  4. Removal of decay heat during LPDHR
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Where does HP discharge from the coolant discharge system go to?

A

MUD vessel overboard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the subsections of the coolant makeup system?

A
  1. Recirculation system (normal)
  2. Back up system (DE-OX/Demin system)
  3. Emergency system
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Components of the primary shield system?

A
  1. A steel tank surrounding the RPV which contains:
    i. RCFW cooling coils
    ii. Neutron detectors
    iii. Core catcher
    iiii. Test source track
  2. A shield water head tank with interconnecting piping and valves.
17
Q

2 methods of using the HPDHR system

A
  1. Forced high pressure decay heat removal (FHPDHR)

2. Natural high pressure decay heat removal (NHPDHR)

18
Q

State the system code for the coolant treatment system?

A

W