Lesson 5: Concealed and Structural Steel Systems

1
Q

When they are to be concealed, lightning conductors may be installed?.

Select one:

a. behind exterior wall facing
b. between wall studs
c. under roof framing
d. under roofing materials
e. all of the above

A

e. all of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If the lightning conductor is run in metal conduit, it must be bonded to the conduit at?.

Select one:

a. any point where the conduit is not electrically continuous
b. both ends
c. the center of the conduit
d. a. and b.
e. all of the above

A

d. a. and b

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In masonry chimneys, both strike termination devices and lightning conductors can be concealed within the chimney itself or attached to the exterior and routed through the structure to conceal main conductors.

Select one:

True

False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Lightning conductors and all other lightning protection components concealed in steel reinforced concrete must be connected to the reinforcing steel at?.

Select one:

a. the center
b. the lower extremities
c. the upper extremities
d. b. and c.
e. a., b., and c.

A

d. b. and c

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Long vertical reinforcing steel members must have additional connections to the lightning conductor at intervals not exceeding?.

Select one:

a. 50’
b. 75’
c. 100’
d. 200’

A

D 200’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Horizontal lightning conductor runs must be connected to the reinforcing steel at intervals not exceeding?.

Select one:

a. 50’
b. 75’
c. 100’
d. 200’

A

C 100’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Grounding electrodes for concealed systems follow the same rules as those for exposed systems.

Select one:

True

False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Grounding electrodes located under basement slabs or in crawl spaces need to be installed as close as possible to the outer perimeter of the structure.

Select one:

True

False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where ground rods are used for grounding electrodes, they must be in contact with the earth for a minimum of?and extend to a depth ofnot lessthan?below finished grade, except as permitted by the requirements for shallow soil.

Select one:

a. 4’ / 6’
b. 6’ / 8’
c. 8’ / 10’
d. 10’ / 12’

A

c. 8’ / 10’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The structural steel framework of a structure can be utilized as a main lightning conductor of the lightning protection system if?.

Select one:

a. it is electrically continuous
b. it is less than 30’ in length
c. it is made electrically continuous
d. a. or c.
e. a., b., or c.

A

d. a. or c.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Strike termination devices must be connected to the structural steel framing by?.

Select one:

a. direct connection
b. the use of an external lightning conductor that interconnects all strike termination devices
c. the use of individual conductors routed through the roof or parapet walls to the structural steel framework
d. any of the above

A

D all

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When the external lightning conductor is used, it must be connected to the structural steel at intervals not exceeding?.

Select one:

a. 50’
b. 75’
c. 100’
d. 150’

A

c. 100’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following isNOTa method to connect the lightning conductor to the structural steel?

Select one:

a. Brazing
b. Mechanically
c. Welding
d. None of the above

A

D none of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When making the connection for a lightning conductor mechanically, the steel must be cleaned down to the?.

Select one:

a. base metal
b. first layer of paint
c. primer
d. a. or c.

A

A base metal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When a bonding plate is used on a structural steel member, it must have a minimum surface area of at least?.

Select one:

a. 4 in2
b. 8 in2
c. 1 ft2
d. 2 ft2

A

b. 8 in2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Bonding plates must have bolt-pressure cable connectors and be?to the steel column.

Select one:

a. bolted
b. brazed
c. welded
d. b. or c.
e. a., b., or c.

A

e. a., b., or c.

17
Q

When rust-protective paint has been removed from the steel column, the base steel must be protected with a conductive corrosion-inhibiting coating.

Select one:

True

False

A

True

18
Q

Although allowed by UL and NFPA standards, drilling and tapping a steel column to install an air terminal is not a good idea since it makes it very difficult to replace the air terminal if it breaks.

Select one:

True

False

A

True

19
Q

If the drilling and tapping method into a steel column is employed, the air terminal must have at least?one-half-inch threads fully engaged and secured with a jam nut.

Select one:

a. 3
b. 4
c. 5
d. 6

A

C. 5

20
Q

When structural steel is used as the lightning down conductor, grounding electrodes must be connected to approximately every other steel column around the perimeter of the structure at intervals averaging not more than?.

Select one:

a. 40’
b. 50’
c. 60’
d. 80’

A

C 60’

21
Q

When structural steel is used as the lightning down conductor, grounding electrodes must be connected near the base of the column.

Select one:

True

False

A

True