Liens Flashcards

1
Q

Vendor’s Lien

A

A lien in favor of a seller of real property to secure payment of the unpaid portion of the purchase price of the property

The usual practice in Tx is to expressly reserve a vendor’s lien in the deed to the purchaser so that when the deed is recorded, third parties will have notice of the lien

The effect of the vendor’s lien is to reserve “superior title” to the property in the seller until such a time as the remainder of the purchase price is paid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

*IRS Fed Tax Liens

A

Fed tax liens have priority over other liens on a taxpayer’s property only if the IRS lien was recorded first

In the non-judicial foreclosure proceeding of a lien w/ priority to the IRS lien, the Sec. of Treasury may redeem the property w/in 120 days from the date of sale

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Vendor’s Lien is Fully Assignable

A

A vendor’s lien is fully assignable in Tx. Therefore, whenever a purchaser obtains a conventional loan from a person or entity other than the seller, the deed will often transfer and assign the vendor’s lien to the 3P lender to further secure the obligation to it

Vendor’s lien is in addition to, not in place of, deed of trust lien

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Vendor’s Lien Implied by Operation of Law

A

A vendor’s lien is implied by operation of law where it is not reserved in the deed but the purchase price is not fully paid at the time of closing

However, there is no retention of “superior title” to the seller if the lien is not expressly reserved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Constitutional Mechanics’ Liens

A

Art. XVI, Sec. 37 of Tx Const. created broad, non-statutory lien protection for mechanics, artisans, and materialmen who have a direct contractual relationship w/ the owner of the property being improved or repaired

For a claimant who has provided services or materials to be entitled to a constitutional lien, Tx courts generally have required the following:

For a claimant who has provided services or materials to be entitled to a constitutional lien, Tx courts generally have required the following:

(i) Debtor owns the building or article;
(ii) Materialman was in privity of K w/ the debtor;
(iii) Materialman made or repaired the building or article by:
a. supplying goods & constructing all or part of it
b. supplying goods & repairing it
c. supplying unique goods manufactured in accordance w/ the debtor’s specifications, or
d. furnishing off-the-shelf general inventory goods w/ the intent that they be incorporated into it;
(iv) Materialman actually supplied those goods to the debtor; and
(v) Good were incorporated into the building or article

Constitutional provision relating to liens is self-executing and automatic and exists independently and apart from any legislative act. This automatic protection obviates any need for the claimant in privity w/ the owner to comply w/ any statutory notice or filing requirements relating to the lien

The constitutional lien is ineffective against subsequent bona fide good faith purchasers for value w/o notice. It is superior to a prior recorded deed of trust lien on the improvements and materials for which the mechanic’s lien exists if the materials supplied can be removed w/o material injury to the property or materials

Neither a constitutional nor a statutory mechanic’s lien may be enforced against a HOMESTEAD unless a written K for the work and materials to be supplied is signed by all owners prior to the work commencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

*Statutory Mechanics’ Liens

A

Contractors, subcontractors, craftsmen, artisans, and suppliers of materials for use in construction of improvements on real property may obtain security for credit extended by perfecting liens that are provided by statute in Tx (MMLs)

The statutory schemes for creation and perfection of these types of liens must be followed strictly. Additionally, if the liens are on property claimed as a homestead, the rules of compliance are even more complex.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When is a perfected MML effective?

A

A perfected MML is effective as of the date when visible construction or delivery of materials begins. This relation-back provision fixes the protections and obligations of the lien statutes in general as having arisen on the inception date and takes priority over any subsequent transfer of interest by the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Perfecting MML: Need Affidavit of MML + Notice (see below)

A

A person claiming a statutory MML must file a signed affidavit w/ the clerk of the county in which the property is located no later than the 15th day of the fourth calendar month (or third calendar month for residential projects) after the day on which the indebtedness accrues

Determining when the indebtedness accrues depends on the type of claimant and type of material furnished

A copy of the affidavit must be sent by contractor no later than 5 business days after the date the affidavit is filed w/ the county clerk

Affidavit must contain:

(i) sworn statement of the amount of claim
(ii) the names and addresses of the owner, original contractor, claimant, and claimant’s employer
(iii) a general statement of the kind of work done and materials furnished
(iv) a legal description of the property sought to be charged w/ the lien
(v) if the claimant is not the original contractor, the affidavit must also identify each month in which the work was done and materials were furnished
(vi) the date and method by which each notice of the claim was sent to the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

*Notice of Claim for MML

A

A derivative claimant (i.e., a subcontractor) must then give the notice prescribed by statute for the lien to be valid.

Generally, notice must be given no later than the 15th day of the second and third months following each month in which all or part of the claimant’s labor was performed or material was delivered

For RESIDENTIAL projects, however, the second notice is not required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

*Source of Funds for MML

A

(1) Fund Trapping

(2) Statutory Retainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

*Fund trapping

A

Fund trapping allows a subcontractor to trap, in the owner’s hands, funds payable to the general contractor if the owner receives notice from the subcontractor that it is not being paid. Unless payment of the claim is made on demand or the claim is otherwise settled, discharged, or determined to be invalid, the owner must retain the withheld funds until:

a. the time for the filing of the affidavit of MML has passed, or
b. if a lien affidavit has been filed, until the lien claim has been satisfied or released

If the owner never pays any money to the original contractor after receiving notice from the subcontractor, the owner’s property is subject to a lien to the extent of the money paid.

A subcontractor may make written demand for payment out of trapped funds. The subcontractor must send a copy of the demand to the original contractor, who has 30 days to provide the owner w/ written notice that it intends to dispute the claim. If the original contractor does not give the owner timely notice, it is considered to have assented to the demand, and the owner must pay the claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

*Statutory Retainage

A

Regardless of notice of a claim, the owner of property must retain during the progress of the work and for 30 days after the work is completed either:

(i) 10% of K price of the work to the owner, or
(ii) 10% of the value of the work, measured by the proportion of work done to the work to be done, using the K price or, if none, the reasonable value of the completed work

The owner’s failure to hold back the statutory retainage may result in lien exposure at least to the extent of the amount that should have been retained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

*Preferences and Priorities of MML

A

All subcontractors, laborers, and materialmen who have a MML have preference over other creditors of the original contractor. This is b/c the materialman has contributed to the improvement and additional value of the real property.

Generally, perfected MMLs are on equal footing w/o reference to the date of filing the affidavit of lien. Thus, if proceeds of a foreclosure sale are insufficient to discharge all MMLs against the property, the proceeds are paid pro rata.

Exceptions = w/ respect to other MMLs, the priority of a lien claimed by an architect, engineer, surveyor, landscaper, or one who provides demolition services is determined by the date the affidavit is recorded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Foreclosure of MML

A

A MML may be foreclosed on on j/m of a court

District courts have exclusive jurisdiction over suits to enforce and foreclose MML

For non-residential construction, a suit to foreclose a MML must be filed w/in 2 years after filing the lien affidavit or w/in a year of completion, termination, or abandonment of the work under the original K, whichever is later

However, when there is direct privity of K b/w the owner and contractor, a suit for debt can still be filed w/o consideration of any claim under a lien

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Construction Payments as Trust Funds

A

Under the statute, payments made to a contractor or subcontractor under a construction K for the improvement of real property are “trust funds.”

No proof of creation of a trust is necessary. The funds are held by the recipients for the benefit of the contractor or subcontractor w/o regard to whether it has complied w/ the procedural requirements for creating and perfecting MMLs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Seniority of Liens

A

Tx statutes have established several exceptions to the CL rules of priority (e.g., recording statutes and MML statutes), which have caused certain liens that were created first in time to be inferior to subsequently created liens

17
Q

Rights and Remedies - Mortgage or Deed of Trust

A

A power of sale provision in a deed of trust or mortgage gives the trustee the right to sell the property w/o resorting to court action if the debtor fails to remedy a default. This power emanates from the instrument itself.

18
Q

Sale Under a Power of Sale (Non-judicial foreclosure sale)

These require STRICT compliance bc it is a harsh remedy, or else the sale is invalid.

A

Under the Texas Property Code, the Trustee must:

(i) give the parties 21 days notice of default before the nonjudicial foreclosure sale to cure. If the property is a residence, the parties must be given an additional 20 days to be able to cure the default.

(2) if default is not cured, then
notice of the non-judicial foreclosure sale must give at 21 days in advance. The notice must be posted at
the courthouse in the county where the property is located, filed with the clerk of the county, and posted
on the county clerk’s website if possible. The notice must state the when and where the sale is to be
conducted and the earliest time at which it can be conducted.

(2) The sale must take place on the first Tuesday of the month; if that Tuesday is a January 1 or July 4, the sale will take place on the first Wednesday of the month.
(3) The sale must take place between 10am to 4pm.

(4) The sale must take place at the country courthouse in which the real property
resides (if try to sell two pieces of property in different county, not valid bc this wouldn’t be met)

Compliance w/ these statutory requirements, as well as those contained in the deed of trust, is a pre-req to the right of the trustee to make a sale.

19
Q

*Property Sold “As Is”

A

A purchaser at a foreclosure sale takes the property as is. No express or implied warranties are included

e.g. if the property is encumbered with a federal tax lien, then the new buyer is responsible for the tax lien since it is bought “as-is”

20
Q

No Self-Help Repossession

A

Tx law does not recognize self-help repossession of real estate. Non-judicial foreclosure transfer title to the property to the purchaser at the foreclosure sale but does not deliver possession. If the debtor remains on the property, the new owner must ordinarily file a forcible detainer suit to remove the debtor

21
Q

Vendor’s Lien Remedies

A

Under an express vendor’s lien, the seller has an election of remedies on the buyer’s default:

(i) sue for the balance of the purchase money and foreclose the lien
(ii) rescind the K and take possession
(iii) sue to recover title and possession

If the seller takes a deed of trust from the purchaser in addition to the vendor’s lien, he will have the additional remedy of non-judicial foreclosure under the power of sale.

If the vendor’s lien is implied, the seller cannot rescind the sales K and recover the land. His only remedy is to sue for foreclosure

22
Q

Other Liens

A

After default and any necessary acceleration of the debt, a secured creditor may judicially foreclose on the real property. This means filing a lawsuit to obtain a j/m foreclosing the debtor’s interest in the property.

A secured creditor of any type may abandon teh security interest and sue on the underlying debt instead

23
Q

Limitations Period for Enforcement of Liens

A

4-year SoL

Tx CL tolls the applicable SoL during the period of an automatic stay, and the Bankruptcy Code does not preempt this rule

24
Q
  • Perfecting Mechanics and Materialmen’s lien:

Notice of Affidavit

A

person claiming statutory MML must file a signed affidavit with the clerk of the county in which the property is located no later than the 15th day of the 4th calendar month (or 3rd calendar month if residential) after the date on which the indebtedness accrued.

Determining when the indebtedness accrues depends on the type of claimant and type of material furnished (e.g. indebtedness to a subcontractor accrues on the last day of the last month in which the subcontractor performed labor or furnished materials.

If materialman is a subcontractor, Copy of the affidavit must be sent by mail to owner and the original contractor no later than 5 business days after the date of the affidavit is filed with the county clerk.

25
Q

Deed of Trust

A

Creates mortgage liens in Tx.

Lender gives borrower money.

Borrower gives lender promissory note (promise to pay)

Borrower gives property to third party (trustee)

26
Q

*Is party that acquires real property by foreclosure sale required to complete and give Buyer a Seller’s Disclosure of Property Condition.

A

In Texas, a seller must provide a seller’s
disclosure of property condition before the buyer and seller enter into a contract for sale. The seller
must accurately fill out the form and fill it out in good faith.

However, a bank may sell a foreclosed house
“as is”, and thus the bank does not have to fill out and provide a seller’s disclosure.

27
Q

*Types of Deeds

A

General warranty deeds come with both present and future covenants.

Special warranty deeds come with present covenants, but no future covenants (e.g. no encumbrances)

A quitclaim deed comes with no covenants, however. A quitclaim deed effectively says “whatever interest I have in the property is now yours.”

  • can only convey what you have
28
Q

*To have an enforceable lien, what must the lien holder do?

A

In Texas, in order to have a valid lien on property, the lien holder must file the lien in the county where property is held to give others notice of the lien.

If the deed of the conveyance to the person who is mortgaging the property has not been recorded and the lien holder then records their security interest, the lien is considered “wild” because a person searching the county’s grantee-grantor index would not be able to tell what property to which the lien attached by performing a
regular title search.