Level 3 - Programming and Planning Flashcards
N 1. What is PERT?
Programme, Evaluation, and Review Technique
You create three estimates for the duration of a project,
- The most Optimistic (Shortest)
- The most pessimistic (Longest)
- The most likely (an average of the two)
N 2. What is a Project Programme?
A sequence in which tasks must be carried out to ensure a project can be completed on time.
N 3. What can be identified from the project programme?
- The overall Start Date.
- The overall Completion Date.
- The start date for each activity.
- The completion date of each activity.
- The amount of ‘Float’ each activity has.
- The Critical Path.
- Tasks which can only be carried out sequentially.
- Tasks which can be carried out simultaneously.
N 4. What should a programme help you do?
- Plan Activities.
- Monitor progress.
- Manage Resources.
N 5. What types of Programme are there?
- Contractors Master Programme.
- Clients Overall Programme.
- Design Programme.
- Information Release Schedule.
N 6. What goes into the Clients Overall Programme?
- Everything, from the appointment of the consultant, through to the completion of the project.
- This will include work outside the scope of the main-contractor.
N 7. What goes into the design Programme?
• It describes the sequence of design tasks, i.e. from the process of design from inception through the Technical Design.
N 8. What goes into an information release schedule?
- The dates by which information needs to be released by the design team, to avoid any delays.
- This works both ways, for example when the contractor has a Contactors Design Portion.
N 9. What goes into the Contractors Master Programme?
• The schedule and sequence of construction activities.
N 10. Can you employ a consultant to produce a programme?
• Yes, on large projects they can prepare the outline programme.
N 11. What should you consider when preparing a programme?
- Items with a long lead-in.
- Pre-contract works.
- Pre-fabrication elements.
- Works outside of the main contract.
- Relationships with other projects.
- Phasing and Sectional Completion.
- CDM Planning Period.
N 12. What is the CDM planning period?
• An amount of time given to the contractor, with the intention of allowing contractors to assess Health and Safety issues and plan their works before construction commences.
N 13. How long is the CDM planning period?
• Not specified, it should be proportional to the size and complexity of the project and the risk.
N 14. What is a Flow diagram?
• A Graphical representation of a process of steps/sequences required to achieve an end goal.
N 15. What is the benefit of using a Flow Diagram?
• It helps the team to understand the different processes and relationships between activities.
N 16. What is an Activity Schedule?
• A list of activities which outlines the works required to complete a project/package etc.
N 17. What type of contract uses an Activity Schedule?
• A simple project with few activities.
N 18. What type of contract uses an Activity Schedule?
• New Engineering Contracts, Engineering and Construction Contract Options A and C.
N 19. How is an activity schedule represented graphically on a programme?
- Typically using a Gantt chart.
- Each activity gets a bar.
- With a separate bar for preliminaries.
N 20. What should a PM do when receiving a contractors programme?
• Check that it is not front loaded.
- Check the activity timescales are reasonable and realistic